Prime Minister attends conference to review 500kV line circuit 3

Cường Ngô |

On the morning of December 8, the Prime Minister attended the conference to summarize the 500kV line circuit 3. The project was inaugurated on August 29, 2024 after more than 6 months of rapid construction.

The project is a miracle of the electricity industry.

The 500kV circuit 3 transmission line project was assigned by Vietnam Electricity Group (EVN) to the National Power Transmission Corporation (EVNNPT) as the investor, with a total length of 519 km, 1,177 pole locations, passing through 211 communes/wards of 43 districts in 9 provinces with a total investment of more than 22,300 billion VND.

EVNNPT leaders said that these are power transmission projects that play a particularly important role in increasing the stable reserve on the North - Central interface, supplementing capacity from the North Central region to the Northern region, reducing the load on existing 500kV lines to ensure the N-1 criteria.

Thu tuong Pham Minh Chinh (ngoai cung ben trai), Bo truong Nguyen Hong Dien va cac dai bieu tham du. Anh: Can Dung
Prime Minister Pham Minh Chinh (far left), Minister of Industry and Trade Nguyen Hong Dien and delegates attending the conference to review the 500kV line circuit 3. Photo: Can Dung

Under the strong direction of the Prime Minister, the Government, the attention and support of ministries, localities and people, EVN/EVNNPT has made efforts to complete the construction and energize according to the assigned schedule after more than 6 months.

According to EVNNPT leaders, the first thing to mention is the investment preparation work when after only nearly 5 months from the time of the decision to implement, the projects were approved by the Prime Minister for investment policy, investment policy adjustment along with forest use conversion. This is a record short time, while projects of similar scale take 2-3 years.

Chu tich Hoi dong thanh vien Tap doan Dien luc Viet Nam (EVN) Dang Hoang An bao cao tai Hoi nghi. Anh: Can Dung
Chairman of the Board of Members of Vietnam Electricity Group (EVN) Dang Hoang An reports at the Conference. Photo: Can Dung

In the contractor selection process, the projects had a total of 226 packages. EVNNPT and the Project Management Boards mobilized all specialized personnel, organized centralized bidding, worked day and night, without days off. As a result, the project was completed in about 60 days.

With the direction of the Prime Minister, the participation of the entire political system with the motto "4 on-site", "3 shifts, 4 crews" construction, "overcoming the sun, overcoming the rain", "only working, not working backwards", "working through holidays, Tet, and days off"... after just over 6 months of construction, the 500 kV line project, circuit 3, Quang Trach - Pho Noi has reached the finish line and created a "miracle" for the electricity industry; many great lessons have been learned from this particularly important project, inspiring and motivating the following projects.

Launching the emulation movement of 3 pioneers, 2 responsibilities

At the conference, on behalf of the leaders of the Vietnam General Confederation of Labor and EVN Group, Mr. Nguyen Dinh Khang - Member of the Party Central Committee, President of the Vietnam General Confederation of Labor officially launched the emulation movement among union members, civil servants, and employees to accelerate the investment and construction progress of EVN's key projects in 2025, with the emulation theme "three pioneers, two responsibilities".

Ong Nguyen Dinh Khang - Uy vien Trung uong Dang, Chu tich Tong Lien doan Lao dong Viet Nam (thu 3 tu trai sang) du hoi nghi. Anh: Duong Giang/TTXVN
Mr. Nguyen Dinh Khang - Member of the Party Central Committee, President of the Vietnam General Confederation of Labor (3rd from left) - attended the conference. Photo: Duong Giang/VNA

Three pioneers include pioneering in infrastructure, pioneering in completing progress, pioneering in overcoming difficulties; two responsibilities include responsibility for ensuring quality; responsibility for saving and fighting waste.

According to the President of the Vietnam General Confederation of Labor, for union members, cadres, engineers, and workers in units and enterprises that directly manage, supervise, organize construction and serve on projects and construction sites.

Compete in innovation, improve the efficiency of project management, rationally use human resources, labor efficiency, labor time, promote the capacity and strengths of the team of engineers and workers on projects and works;

Compete to apply science, technology, and management solutions to improve the efficiency of using equipment, means, and labor and production tools; save materials, reduce costs, and construction prices;

Compete to promote initiatives, improve techniques, enhance on-site training to improve skills and expertise, contributing to improving labor productivity for workers directly at construction sites;

Compete to implement solutions to ensure good implementation of technical construction requirements, build a safe working environment, and minimize risks in construction;

Strive to overcome all difficulties and challenges, arrange production and working hours to suit weather conditions;

Compete to save money and fight waste at construction sites and regularly inspect and supervise the practice of saving money and fighting waste during construction.

Chu tich Tong Lien doan Lao dong Viet Nam Nguyen Dinh Khang phat bieu tai hoi nghi. Anh: Anh Tuan
Party Central Committee member, President of the Vietnam General Confederation of Labor Nguyen Dinh Khang speaks at the conference. Photo: Anh Tuan

For union members, cadres, civil servants and public employees in local State management agencies related to key projects and works of the electricity sector, it is necessary to compete to improve the quality and effectiveness of management work, advisory work on contents related to mechanisms, policies, regulations on site clearance procedures, design work, appraisal, approval, supervision, inspection and payment settlement for works.

Compete to reform administrative procedures, create all favorable conditions for contractors to participate in the implementation of projects; speed up the submission and approval of documents related to the implementation of projects, especially in site clearance in localities with electricity projects.

Emulate the practice of thrift and anti-waste in the management and use of state capital and assets; publicly and transparently disclose information on new mechanisms and regulations related to the implementation of works and projects.

Compete to effectively implement the campaign "Cadres, civil servants and public employees say no to negativity" launched by the Vietnam General Confederation of Labor.

"We together show our highest determination to the Prime Minister - Chairman of the Central Emulation and Commendation Council, competing to speed up the investment and construction progress of EVN's key projects in 2025.

The Vietnam General Confederation of Labor will select outstanding projects and works to be awarded the General Confederation's plaque to welcome Party Congresses at all levels, Patriotic Emulation Congresses, and to welcome major national holidays and events of the Vietnam Trade Union in 2025," said Chairman Nguyen Dinh Khang.

Cường Ngô
TIN LIÊN QUAN

500kV line circuit 3 and the miracle of speed, economy and efficiency

|

In the article "Fighting waste", General Secretary and President To Lam emphasized the need to summarize and replicate the experience of implementing the 500kV line 3 project for key and important national public investment projects and works.

Weather forecast for the next 10 days from December 12 to December 21 in all three regions

|

The National Center for Hydro-Meteorological Forecasting forecasts the weather for the next 10 days (from the night of December 11 to December 21) in regions across the country.

Update on the closing price of gold on December 11: The upward trend continues

|

Updated gold price closing session 11.12 continues to increase. World gold is receiving many supporting factors.

Investigation into the death of an 8th grade student in the schoolyard in Hai Phong

|

Hai Phong - On the evening of December 11, a representative of the People's Committee of Thuy Nguyen district (Hai Phong) said that the police are investigating the death of an 8th grade female student.

Keeping the Zoo in Ho Chi Minh City Open

|

Ho Chi Minh City - Saigon Zoo and Botanical Garden - childhood memories of many generations. In the face of tax debt difficulties, the Board of Directors here is still determined to maintain the unit's operations.

Singapore team won dramatically 2-1 against Cambodia at ASEAN Cup 2024

|

On the evening of December 11, the Cambodian team lost 1-2 to Singapore in the group stage of the ASEAN Cup (formerly known as the AFF Cup) 2024.

Disciplinary action against former Director General of General Department of Roads

|

The Central Inspection Committee decided to discipline Mr. Nguyen Van Huyen - former Party Secretary, General Director of the Vietnam Road Administration.

On December 14, Binh Phuoc broke ground on the first expressway

|

Binh Phuoc province will break ground on the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project on December 14.

500kV line circuit 3 and the miracle of speed, economy and efficiency

Cường Ngô |

In the article "Fighting waste", General Secretary and President To Lam emphasized the need to summarize and replicate the experience of implementing the 500kV line 3 project for key and important national public investment projects and works.

Đã khắc phục xong sự cố đường dây 500kV sau bão số 3

Anh Tuấn |

Tính đến sáng 16.9, EVN đã cấp điện lại được hơn 5,98 triệu khách hàng trên tổng số khoảng 6,1 triệu khách hàng bị ảnh hưởng do bão số 3.

Đường dây 500kV mạch 3 có bị ảnh hưởng bởi bão số 3?

Anh Tuấn |

Theo EVNNPT, đường dây 500kV mạch 3 từ Quảng Trạch (Quảng Bình) đến Phố Nối (Hưng Yên) không bị ảnh hưởng, hư hỏng bởi bão số 3.