Khanh Hoa proposes to connect a series of solar power projects

Hữu Long |

Khanh Hoa - There are still some solar power projects being temporarily connected, so the locality proposed that the Central Government agree to switch to the main connection option.

In February 2025, the authorities of Khanh Hoa province reviewed the difficulties and problems of 9 non-budgetary investment projects in the renewable energy sector.

Khanh Hoa province has also reported to the Ministry of Industry and Trade and the Prime Minister about the difficulties and problems of the projects and proposed to resolve them.

There are currently 9 solar power projects deployed in Khanh Hoa with a total capacity of 580.6 MWp. Of the total 9 projects, 6 projects have been energized before June 30, 2019 with a total capacity of 275.6MWp.

The remaining 3 projects will be energized before December 31, 2020 with a total capacity of 305 MWp.

According to Inspection Conclusion No. 1027 of 2023 of the Government Inspectorate, there are still some shortcomings and deficiencies in the implementation of solar power projects in Khanh Hoa.

After the inspection conclusion, Khanh Hoa reported and asked for the Government Inspectorate's opinion on the problems of the above projects but has not yet received a response.

Currently, there are a number of solar power projects mentioned in Inspection Conclusion No. 1027 that are temporarily connected, not yet converted to the main connection plan according to the power plan previously approved by the Ministry of Industry and Trade.

In addition, the main connection plans for these solar power projects have not been updated in the Khanh Hoa Provincial Planning for the period 2021-2030 (approved by the Prime Minister in Decision No. 318 of 2023).

In 2024, the People's Committee of Khanh Hoa province has proposed that the Central Power Corporation consider and temporarily extend the connection during the implementation of the procedures for transferring the connection to the main connection plan according to the approved power plan.

Up to now, Khanh Hoa has proposed and requested the Ministry of Industry and Trade and the Government to allow solar power projects in Khanh Hoa province to be implemented according to the main connection plan previously approved by the Ministry of Industry and Trade (according to individual decisions).

In the process of adjusting the Khanh Hoa Provincial Planning for the period 2021-2030, Khanh Hoa province will update the main connection plan of solar power projects according to the power plan approved by the Ministry of Industry and Trade.

A series of billion-dollar solar power projects were "whistled"

9 solar power projects in Khanh Hoa include the Central Power Company (not yet completed land procedures for the entire project area); Cam Lam VN Solar Power Plant (used but still stuck in planning); KN Cam Lam Solar Power Plant of Cam KN Lam Company Limited; Quang Hoa Solar Power Plant (there are still 12,000m2 of land that have not been compensated for site clearance).

In addition, there are a number of other names on the list of 9 projects such as Song Giang Solar Power Plant; Tuan An Solar Power Plant; Trung Son Solar Power Plant; KN Van Ninh Solar Power Plant.

Also in 2023, Khanh Hoa province reported and provided documents related to 9 above-ground power projects connecting to the grid in the province according to the request of the Investigation Security Agency - Ministry of Public Security.

Regarding solar power violations, many departments and branches of Khanh Hoa province have organized reviews of related individuals.

In particular, the Department of Industry and Trade held a meeting to review the Energy Management Department and 2 individuals, Mr. Truong Tam - Head of the Energy Management Department and Ms. Vo Nguyen Phuong Mai - Deputy Head of the Energy Management Department on June 15, 2023 and July 27, 2023...

Hữu Long
TIN LIÊN QUAN

Ninh Binh Provincial Police has 8 deputy directors after the merger

|

Ninh Binh - The new Ninh Binh Provincial Police after merging with Ha Nam and Nam Dinh provinces has 1 director and 8 deputy directors.

Israel declares to kill Hamas co-founder

|

The Israeli military has confirmed it has eliminated one of Hamas' remaining top military leaders in the Gaza Strip.

Gold price update on the morning of September 30: Domestic gold ignored world developments

|

Gold price update on the morning of September 30: Looking at the chart, it can be seen that domestic gold prices last week did not fluctuate too much, while the world market plummeted.

Forecast of the possibility of a super typhoon appearing in July

|

The threat level of super typhoons in July may remain low, despite sea temperatures rising above average.

Verify and handle drivers who let children sit in a truck box on the highway

|

Hanoi - A driver carrying 6 children in a pickup truck traveling on Thang Long Avenue Expressway. The traffic police force verified and handled the case.

Big fire at a paper packaging company in Binh Duong

|

Binh Duong - In Tan Hiep ward, Tan Uyen city, a fire is occurring at a packaging company, police mobilized many vehicles to put out the fire.

PSG eliminates Messi and Inter Miami from FIFA Club World Cup

|

PSG easily won 4-0 against Inter Miami to advance to the quarter-finals of the FIFA Club World Cup 2025.

Kiểm điểm loạt cán bộ Khánh Hòa liên quan sai phạm điện mặt trời

Hữu Long |

Khánh Hòa - Liên quan đến các dự án điện mặt trời có sai phạm mà Thanh tra Chính phủ đã kết luận, đến nay địa phương đã tổ chức kiểm điểm cựu lãnh đạo, cán bộ đương chức.

Bán điện trước nghiệm thu sau, điện mặt trời Trung Sơn phải rà soát

Hữu Long |

Dự án điện mặt trời Trung Sơn vận hành thương mại, bán điện cho Tập đoàn Điện lực Việt Nam (EVN) vào năm 2020. Đáng nói là 3 năm sau khi vận hành thương mại, dự án này mới được nghiệm thu.

Nghiệm thu điện mặt trời 1.000 tỉ dù còn vướng quy hoạch rừng ở Khánh Hòa

Hữu Long |

Khánh Hòa - Dự án Điện mặt trời Trung Sơn có vốn đầu tư hơn 1.000 tỉ đồng và đã được nghiệm thu dù vẫn có khoảng 8,64ha thuộc quy hoạch rừng sản xuất. Hiện nay, địa phương đang rà soát pháp lý tại dự án này.