EVN focuses on building a 500kV line, to be completed before September 2, 2025

Tuyết Lan |

On March 3, EVN, Power Project Management Board 1 held a ceremony to launch the construction of the 500KV Lao Cai - Vinh Yen transmission line, the section passing through Yen Bai province.

Speaking at the Construction Implementation Ceremony, Deputy General Director of Vietnam Electricity Group (EVN) - Mr. Pham Hong Phuong said that during the investment preparation and project implementation, EVN has received the attention and close direction of the Government, the Prime Minister, the Ministry of Industry and Trade... and the joint efforts and consensus of the people in the Project area to speed up the progress of compensation, support and resettlement.

Pho Tong giam doc Tap doan Dien luc Viet Nam (EVN) ong Pham Hong Phuong. Anh: Tuyet Lan
Deputy General Director of Vietnam Electricity Group (EVN) Mr. Pham Hong Phuong spoke at the ceremony. Photo: Tuyet Lan

Mr. Pham Hong Phuong respectfully requested the leaders of the Provincial Party Committee, the Provincial People's Committee, leaders of Departments and branches of Yen Bai province; leaders of districts and localities in the project area to continue to pay attention and direct the implementation of compensation, support, resettlement work, and soon complete it.

Hand over the entire site of the pole foundation and corridor for the Investor to organize the synchronous and simultaneous implementation of the electric pole foundation locations along the entire route to meet the progress of the project.

"Vietnam Electricity Group assigned the task to the Power Power Project Management Board 1 and contractors to manage the project, organize construction to ensure compliance with requirements on quality, environment, focus resources and equipment to speed up progress, strive to complete the project according to the set plan" - Mr. Pham Hong Phuong said.

In order for the project to be invested in accordance with regulations, achieve high quality, complete on schedule and promote investment efficiency, at the groundbreaking ceremony, Vice Chairman of Yen Bai Provincial People's Committee Mr. Ngo Hanh Phuc requested - units related to the project implementation to focus and strive to perform well a number of tasks.

Pho Chu tich UBND tinh Yen Bai ong Ngo Hanh Phuc yeu cau - cac don vi lien quan den viec trien khai du an tap trung, no luc thuc hien tot mot so nhiem vu. Anh: Tuyet Lan
Vice Chairman of Yen Bai Provincial People's Committee Mr. Ngo Hanh Phuc requested - units involved in project implementation to focus and strive to perform well a number of tasks. Photo: Tuyet Lan

"Firstly, the Investor, Power Project Management Board 1 and related contractors and units must strictly comply with the construction procedures and technical regulations, ensuring the highest progress and quality... Strive to complete the project before September 2, 2025.

Second, the Party Committee, government, organizations of Luc Yen, Yen Binh districts and communes and towns within the scope of project implementation need to focus on implementing well, maintaining the tradition of being a bright spot, the leading flag in site clearance.

Third, relevant departments, branches and sectors of the province need to perform well the function of State management, be responsible for inspecting and closely supervising the project implementation process.

Fourth, organizations and individuals within the project scope, especially 65 households and organizations with land and assets on the land that have been collected and cleared, must promptly hand over the site to serve the construction organization according to the approved schedule" - Mr. Ngo Hanh Phuc requested emphasizing.

Speaking with Lao Dong, Mr. Chu Hoang Tung - Chairman of the Board of Directors of Ngai Cau Construction and Trading Investment Joint Stock Company, said that for the package in the 500 kV Lao Cai - Vinh Yen transmission line project, the company is ready in all aspects to ensure the project is on schedule and of good quality.

The company will participate in implementing 17 pole locations and about 2,000 tons of steel columns for this project. We are committed to making every effort to complete the project ahead of schedule, based on the team's experience and high determination. The company will closely coordinate with departments and partners to achieve the highest goal" - Mr. Tung said.

The 500kV Lao Cai - Vinh Yen Power Line project has a total length of 229.5km, with a total of 468 electric pole foundation locations. The total investment of the Project of more than VND 7,410 billion is arranged from the loan capital of the Joint Stock Commercial Bank for Foreign Trade of Vietnam (Vietcombank) of 80%, and EVN's counterpart capital is 20% of the total investment (before tax).

The section passing through Yen Bai province is 90.06 km long, with 173 locations for electric pole foundations (from VT102 to VT274), passing through 2 districts, Luc Yen and Yen Binh.

Tuyết Lan
TIN LIÊN QUAN

The last Tet under the 500kV power line corridor

|

This will be the last Tet holiday for many families in Lao Cai because they have to move their houses because they are located under the corridor of the 500kV Lao Cai - Vinh Yen power line.

Before G hour, construction of 500kV Lao Cai - Vinh Yen transmission line started

|

The 500kV Lao Cai - Vinh Yen transmission line project will start construction in February this year and be completed before September 2.

500kV line circuit 3 - symbol of determination and solidarity

|

On December 8, Politburo member and Prime Minister Pham Minh Chinh attended the conference to review the 500kV line 3. The 500kV line 3, completed after more than 6 months of rapid progress, is a vivid testament to the strength of solidarity, strong will and aspiration to rise of the nation.

Audiences mention Tu Long after Hoa Minzy's MV Bac Bling

|

A series of artists were mentioned when Hoa Minzy released a new MV in her hometown of Bac Ninh.

Ukrainian President Zelensky declares he will not be easily replaced

|

Ukrainian President Volodymyr Zelensky has said that replacing him at this time is not simple, but he is ready to resign on one condition.

The Ministry of Home Affairs proposes to review the quantity and quality of commune civil servants

|

The Ministry of Home Affairs requests the People's Committees of provinces and centrally run cities to review the quantity and quality of commune-level cadres and civil servants as of December 31, 2024.

Controversy giacks over attack on Russia- Europe gas pipeline

|

Hungary has warned that if the Russia-China gas pipeline TurkStream is disabled, it will seriously affect the country's energy security.

EU country says Ukraine wants conflict to continue

|

Hungarian Foreign Minister Peter Szijjarto said that the meeting between Mr. Trump and Mr. Zelensky exposed the stance on finding a solution to the Ukrainian conflict.

The last Tet under the 500kV power line corridor

NHÓM PV |

This will be the last Tet holiday for many families in Lao Cai because they have to move their houses because they are located under the corridor of the 500kV Lao Cai - Vinh Yen power line.

Before G hour, construction of 500kV Lao Cai - Vinh Yen transmission line started

NHÓM PV |

The 500kV Lao Cai - Vinh Yen transmission line project will start construction in February this year and be completed before September 2.

500kV line circuit 3 - symbol of determination and solidarity

Cường Ngô |

On December 8, Politburo member and Prime Minister Pham Minh Chinh attended the conference to review the 500kV line 3. The 500kV line 3, completed after more than 6 months of rapid progress, is a vivid testament to the strength of solidarity, strong will and aspiration to rise of the nation.