Khanh Hoa needs to disburse 3,500 billion VND of public investment capital in September

Phương Linh |

Khanh Hoa - Site clearance continues to be the biggest bottleneck of the locality to achieve the target of disbursing 75% of the public investment capital plan by the end of the third quarter of 2026.

Control disbursement progress weekly

According to a report by the Department of Finance of Khanh Hoa province, as of August 28, the province has disbursed 8,585,761 billion VND of public investment capital, reaching 54.51% of the plan assigned by the Prime Minister. If not including 5% savings in development investment spending, the disbursement rate reached 56.93%.

This result is still higher than the national average of 51.9%. However, the disbursement rate in August showed signs of slowing down, making the pressure to complete the target of 75% by the end of Q3 increasing.

Ảnh: Hữu Long
Currently, the whole province still has 4/21 provincial units and 21/64 communes and wards with disbursement rates below 50%. Notably, key and dynamic project groups with large capital scale have only disbursed 37.3% of the plan. Photo: Huu Long

According to the Department of Finance, the main bottlenecks lie in compensation and site clearance; determining the origin of land; preparing resettlement plans; the supply of construction materials and the construction capacity of some contractors.

To achieve the target of disbursing 75% by September 30th, Khanh Hoa needs to disburse an additional VND 3,500 billion in September.

At the meeting on public investment disbursement, leaders of the Provincial People's Committee requested localities and departments to shift from a general monitoring mechanism to detailed weekly and project-by-project control. The progress of site handover and actual construction volume will be used as a basis for evaluating the level of task completion of units.

The province sets progress milestones until September 15, the disbursement rate must reach 62-64%; September 20 reach 66-68%; September 25 reach 72% and by September 30 reach at least 75%.

Focus on thoroughly handling backlog dossiers

In site clearance work, local leaders requested the Khanh Hoa Land Fund Development Center to coordinate with localities to focus on thoroughly handling backlog dossiers.

The areas required to focus include the wards of South Nha Trang, North Nha Trang, East Ninh Hoa, Tay Nha Trang and the communes of Dien Khanh, Khanh Son, Khanh Vinh.

The goal is to complete 100% of site handover for key projects right in September. When there is a site, the investor must coordinate with the contractor to organize rolling construction, avoiding the situation where the site is handed over but the project is still slow to deploy.

For projects that do not meet the committed progress in mid-September, the Department of Finance will coordinate with the Department of Home Affairs to advise the Provincial People's Committee to organize a review of the responsibilities of each unit. Projects that are behind schedule and unable to absorb capital will be considered for capital transfer to projects with better construction progress.

According to Chairman of Khanh Hoa Provincial People's Committee Nguyen Viet Hung, from now until the end of September is a decisive period for the disbursement of public investment capital. Therefore, it is required that departments, branches, localities and investors focus highly and unanimously remove bottlenecks, especially focusing on handling obstacles in site clearance.

Difficulties under the authority of which agency or unit must be proactively resolved immediately, without shirking or avoiding, affecting the project progress.

Heads of agencies, units and localities must be directly responsible for the assigned tasks and the results of public investment capital disbursement. The progress of site clearance, construction and disbursement will be important criteria for evaluating the results of task implementation.

Through reviewing 18 projects that are within the 90-day peak program for site clearance of key and dynamic projects in the area, the Khanh Hoa Land Fund Development Center assessed that 9 projects continue to have the ability to ensure progress, and 9 projects were proposed to adjust the implementation time.

Among the projects proposed for extension are Ninh Xuan Industrial Park 1, 2; the project to complete level II and level III pipeline canals under the Song Cai - Tan My Irrigation System; the project to combat drought, erosion, and flooding adapting to climate change in Anh Dung, My Son, Phuoc Hau communes...

Phương Linh
RELATED NEWS

Da Nang disburses more than 9,200 billion VND of public investment capital in 8 months

|

Da Nang - In the first 8 months of 2026, Da Nang City disbursed more than 9,200 billion VND of public investment capital.

Hai Phong Chairman directs to use disbursement results as a measure to evaluate officials

|

Hai Phong - On August 28, the City People's Committee held a regular meeting in August to assess the socio-economic development situation in the first 8 months of 2026.

Disbursing more than 1 million billion VND, need to overcome implementation bottlenecks

|

Most of the public investment capital plan has been allocated, but for more than 1 million billion VND to truly be converted into projects, jobs and growth still largely depend on implementation capacity.

Southern Power Company urgently warns of fake EVN brand website and EVNSPC customer service application

|

EVNSPC urgently notifies all customers about the situation of impersonating the website and CSKH EVNSPC application to spread malware and appropriate bank accounts.

Bamboo Airways owes more than 440 billion VND in taxes, former Chairman Le Thai Sam's departure postponed

|

Gia Lai - Former Chairman of Bamboo Airways Le Thai Sam is temporarily suspended from leaving the country due to tax debt of more than 440 billion VND of this airline.

Stock market today: VN-Index increased by more than 25 points, VIC alone contributed nearly 20 points

|

VIC shares once again became a fulcrum for the stock market to rebound in the session on September 4.

Da Nang disburses more than 9,200 billion VND of public investment capital in 8 months

Nguyễn Linh |

Da Nang - In the first 8 months of 2026, Da Nang City disbursed more than 9,200 billion VND of public investment capital.

Hai Phong Chairman directs to use disbursement results as a measure to evaluate officials

Theo Cổng TTĐT Hải Phòng |

Hai Phong - On August 28, the City People's Committee held a regular meeting in August to assess the socio-economic development situation in the first 8 months of 2026.

Disbursing more than 1 million billion VND, need to overcome implementation bottlenecks

Thuận Hiền |

Most of the public investment capital plan has been allocated, but for more than 1 million billion VND to truly be converted into projects, jobs and growth still largely depend on implementation capacity.