Many hydropower and wind power projects in Quang Tri are behind schedule

HƯNG THƠ |

Quang Tri - The specialized agency proposed that the People's Committee of Quang Tri province require wind and hydropower projects that are behind schedule to deposit funds to ensure investment.

On January 4, the People's Committee of Quang Tri province confirmed that, in the face of many energy projects in the area being behind schedule, the Department of Planning and Investment of Quang Tri province has made a proposal to urge investors to soon implement the project.

The Department of Planning and Investment of Quang Tri province proposed that the Provincial People's Committee require investors of slow-progressing energy projects to complete their investment guarantee deposit obligations - before considering approving the extension of the project implementation schedule.

Up to now, in Quang Tri province, there are 10 wind power projects under investment, 1 project has completed construction and is completing related procedures to put into commercial operation. Of which, 6 projects are under investment behind schedule including: Huong Linh 5, Huong Hiep 2, Huong Hiep 3, Huong Phung 1, TNC 1, TNC 2.

Of the 6 projects behind schedule, 5 projects have not yet signed an investment guarantee fund, only 1 project has signed an investment guarantee fund with the amount of 12.8 billion VND, which is the Huong Phung 1 project. Currently, the Huong Phung 1 project has prepared a dossier to adjust the project implementation progress, which has been presided over by the Department of Planning and Investment, and has prepared a report to advise the Provincial People's Committee to consider and decide.

The provincial Department of Planning and Investment has also drawn up a record of violations and imposed administrative penalties on projects that are behind schedule and have violations. The projects that have paid fines totaling VND180 million are Huong Linh 5, Huong Hiep 2 and Huong Hiep 3.

In addition to wind power projects, in Quang Tri there are also 4 hydropower projects behind schedule including: Huong Phung Hydropower and 3 hydropower projects Huong Son 1, 2, 3.

Of the 4 projects behind schedule, only Huong Phung Hydropower project has made an investment guarantee deposit of 7.7 billion VND and this project is currently carrying out procedures to propose an adjustment to the progress. For the 3 hydropower projects Huong Son 1, 2, 3, the Department of Planning and Investment has sent a document to the investor urging to speed up the progress and make an investment guarantee deposit.

To strengthen state management of slow-progressing projects and overcome the situation of suspended projects and projects that are not feasible, the Department of Planning and Investment proposes that when a project is behind schedule not due to objective reasons, investors must pay a deposit to ensure investment in order to continue implementing the project in accordance with regulations.

HƯNG THƠ
RELATED NEWS

Removing obstacles for 5 wind power projects, increasing income from renewable energy

|

Gia Lai is stepping up efforts to remove legal obstacles for five wind power projects worth hundreds of billions of dong, in order to soon connect to the grid, increase budget revenue, promote socio-economic development, and avoid wasting investment resources.

Deadline for handling difficulties for renewable energy projects

|

Emphasizing the determination to resolutely handle and resolve difficulties and obstacles of renewable energy projects, the Prime Minister requested to complete them before January 31, 2025.

Difficult to achieve the set goal of building an energy center

|

Quang Tri - Several large energy projects have been stopped or delayed, making it difficult to complete the plans set by Quang Tri province.

International beauties, used cars add sparkling beauty to Da Lat streets

|

Da Lat - Da Lat City of Thousands of Flowers is more sparkling with the participation of nearly 80 international beauties and dozens of ancient cars participating in the parade through the streets.

Electricity says Ecohome Nhon Binh lacks cooperation in power generation

|

Gia Lai - Regarding the prolonged power outage at Ecohome Nhon Binh Social Housing Apartment, the Electricity sector said it has provided full support but the repair process is still very slow.

Thien Khoi FC crowned champion of the 2025 National 7-a-side Football Cup

|

Defeating Dai Tu in a dramatic final match, Thien Khoi FC became the champion of the 2025 Hyundai Thanh Cong Cup National 7-a-side Football Cup (VSC-S5).

Traffic ban on Prenn Pass to Da Lat from tomorrow afternoon, December 8

|

Lam Dong - The ban on traffic on Prenn Pass will take place from 11am to 5pm on December 8 to cut down trees at risk of falling, causing traffic insecurity.

Gia Bac Pass in Lam Dong opens to traffic after 5 days of paralysis due to serious landslides

|

Lam Dong - At 5:00 p.m. this afternoon, Gia Bac Pass officially opened the route, vehicles on National Highway 28 began traveling again after a period of paralysis due to landslides.

Removing obstacles for 5 wind power projects, increasing income from renewable energy

THANH TUẤN |

Gia Lai is stepping up efforts to remove legal obstacles for five wind power projects worth hundreds of billions of dong, in order to soon connect to the grid, increase budget revenue, promote socio-economic development, and avoid wasting investment resources.

Deadline for handling difficulties for renewable energy projects

PHẠM ĐÔNG |

Emphasizing the determination to resolutely handle and resolve difficulties and obstacles of renewable energy projects, the Prime Minister requested to complete them before January 31, 2025.

Difficult to achieve the set goal of building an energy center

HƯNG THƠ |

Quang Tri - Several large energy projects have been stopped or delayed, making it difficult to complete the plans set by Quang Tri province.