The industrial cluster hopes to "escape" thanks to the 245 billion VND road

Bài và ảnh: Tô Công |

Phu Tho - The traffic project connecting Bac Lam Thao Industrial Cluster via National Highway 2 to Phu Gia Industrial Cluster after nearly 2 years of construction has now taken shape.

Road Project connecting provincial road 325B (Bac Lam Thao Industrial Cluster) - National Highway 2 - Provincial Road 323H - District Road P2 (Phu Gia Industrial Cluster, Phu Ninh District) invested by Phu Ninh District People's Committee , with a total investment of over 245 billion VND.
Road Project connecting provincial road 325B (Bac Lam Thao Industrial Cluster) - National Highway 2 - Provincial Road 323H - District Road P2 (Phu Gia Industrial Cluster, Phu Ninh District) invested by Phu Ninh District People's Committee , with a total investment of over 245 billion VND.
The total length of the project route is nearly 7.2km, passing through Tien Kien commune (Lam Thao district), Ha Thach and Phu Ho communes (Phu Tho town) and communes: Phu Loc, Phu Nham, Gia Thanh ( Phu Ninh district). The starting point of the route at Tien Kien commune intersects with provincial road 325B, the end of the route intersects with road 323 to National Highway 2, Gia Thanh commune.
The total length of the project route is nearly 7.2km (main route 6.3km, branch route 0.9km) passing through Tien Kien commune (Lam Thao district), Ha Thach and Phu Ho communes (Phu Tho town). and communes: Phu Loc, Phu Nham, Gia Thanh (Phu Ninh district). The starting point of the route at Tien Kien commune intersects with provincial road 325B, the end of the route intersects with road 323 to National Highway 2, Gia Thanh commune.
As noted by a reporter from Lao Dong Newspaper in mid-August, this route designed according to class III plain road standards passes through many low hills and mountains of midland communes in Phu Tho.
As noted by a reporter from Lao Dong Newspaper in mid-August, this route designed according to class III plain road standards passes through many low hills and mountains of midland communes in Phu Tho (Roadbed width 12m, road surface width 7m; design speed 80km/h).
After the drainage system was basically completed, there are now sections of the route covered with asphalt, many sections are being spread with crushed stone, and the remaining sections are being excavated and embanked...
After the drainage system was basically completed, up to now, some sections of the route have been paved with asphalt, many sections are being spread with crushed stone, and the remaining sections have been excavating and embanking the roadbed...
Many machines and equipment are under construction at the project site.
Many machines and equipment are under construction at the project site.
Phuong Nam Construction and Mechanical Joint Stock Company is the project contractor.
Phuong Nam Construction and Mechanical Joint Stock Company is the project contractor.
According to the investor's representative, the Phu Ninh District Construction Investment Project Management Board, 6.5/7.2km of the site has now been handed over. Of which, 6.5km of roadbed and vertical and horizontal drainage systems have been completed; Asphalt concrete carpet on the road surface reaches 3km; 5.5km of gravel gravel spread (0.9km of branch route has 0.8km of asphalt carpet).
According to the investor's representative, the Phu Ninh District Construction Investment Project Management Board, 6.5/7.2km of the site has now been handed over. Of which, 6.5km of roadbed and vertical and horizontal drainage systems have been completed; Asphalt concrete carpet on the road surface reaches 3km; 5.5km of gravel gravel spread (0.9km of branch route has 0.8km of asphalt carpet).
Once completed, the project will meet the needs of goods trade and travel of the people, maximize the efficiency of traffic routes in the area, creating conditions to promote socio-economic development for the region. localities. At the same time, increase the efficiency of attracting investors to Phu Gia Industrial Cluster, Phu Ha Industrial Park, Phu Ho Industrial Cluster, especially Bac Lam Thao Industrial Cluster, which is still having results in attracting investment. investment has been "sluggish" in recent times.
Once completed, the project will meet the travel needs of people, maximize the efficiency of traffic routes in the area, creating conditions to promote socio-economic development for localities. At the same time, increase the efficiency of attracting investors to Phu Gia Industrial Cluster, Phu Ha Industrial Park and Phu Ho Industrial Cluster (Phu Tho town), especially Bac Lam Thao Industrial Cluster, which is still under construction. The results of attracting investment are quite "poor" even though the construction of technical infrastructure has been completed.
Bac Lam Thao Industrial Cluster was established under Decision No. 1553/QD-UBND dated June 30, 2016 of Phu Tho Provincial People's Committee. This industrial cluster has a phase I planning area of ​​43 hectares in Tien Kien commune (Lam Thao district), located next to Noi Bai - Lao Cai highway and provincial road 325B.
Bac Lam Thao Industrial Cluster was established under Decision No. 1553/QD-UBND dated June 30, 2016 of Phu Tho Provincial People's Committee. This industrial cluster has a phase I planning area of ​​43 hectares in Tien Kien commune (Lam Thao district), located next to Noi Bai - Lao Cai highway and provincial road 325B.
Recording the reality shows that, at Bac Lam Thao Industrial Cluster, although the technical infrastructure has been completed, there are still no investors to build a factory.
According to the reporter's research, since October 2023, Bac Lam Thao Industrial Cluster has completed the construction of technical infrastructure, but it is noted that there are still no investors here to build a factory.
According to research, the total investment capital of this industrial cluster is about 330 billion VND, with an operating period of 50 years (from 2018 to 2068).
The total investment capital of this industrial cluster is about 330 billion VND, with an operating period of 50 years (from 2018 to 2068).
Phu Gia Industrial Cluster has an area of ​​38 hectares located in 3 communes: Phu Loc, Gia Thanh and Phu Nham of Phu Ninh district. This industrial cluster is invested by Phu Gia Investment and Construction Company Limited, with a total investment of more than 118 billion VND.
Phu Gia Industrial Cluster has an area of ​​38 hectares located in 3 communes: Phu Loc, Gia Thanh and Phu Nham of Phu Ninh district. This industrial cluster is invested by Phu Gia Investment and Construction Company Limited, with a total investment of more than 118 billion VND.
Currently, the site occupancy rate of Phu Gia Industrial Cluster has reached nearly 30%, has attracted 5 investment projects, 4 projects are in operation although many areas are still in the process of site clearance. Technical infrastructure construction, not fully completed like Bac Lam Thao Industrial Cluster.
Although Phu Gia Industrial Cluster has not completed the entire technical infrastructure like Bac Lam Thao Industrial Cluster, it is even in the process of both site clearance and construction... However, the occupancy rate The land area has reached nearly 30%, attracting 5 investment projects, of which 4 projects are in operation.
According to Phu Ninh District People's Committee, at Phu Gia Industrial Cluster, the total capital of implemented projects is 18.47/27 million USD. The area where site clearance compensation has been paid is 27.79 hectares, the area allocated land by the Provincial People's Committee is 14.97 hectares; The land area that has been compensated and cleared for purposes that have not yet been converted is 12.82 hectares; The uncompensated area is 10.21 hectares, of which 9.13 hectares have been counted and 1.08 hectares have not been counted.
According to Phu Ninh District People's Committee, at Phu Gia Industrial Cluster, the total capital of implemented projects reached 18.47/27 million USD. The area where site clearance compensation has been paid is 27.79 hectares, the area allocated land by the Provincial People's Committee is 14.97 hectares; The land area that has been compensated and cleared for purposes that have not yet been converted is 12.82 hectares; The uncompensated area is 10.21 hectares, of which 9.13 hectares have been counted and 1.08 hectares have not been counted.
Bài và ảnh: Tô Công
TIN LIÊN QUAN

Sắp thành lập cụm công nghiệp tại 2 xã "chuyên" gỗ ở Phú Thọ

Tô Công |

Phú Thọ - UBND huyện Hạ Hòa giao Phòng Kinh tế và Hạ tầng và 2 xã Ấm Hạ, Phương Viên thực hiện các thủ tục đầu tư và thành lập Cụm công nghiệp Ấm Hạ.

Dọn rác thải đổ bừa bãi trong cụm công nghiệp ở Thái Bình

TRUNG DU |

Thái Bình - Điểm tập kết rác thải tự phát bừa bãi gây ô nhiễm môi trường trong cụm công nghiệp thị trấn Vũ Thư bước đầu đã được xử lý, dọn dẹp.

Thu hút đầu tư cụm công nghiệp miền núi Sông Cầu

Bình Quý |

Khánh Hòa - Trong năm nay, Cụm Công nghiệp Sông Cầu thu hút thêm nhiều nhà đầu tư thứ cấp mới, đạt tỷ lệ lấp đầy hơn 80% và mở rộng khoảng 35ha về phía đông.

VĐV bóng chuyền Nguyễn Thị Xuân và sự bền bỉ ở tuổi U40

NHÓM PV |

Góc nhìn thể thao số 181 có buổi trò chuyện với chủ công Nguyễn Thị Xuân về hành trình gắn bó với bóng chuyền cũng như dự định trong tương lai của tay đập 38 tuổi.

Ảnh hưởng thi công âu thuyền, nhà dân bị ngập sâu trong nước

YẾN PHƯƠNG - TẠ QUANG |

Việc thi công công trình Âu thuyền Cái Khế đã khiến nhiều nhà dân tại TP Cần Thơ bị lún, nứt nghiêm trọng và ngập sâu trong nước.

Người dân ở Hoài Đức phải khám da liễu hàng tháng vì thiếu nước sạch

KHÁNH AN |

Suốt 6 năm qua, hàng tháng, vợ chồng anh Nguyễn Đình Minh (Hoài Đức, Hà Nội) đều đưa các con đi khám da liễu vì không có nước sạch sử dụng.

6 lần thu hồi đất bất thành của chính quyền TP Thái Nguyên

Lam Thanh |

Thái Nguyên - Dù các cơ quan chức năng có hàng loạt thông báo yêu cầu di dời tài sản, bàn giao lại đất nhưng Trung tâm Nông nghiệp công nghệ cao vẫn phớt lờ.

Tăng trợ cấp thất nghiệp lên 75% giúp người lao động yên tâm

MINH HÀ - HOÀNG XUYẾN |

Tăng mức hưởng trợ cấp thất nghiệp lên 75% lương bình quân là mong mỏi của rất nhiều người lao động.

Establishing an industrial cluster in 2 wood-specialized communes in Phú Thọ.

Tô Công |

Phu Tho - The People's Committee of Hạ Hòa District assigns the Department of Economics and Infrastructure and two communes, Ấm Hạ and Phương Viên, to implement investment procedures and establish the Industrial Cluster of Ấm Hạ.

Clearing waste scattered in the industrial cluster in Thai Binh

TRUNG DU |

Thai Binh - A spontaneous waste collection point causing environmental pollution in the industrial cluster of Vu Thu town has been initially handled and cleaned up.

Attracting investment to the mountainous industrial cluster of Sông Cầu

Bình Quý |

Khanh Hoa - In this year, Cluster of Industrial Estates Sông Cầu attracted additional new secondary investors, achieving a fill rate of over 80% and expanding approximately 35ha towards the east.