The Thuy Khue ditch improvement project still has land problems

NGỌC THÙY |

After many years of implementation, up to now, the project to improve the environment of Thuy Khue ditch has not been completed because of land problems .

At the end of 2012, the project to improve the environment around the Thuy Khue drainage ditch was started with a capital of 400 billion VND invested by the People's Committee of Tay Ho district.
At the end of 2012, the project to improve the environment around the Thuy Khue drainage ditch was started with a capital of 400 billion VND invested by the People's Committee of Tay Ho district.
This is a ditch drainage project using a 2-lane box sewer system, with sidewalks on both sides along with a water supply system and lighting on the sewer surface. Initially, the local government determined that the project would be completed in 2017. However, up to now, the project is still being constructed in a "turtle" style, causing hundreds of households living along this ditch to live in squalor and pollution. .
This is a ditch drainage project using a 2-lane box sewer system, with sidewalks on both sides along with a water supply system and lighting on the sewer surface. Initially, the local government determined that the project would be completed in 2017. However, up to now, the project is still being constructed in a "turtle" style, causing hundreds of households living along this ditch to live in squalor and pollution. .
As noted by Labor on August 3, in the area of ​​alley 167 and 123A, Thuy Khue street, many items of the environmental improvement project are unfinished.
As noted by Labor on August 3, in the area of ​​alley 167 and 123A, Thuy Khue street, many items of the environmental improvement project are unfinished.
Some residential buildings of households have not yet been cleared for the project.
Some residential buildings of households have not yet been cleared for the project.
Around the area, there are many spontaneous garbage collection points, combined with open sewers, causing strong stench and pollution.
Around this area, there exist many spontaneous garbage collection points, combined with open sewers, causing strong stench and pollution.
According to feedback from Thuy Khue residents, although the project has been implemented for more than a decade, there are still some places on the route that have not been constructed, creating open ditch areas that are unsanitary. environment and urban aesthetics.
According to feedback from Thuy Khue residents, although the project has been implemented for more than a decade, there are still some places on the route that have not been constructed, creating open ditch areas that are unsanitary. environment and urban aesthetics.
Mr. Phan Anh Hai (residing in Thuy Khue street) said that people have posted garbage disposal signs in these sewer sections, but the situation of indiscriminate disposal of household garbage has not improved. Meanwhile, many construction sites are unfinished, causing the area to always be filled with dust.
Mr. Phan Anh Hai (residing in Thuy Khue street) said that people have posted garbage disposal signs in these sewer sections, but the situation of indiscriminate disposal of household garbage has not improved. Meanwhile, many construction sites are unfinished, causing the area to always be filled with dust.
"Not only does it cause environmental unsanitary conditions, the construction of the "turtle-crawling" project also affects the movement and daily activities of people. We encounter many difficulties and inconveniences," Ms. Vu Thu Hoa (residing in Thuy Khue) lamented.
"Not only does it cause environmental unsanitary conditions, the construction of the "turtle-crawling" project also affects the movement and daily activities of people. We encounter many difficulties and inconveniences," Ms. Vu Thu Hoa (residing in Thuy Khue) lamented.
According to the reporter's research, one of the main reasons why the project to improve the environment around the Thuy Khue drainage ditch is repeatedly behind schedule is because there is no clean ground to serve the construction.
According to the reporter's research, one of the main reasons why the project to improve the environment around the Thuy Khue drainage ditch is repeatedly behind schedule is because there is no clean ground to serve the construction.
Regarding this, Mr. Nguyen Hai Duong - Head of Land Clearance and Land Fund Development Department, Construction Investment Project Management Board of Tay Ho District (Hanoi) said that up to now, the project investor has received the premises of 317/ 325 cases in the project area and construction has been completed on the area handed over.
Regarding this, Mr. Nguyen Hai Duong - Head of Site Clearance and Land Fund Development, Tay Ho District Construction Investment Project Management Board (Hanoi) said that up to now, the project investor has continued to received premises of 317/325 cases in the project area and completed construction on the area handed over.
Currently, the ditch section about 100m long in lane 167 Thuy Khue and part of lane 123A Thuy Khue has not been constructed yet due to lack of clean ground. In addition, in the project area there are 8 cases where people have agreed to hand over the premises. But because the CT2 Xuan La building (area planned for resettlement) has not been put into use, the functional units have not been able to hand over resettlement houses to households.
Currently, the ditch section about 100m long in lane 167 Thuy Khue and part of lane 123A Thuy Khue has not been constructed yet due to lack of clean ground. In addition, in the project area there are 8 cases where people have agreed to hand over the premises. But because the CT2 Xuan La building (area planned for resettlement) has not been put into use, the functional units have not been able to hand over resettlement houses to households.
NGỌC THÙY
TIN LIÊN QUAN

Vướng mặt bằng, đường 474 tỉ ở Hòa Bình nguy cơ chậm tiến độ

Minh Chuyên |

Hòa Bình - Dự án cải tạo, nâng cấp đường tránh thành phố Hòa Bình gần 500 tỉ đồng có nguy cơ chậm tiến độ do vướng mắc trong công tác giải phóng mặt bằng.

Dự án cải thiện môi trường xung quanh mương Thụy Khuê: Khâu nào cũng chậm

Quỳnh Trang |

Theo phản ánh của người dân, trước khi khu vực này giải phóng mặt bằng tại Dự án cải thiện môi trường xung quanh mương Thụy Khuê (Tây Hồ, Hà Nội) họ đã phải đối mặt với tình trạng ô nhiễm nghiêm trọng trên đoạn mương này. Và đến nay, các hộ dân còn phải chịu ảnh hưởng của ô nhiễm tiếng ồn, khói bụi từ những công trình đang được tháo dỡ dang dở mà không rõ ngày hoàn thiện.

Công trình nhà ở của người dân tại 225 Thụy Khuê tạm dừng vì phải chờ vốn

ANH THƯ |

Công ty TNHH MTV Quản lý và Phát triển nhà Hà Nội đang liên hệ Sở Kế hoạch và Đầu tư để đề nghị xem xét bố trí vốn để tiếp tục triển khai công trình 225 Thuỵ Khuê.

Hiện trường cướp ô tô gây tai nạn liên hoàn ở Cần Thơ

QUANG PHƯƠNG |

Cần Thơ - Một đối tượng nghi sử dụng ma túy đã cướp ô tô tải gây tai nạn liên hoàn tại khu vực trước cổng Khu Công nghiệp Trà Nóc, quận Bình Thủy, TP Cần Thơ.

Biểu tượng tâm linh 70 tỉ đồng đang thi công ở Lào Cai

Đinh Đại |

Lào Cai - Sau khoảng 10 tháng thi công, dự án Tháp Kim Thành ở tỉnh biên giới Lào Cai đã thành hình.

Cục Thuế Bình Định cưỡng chế nợ thuế đối với Bamboo Airways

Hoài Phương |

Theo Cục Thuế tỉnh Bình Định, trường hợp Bamboo Airways không nộp đủ số tiền thuế nợ, Cục sẽ cưỡng chế ngừng sử dụng hóa đơn đối với công ty này.

Thêm một thi thể mất tích tại Làng Nủ được tìm thấy

Đinh Đại |

Lào Cai - Sau hơn 2 tuần tìm kiếm, lực lượng chức năng đã tìm thấy một thi thể mất tích do lũ quét xảy ra tại thôn Làng Nủ, xã Phúc Khánh, huyện Bảo Yên.

Cho thôi Đại biểu Quốc hội đối với Phó Bí thư Lâm Đồng

Lan Nhi |

Ủy ban Thường vụ Quốc hội đã ban hành Nghị quyết về việc cho thôi làm nhiệm vụ Đại biểu Quốc hội khóa XV đối với ông Trần Đình Văn.

Dự án cải thiện môi trường xung quanh mương Thụy Khuê: Khâu nào cũng chậm

Quỳnh Trang |

Theo phản ánh của người dân, trước khi khu vực này giải phóng mặt bằng tại Dự án cải thiện môi trường xung quanh mương Thụy Khuê (Tây Hồ, Hà Nội) họ đã phải đối mặt với tình trạng ô nhiễm nghiêm trọng trên đoạn mương này. Và đến nay, các hộ dân còn phải chịu ảnh hưởng của ô nhiễm tiếng ồn, khói bụi từ những công trình đang được tháo dỡ dang dở mà không rõ ngày hoàn thiện.

Công trình nhà ở của người dân tại 225 Thụy Khuê tạm dừng vì phải chờ vốn

ANH THƯ |

Công ty TNHH MTV Quản lý và Phát triển nhà Hà Nội đang liên hệ Sở Kế hoạch và Đầu tư để đề nghị xem xét bố trí vốn để tiếp tục triển khai công trình 225 Thuỵ Khuê.