The Thuy Khue ditch improvement project still has land problems

NGỌC THÙY |

After many years of implementation, up to now, the project to improve the environment of Thuy Khue ditch has not been completed because of land problems .

At the end of 2012, the project to improve the environment around the Thuy Khue drainage ditch was started with a capital of 400 billion VND invested by the People's Committee of Tay Ho district.
At the end of 2012, the project to improve the environment around the Thuy Khue drainage ditch was started with a capital of 400 billion VND invested by the People's Committee of Tay Ho district.
This is a ditch drainage project using a 2-lane box sewer system, with sidewalks on both sides along with a water supply system and lighting on the sewer surface. Initially, the local government determined that the project would be completed in 2017. However, up to now, the project is still being constructed in a "turtle" style, causing hundreds of households living along this ditch to live in squalor and pollution. .
This is a ditch drainage project using a 2-lane box sewer system, with sidewalks on both sides along with a water supply system and lighting on the sewer surface. Initially, the local government determined that the project would be completed in 2017. However, up to now, the project is still being constructed in a "turtle" style, causing hundreds of households living along this ditch to live in squalor and pollution. .
As noted by Labor on August 3, in the area of ​​alley 167 and 123A, Thuy Khue street, many items of the environmental improvement project are unfinished.
As noted by Labor on August 3, in the area of ​​alley 167 and 123A, Thuy Khue street, many items of the environmental improvement project are unfinished.
Some residential buildings of households have not yet been cleared for the project.
Some residential buildings of households have not yet been cleared for the project.
Around the area, there are many spontaneous garbage collection points, combined with open sewers, causing strong stench and pollution.
Around this area, there exist many spontaneous garbage collection points, combined with open sewers, causing strong stench and pollution.
According to feedback from Thuy Khue residents, although the project has been implemented for more than a decade, there are still some places on the route that have not been constructed, creating open ditch areas that are unsanitary. environment and urban aesthetics.
According to feedback from Thuy Khue residents, although the project has been implemented for more than a decade, there are still some places on the route that have not been constructed, creating open ditch areas that are unsanitary. environment and urban aesthetics.
Mr. Phan Anh Hai (residing in Thuy Khue street) said that people have posted garbage disposal signs in these sewer sections, but the situation of indiscriminate disposal of household garbage has not improved. Meanwhile, many construction sites are unfinished, causing the area to always be filled with dust.
Mr. Phan Anh Hai (residing in Thuy Khue street) said that people have posted garbage disposal signs in these sewer sections, but the situation of indiscriminate disposal of household garbage has not improved. Meanwhile, many construction sites are unfinished, causing the area to always be filled with dust.
"Not only does it cause environmental unsanitary conditions, the construction of the "turtle-crawling" project also affects the movement and daily activities of people. We encounter many difficulties and inconveniences," Ms. Vu Thu Hoa (residing in Thuy Khue) lamented.
"Not only does it cause environmental unsanitary conditions, the construction of the "turtle-crawling" project also affects the movement and daily activities of people. We encounter many difficulties and inconveniences," Ms. Vu Thu Hoa (residing in Thuy Khue) lamented.
According to the reporter's research, one of the main reasons why the project to improve the environment around the Thuy Khue drainage ditch is repeatedly behind schedule is because there is no clean ground to serve the construction.
According to the reporter's research, one of the main reasons why the project to improve the environment around the Thuy Khue drainage ditch is repeatedly behind schedule is because there is no clean ground to serve the construction.
Regarding this, Mr. Nguyen Hai Duong - Head of Land Clearance and Land Fund Development Department, Construction Investment Project Management Board of Tay Ho District (Hanoi) said that up to now, the project investor has received the premises of 317/ 325 cases in the project area and construction has been completed on the area handed over.
Regarding this, Mr. Nguyen Hai Duong - Head of Site Clearance and Land Fund Development, Tay Ho District Construction Investment Project Management Board (Hanoi) said that up to now, the project investor has continued to received premises of 317/325 cases in the project area and completed construction on the area handed over.
Currently, the ditch section about 100m long in lane 167 Thuy Khue and part of lane 123A Thuy Khue has not been constructed yet due to lack of clean ground. In addition, in the project area there are 8 cases where people have agreed to hand over the premises. But because the CT2 Xuan La building (area planned for resettlement) has not been put into use, the functional units have not been able to hand over resettlement houses to households.
Currently, the ditch section about 100m long in lane 167 Thuy Khue and part of lane 123A Thuy Khue has not been constructed yet due to lack of clean ground. In addition, in the project area there are 8 cases where people have agreed to hand over the premises. But because the CT2 Xuan La building (area planned for resettlement) has not been put into use, the functional units have not been able to hand over resettlement houses to households.
NGỌC THÙY
TIN LIÊN QUAN

Vướng mặt bằng, đường 474 tỉ ở Hòa Bình nguy cơ chậm tiến độ

Minh Chuyên |

Hòa Bình - Dự án cải tạo, nâng cấp đường tránh thành phố Hòa Bình gần 500 tỉ đồng có nguy cơ chậm tiến độ do vướng mắc trong công tác giải phóng mặt bằng.

Dự án cải thiện môi trường xung quanh mương Thụy Khuê: Khâu nào cũng chậm

Quỳnh Trang |

Theo phản ánh của người dân, trước khi khu vực này giải phóng mặt bằng tại Dự án cải thiện môi trường xung quanh mương Thụy Khuê (Tây Hồ, Hà Nội) họ đã phải đối mặt với tình trạng ô nhiễm nghiêm trọng trên đoạn mương này. Và đến nay, các hộ dân còn phải chịu ảnh hưởng của ô nhiễm tiếng ồn, khói bụi từ những công trình đang được tháo dỡ dang dở mà không rõ ngày hoàn thiện.

Công trình nhà ở của người dân tại 225 Thụy Khuê tạm dừng vì phải chờ vốn

ANH THƯ |

Công ty TNHH MTV Quản lý và Phát triển nhà Hà Nội đang liên hệ Sở Kế hoạch và Đầu tư để đề nghị xem xét bố trí vốn để tiếp tục triển khai công trình 225 Thuỵ Khuê.

Vụ công trình làm nứt nhà dân ở Hà Nội, chính quyền nói gì?

NHÓM PV |

Theo chính quyền phường Quang Trung, hình ảnh công nhân đang làm việc tại công trình số nhà 19, ngõ 136/98 Tây Sơn là để hút nước phòng dịch sốt xuất huyết.

Triều Tiên cho nổ tung tuyến đường bộ nối với Hàn Quốc

Khánh Minh |

Triều Tiên cho nổ tung các tuyến đường nối với Hàn Quốc vốn từng được coi là biểu tượng của sự hợp tác liên Triều.

Thân tín của bà trùm ma túy Oanh "Hà" được trả công 15 tỉ

Việt Dũng |

Trong số hơn 626kg ma túy mua bán xuyên quốc gia do bà trùm Oanh "Hà" cầm đầu, Nguyễn Văn Nam có mặt hầu hết ở các chuyến hàng, nhận công hậu hĩnh.

Bất cập tiền công đức 2 đền ở Ninh Bình do nguồn thu quá lớn

NGUYỄN TRƯỜNG |

Ninh Bình - Những tồn tại, bất cập trong việc quản lý tiền công đức tại đền Dâu và đền Quán Cháo (thành phố Tam Điệp) là do nguồn thu quá lớn.

Chánh văn phòng hãng luật bị tố đe dọa, xúc phạm phụ nữ

TRÍ MINH |

Một chánh văn phòng hãng luật bị tố cáo có hành vi đe dọa, xúc phạm danh dự, nhân phẩm phụ nữ. Người dân đã trình báo sự việc tới cơ quan công an.