Adjusting Kosy's scandalous project in Bac Ninh

Vân Trường |

Bac Ninh - The Provincial People's Committee has just issued a decision approving the adjustment and supplementation of the investment policy content of the Kosy new urban area project, Bac Giang ward.

According to the decision, the content of adjustment and supplementation is as follows:

Adjust the project implementation schedule until the end of June 2026: Complete all obstacles and shortcomings of the project and organize construction, renovation of degraded items, acceptance and handover of works for use.

Supplementing the time when individuals receiving land use rights transfer in the form of subdivision and sale of land plots must complete the construction of houses in the project: no more than 10 years from the time the competent state agency certified that the land has infrastructure meeting the conditions for transfer.

According to the reporter's investigation, in December 2025, Vice Chairman of Bac Ninh Provincial People's Committee Pham Van Thinh had a working session to resolve difficulties and obstacles at the Kosy new urban area project, Bac Giang ward, Bac Ninh province.

It is known that in Bac Giang province (old), now Bac Ninh province, in addition to the above project, Kosy Joint Stock Company also implements the Cau Go town new residential area project, Yen The district (now Yen The commune).

At the 22nd session of the Bac Giang Provincial People's Council (old) taking place from November 10 - 12, 2024, delegate Tran Thi Vuong - Delegation of the Yen The District Provincial People's Council - stated that 2 projects implemented by Kosy Joint Stock Company in Bac Giang caused public outrage.

The new residential area project in Cau Go town, by that time, there were still 88 land plots that people had signed deposit contracts with the company from previous years, and land had not been allocated. The Kosy new urban area project is also behind schedule.

Answering the content of the delegates' questions, the leader of the Department of Planning and Investment of Bac Giang province (old) said that the project progress was slow due to problems in site clearance, but the main reason is that the investor did not actively carry out procedures in investment and construction. The responsibility belongs to Kosy Joint Stock Company.

Vân Trường
RELATED NEWS

Supporting 14.6 billion VND to organize many famous festivals in Bac Ninh

|

Bac Ninh - Locality supports 13 communes and wards with 14.6 billion VND to organize festivals in 2026.

More industrial parks worth more than 1,700 billion VND in Bac Ninh

|

Bac Ninh - Xuan Cam - Huong Lam Industrial Park, phase 2, scale of more than 121 ha invested by Xuan Cau Holdings.

Progress of Logistics Center project 4. 200 billion VND in Bac Ninh

|

Bac Ninh - In 2026, the investor of the International Logistics Center is expected to complete and accept phase 1 items.

Removing obstacles for Kosy's notorious urban area project in Bac Ninh

|

Bac Ninh - Vice Chairman of the Provincial People's Committee Pham Van Thinh has just organized a working session to resolve difficulties and problems in the Kosy new urban area project.

President Donald Trump breaks record for longest State of the Union address

|

President Donald Trump spoke for more than 90 minutes in the State of the Union Address on the evening of February 24, local time (morning of February 25, Hanoi time).

US issues 10-day ultimatum threatening to attack Iran

|

The US is conducting its largest military deployment to the Middle East since 2003, aiming to increase maximum pressure on Iran ahead of nuclear talks.

Thoroughly prevent offensive foreign cultural products in cyberspace

|

The Standing Deputy Prime Minister clearly stated the need to thoroughly prevent offensive foreign cultural products in cyberspace.

F-16 fighter jet crashes in Turkey, pilot killed

|

A Turkish Air Force F-16 fighter jet crashed during a training flight in western Turkey early in the morning, killing the pilot.

Supporting 14.6 billion VND to organize many famous festivals in Bac Ninh

Vân Trường |

Bac Ninh - Locality supports 13 communes and wards with 14.6 billion VND to organize festivals in 2026.

More industrial parks worth more than 1,700 billion VND in Bac Ninh

Vân Trường |

Bac Ninh - Xuan Cam - Huong Lam Industrial Park, phase 2, scale of more than 121 ha invested by Xuan Cau Holdings.

Progress of Logistics Center project 4. 200 billion VND in Bac Ninh

Vân Trường |

Bac Ninh - In 2026, the investor of the International Logistics Center is expected to complete and accept phase 1 items.

Removing obstacles for Kosy's notorious urban area project in Bac Ninh

Vân Trường |

Bac Ninh - Vice Chairman of the Provincial People's Committee Pham Van Thinh has just organized a working session to resolve difficulties and problems in the Kosy new urban area project.

Yêu cầu Kosy giải quyết các kiến nghị tại dự án ở Bắc Ninh

Trần Tuấn |

Bắc Ninh - UBND tỉnh yêu cầu công ty Kosy giải quyết các kiến nghị của khách hàng đối với dự án đang triển khai trên địa bàn tỉnh.