Ninh Binh Provincial People's Committee has just issued a decision approving Northern Power Corporation as the investor to implement the 220kV Dong Van Substation Project.
According to the decision, the project is built with a scale of 3 220kV-250MVA transformers; the first phase installs 2 transformers. The total land area used is about 96,044m2. The project has a total investment of more than 1,556 billion VND.
The 220kV and 110kV connection lines pass through Kim Bang, Tam Chuc, Le Ho, Kim Thanh, Duy Ha, Dong Van, Tien Son and Duy Tien wards; the main substation is built in Duy Tien ward.
Accordingly, the investor will complete legal procedures on land, design, and environment in the first quarter of 2027; deploy construction from the first quarter to the fourth quarter of 2027, complete acceptance and energize to put the project into operation in the fourth quarter of 2027.
Ninh Binh Provincial People's Committee assigned the Department of Finance to take the lead in guiding, monitoring, and inspecting the implementation of the decision; the Departments of Agriculture and Environment, Construction, and Industry and Trade perform state management functions according to regulations. People's Committees of wards with projects passing through coordinate and guide investors to carry out procedures, manage the area and supervise the implementation process.