Quang Tri issues deadline for handling wind power projects that are delayed and do not have collateral

HƯNG THƠ |

Quang Tri - The provincial Department of Finance requires wind power projects with slow progress to deposit funds to ensure and speed up progress, otherwise they will be considered for termination of operations.

On May 10, the Department of Finance of Quang Tri province confirmed that this agency had issued a document requesting investors in wind power projects such as Huong Linh 5, Huong Hiep 2 and Huong Hiep 3 factories to deposit investment guarantee according to current regulations. This is a tough move to rectify the long-term delay, affecting the investment environment and the commitment to developing renewable energy in the locality.

For example, for Huong Linh 5 Wind Power Joint Stock Company, the Department of Finance requires this unit to deposit a fund to ensure project implementation according to Article 43 of the 2020 Investment Law and related provisions in Decree No. 31/2021/ND-CP. The deposit completion date is in May 2025. At the same time, investors must also complete procedures to adjust investment policies according to Article 41 of the Law on Investment.

"If the requirements are not fully implemented before May 31, 2025, the Department of Finance will report to the Provincial People's Committee to consider terminating the project" - said the leader of the Department of Finance of Quang Tri province.

Previously, on April 25, 2025, the People's Committee of Quang Tri province also issued a notice requesting the above projects to deposit and speed up progress, with the deadline being June 10, 2025. This is the basis for the Department of Finance to issue documents urging and increasing legal obligations to investors.

Not only stopping at the above 3 projects, the People's Committee of Quang Tri province also requires the investor of Quang Tri TNC 1 and TNC 2 Wind Power Plants to deposit a deposit to ensure project implementation in the second quarter of 2025. The province assigned the Provincial Economic Zone Management Board to closely monitor, if not implemented, it would advise the province to terminate operations before July 10, 2025.

Quang Tri province's "ultimatum" to a series of wind power projects stems from the fact that 5 projects are behind schedule for a long time, not only causing waste of resources but also affecting the local reputation in its commitment to the Government on developing clean energy.

Currently, Quang Tri has 20 wind power projects in commercial operation, with a total capacity of 742 MW. The Huong Linh 4 factory with a capacity of 30 MW has also completed construction and is ready to be put into operation in 2025.

HƯNG THƠ
RELATED NEWS

More wind power projects request to sell shares to foreign investors

|

Quang Tri - There are many wind power and solar power projects that have come into operation or are under construction, asking to sell shares to foreign investors.

Cloud hunting points in wind power fields attract young people

|

Quang Tri - The cloud hunting spot in the wind power field in Huong Hoa district attracts many young people to experience.

Many hydropower and wind power projects in Quang Tri are behind schedule

|

Quang Tri - The specialized agency proposed that the People's Committee of Quang Tri province require wind and hydropower projects that are behind schedule to deposit funds to ensure investment.

Cambodia arrests and extradites fraud boss Chen Zhi to China

|

Cambodia announced that it has arrested and extradited to China fraud boss Chen Zhi, a subject wanted by the US for criminal charges.

Russia announces casualties in clashes with Ukraine

|

Russia said nearly 60 people were killed and more than 300 injured in clashes with Ukraine in December.

A ward in Hanoi resolves land procedures overdue for 134 days, must apologize to citizens

|

Hanoi - Long Bien Ward is assessed as still having shortcomings and limitations when resolving administrative procedures on land, including dossiers that are overdue for 134 days.

Forecast of the time to end widespread severe cold in the North

|

According to a representative of the meteorological agency, it is forecast that widespread severe cold and frost in the North will last until about January 10, to prevent frost and frost in mountainous areas.

Desolate trillion-VND urban areas in Son La

|

Son La - Many urban areas have been invested hundreds, thousands of billions of VND, spacious infrastructure but desolate, deserted residents, abandoned and lifeless land.

More wind power projects request to sell shares to foreign investors

HƯNG THƠ |

Quang Tri - There are many wind power and solar power projects that have come into operation or are under construction, asking to sell shares to foreign investors.

Cloud hunting points in wind power fields attract young people

CÔNG SÁNG - NGUYỄN LUÂN |

Quang Tri - The cloud hunting spot in the wind power field in Huong Hoa district attracts many young people to experience.

Many hydropower and wind power projects in Quang Tri are behind schedule

HƯNG THƠ |

Quang Tri - The specialized agency proposed that the People's Committee of Quang Tri province require wind and hydropower projects that are behind schedule to deposit funds to ensure investment.