800 billion VND ore processing plant in Lao Cai enters completion phase

Đinh Đại |

Lao Cai - After a period of construction, the factory worth more than 800 billion VND has completed most of the volume, opening up an important step before official operation.

The Lang Phung type III apatite ore processing plant project is invested by Tam Dinh Lao Cai Apatite Investment Joint Stock Company, with a total investment of over 800 billion VND and a designed capacity of 250,000 tons of apatite concentrate/year.

According to records at the construction site, many main items of the factory have been basically completed.

Areas serving the production line are being completed in the final stages, preparing for the trial run and equipment adjustment process.

The fact that the plant is eligible for trial run from August 6 marks an important shift of the project from the construction phase to trial operation.

Nhà máy tuyển quặng apatit Làng Phúng đã hoàn thành hơn 90% khối lượng. Ảnh: Đinh Đại
Lang Phung apatite ore processing plant has completed more than 90% of the volume. Photo: Dinh Dai

This is also the basis for the investor to continue to complete the remaining items, aiming to put the plant into official operation in the third quarter of 2026.

In the process of implementation, the project still has some difficulties that need to be focused on handling. Prolonged rainy weather affects the construction progress of the tailings lake; the road surface to the factory is not completed.

Along with that, site clearance for the mining area is being continued to ensure a stable source of raw materials for the factory during its long-term operation.

The investor and construction units are mobilizing manpower and equipment to complete the remaining items.

Công trường Nhà máy tuyển quặng apatit Làng Phúng những ngày hoàn thiện các hạng mục cuối. Ảnh: Đinh Đại
Construction site of Lang Phung Apatite Ore Preparation Plant in the days of completing the final items. Photo: Dinh Dai

When put into operation, the factory is expected to increase the value of deep processing of apatite ore, creating a stable source of raw materials for the chemical and fertilizer industry.

The project also opens up room for development in the fields of transportation, mechanics, commerce, and services, creating more jobs and contributing to local budget revenue.

For Van Ban commune, a large-scale industrial project put into operation is expected to create more motivation to attract investment, expand economic development space, and at the same time form a spillover effect on supporting industries and services.

Nhà máy tuyển quặng apatit Làng Phúng được kỳ vọng góp phần nâng cao giá trị chế biến sâu khoáng sản tại Lào Cai. Ảnh: Đinh Đại
Lang Phung apatite ore processing plant is expected to contribute to improving the value of deep mineral processing in Lao Cai. Photo: Dinh Dai

According to Mr. Vu Xuan Thuy - Chairman of Van Ban Commune People's Committee, the locality determines that the early operation of industrial projects will create more motivation for economic development, job expansion and promote service industries in the area.

Therefore, the commune will continue to coordinate with the investor and specialized agencies of the province to remove arising difficulties and obstacles, especially in site clearance and ensuring conditions to serve the long-term operation of the factory.

Leaders of Van Ban commune believe that when Lang Phung Apatite ore processing plant comes into stable operation, the economic efficiency of the project will not only lie in ore processing activities but also create spillover effects to transportation, mechanics, commerce, services and jobs for local people.

Nhà máy có công suất thiết kế 250.000 tấn tinh quặng apatit mỗi năm, tổng mức đầu tư trên 800 tỉ đồng. Ảnh: Đinh Đại
The plant has a designed capacity of 250,000 tons of apatite concentrate per year, with a total investment of over 800 billion VND. Photo: Dinh Dai

This is also considered one of the driving forces contributing to the implementation of the goal of industrial development, attracting investment and expanding the commune's economic space in the coming time.

With the current progress, Lang Phung Apatite ore processing plant is entering the final stage before official operation.

The project is expected to become one of the new driving forces for industrial development, deep mineral processing and socio-economic development in Van Ban.

Đinh Đại
RELATED NEWS

Lao Cai tightens progress, decides to disburse 100% of public investment capital

|

Lao Cai - Chairman of the Provincial People's Committee requests the implementation of the disbursement scenario for the last 6 months of the year, flexible capital transfer and clarification of responsibilities for delays.

Groundbreaking ceremony for a 160 billion VND plywood factory in Lao Cai

|

Lao Cai - Started in August 2026, the project is expected to complete phase 1 by the end of 2027 and put the entire factory into operation after 3 years.

Exciting import and export activities at the 860 billion VND smart border gate in Lao Cai

|

Lao Cai - The smart border gate project worth more than 860 billion VND is expected to create a new step for import and export activities.

The reason why 5 veteran artists at the Nursing Center do not have pensions

|

According to People's Artist Trinh Kim Chi - Chairman of the Ho Chi Minh City Theater Association, 5 veteran artists living at Thi Nghe Nursing Center do not have pensions for many reasons.

Hanoi announces a series of decisions on personnel work

|

Hanoi - On the morning of August 10, the City Party Committee, People's Council, and People's Committee of Ho Chi Minh City organized a conference to announce the decisions of the Standing Committee of the City Party Committee, People's Council, and People's Committee of Ho Chi Minh City on organizational structure and personnel work.

Hanoi officially merges the Department of Planning and Architecture into the Department of Construction

|

Hanoi - The city establishes a new Department of Construction on the basis of merging the Department of Planning and Architecture into the Department of Construction.

Lao Cai tightens progress, decides to disburse 100% of public investment capital

Đinh Đại |

Lao Cai - Chairman of the Provincial People's Committee requests the implementation of the disbursement scenario for the last 6 months of the year, flexible capital transfer and clarification of responsibilities for delays.

Groundbreaking ceremony for a 160 billion VND plywood factory in Lao Cai

Đinh Đại |

Lao Cai - Started in August 2026, the project is expected to complete phase 1 by the end of 2027 and put the entire factory into operation after 3 years.

Exciting import and export activities at the 860 billion VND smart border gate in Lao Cai

Đinh Đại |

Lao Cai - The smart border gate project worth more than 860 billion VND is expected to create a new step for import and export activities.