More than 2,000 workers race overnight on the Can Tho - Ca Mau expressway project

Tạ Quang |

Can Tho - 2,100 workers and 1,150 machines are racing to complete the 110 km expressway before the opening date of December 19, 2025

Nhung ngay dau thang 12.2025 — khi thoi gian dang dan “can”, cac nha thau thi cong cao toc Can Tho – Ca Mau lien tuc lam viec ngay dem va duoi thoi tiet that thuong, de kip thong xe dung cam ket vao ngay 19.12.2025.
In early December 2025 - when time was gradually " Running out" - the contractors of the Can Tho - Ca Mau expressway continuously worked day and night and in erratic weather, to open the road on December 19, 2025.
Trao doi voi phong vien Bao Lao Dong, Trung ta Nguyen Thanh Vinh - Pho Giam doc Ban Truong Son Nam cho biet, tien do thi cong tuyen chinh do don vi phu trach da hoan thanh khoang 97% khoi luong, trong do phan tham be tong nhua da duoc thi cong xong. Cac hang muc con lai dang duoc trien khai va se hoan tat truoc ngay 12.12.
Speaking to Lao Dong Newspaper reporter, Lieutenant Colonel Nguyen Thanh Vinh - Deputy Director of Truong Son Nam Board said that the construction progress of the main route under the management of the unit has completed about 97% of the volume, of which the asphalt concrete pavement has been completed. The remaining items are being implemented and will be completed before December 12.
Dem 2.12, ghi nhan cua phong vien Bao Lao Dong tai mot so doan thuoc cao toc, doi ngu cong nhan — ky su van lam viec sau khi mat troi lan.
On the night of December 2, Lao Dong Newspaper reporters recorded that at some locations on the expressway, the team of workers - engineers were still working after the sunset.
Ong Nguyen Van Dat - Can bo ky thuat cua Ban Truong Son Nam cho hay, don vi da tranh thu thoi tiet thuan loi de tang toc thi cong o giai doan nuoc rut. Cac mui thi cong duoc bo tri lam viec lien tuc, duy tri suot dem den khoang 7 gio sang hom sau.
Mr. Nguyen Van Dat - Technical officer of Truong Son Nam Board said that the unit has taken advantage of favorable weather to speed up construction in the final stage. The construction teams were arranged to work continuously, staying all night until about 7:00 a.m. the next morning.
Tai doan Tong Cong ty 36 phu trach, ong Thai Duy Lien - Chi huy truong cong trinh thong tin, tinh den thoi diem nay, phan cau da hoan thanh toan bo, phan duong da thi cong dat 90%. Con 600m dang thi cong cap phoi da dam.
At the section managed by Corporation 36, Mr. Thai Duy Lien - Commander of the information project informed that the entire bridge section has been completed, the road section has reached 90%. The remaining 600m is under construction with crushed stone.
“Don vi dang trien khai dong loat cac mui thi cong va cam ket se hoan thanh dua du an thong xe vao ngay 19-12”, ong Thai Duy Lien neu ro.
"The unit is simultaneously implementing construction phases and is committed to completing the project to open to traffic on December 19," Mr. Thai Duy Lien stated.
Theo bao cao cua Ban Quan ly du an My Thuan, tinh den ngay 2.12, san luong uu tien thi cong dat 90%. Hien nay, cac don vi thi cong dang tap trung may moc thiet bi thi cong mong mat duong va he thong an toan giao thong.
According to the report of My Thuan Project Management Board, as of December 2, the priority construction output reached 90%. Currently, construction units are focusing on machinery and equipment for the construction of road foundations and traffic safety systems.
Toan du an da huy dong 1.150 may moc thiet bi, 2.100  nhan cong. Tap trung to chuc thi cong 3 ca, 4 kip dua du an hoan thanh dung tien do 19.12.2025.
The entire project has mobilized 1,150 machines and equipment, 2,100 workers. Focus on organizing 3 shifts and 4 teams to complete the project on schedule 19.12.2025.
Cao toc Can Tho – Ca Mau co chieu dai tuye chinh dai hon 110 km dang o giai doan nuoc rut. Voi tinh than “xuyen dem, bat chap mua gio”, cac luc luong thi cong dang no luc khong ngung de hoan thien toan bo du an, dap ung dung cam ket thong xe 19.12.2025.
The Can Tho - Ca Mau Expressway, with a main route length of more than 110 km, is in the final stage. With the spirit of "all night, regardless of rain or wind", the construction forces are making continuous efforts to complete the entire project, meeting the commitment to open to traffic.
Tạ Quang
RELATED NEWS

Commitment to handing over 100% of Ca Mau - Dat Mui expressway site before December

|

Ca Mau province commits to handing over 100% of the Ca Mau - Dat Mui expressway site before December 2025.

Officials wade through water to bring public services to people's homes in Can Tho

|

Can Tho - The model of bringing public services to people's homes helps people more conveniently in handling procedures and spreading the image of the government to the people.

40-day peak of connecting the expressway from Cao Bang to Ca Mau

|

Recently, at a meeting of the State Steering Committee for important national and key projects and works in the transport sector, Politburo member and Prime Minister Pham Minh Chinh said that the entire North-South expressway network and the connecting routes at both ends of the country will have to be completed on December 19. Thus, there are only about 40 days left for unfinished projects to speed up traffic opening, connecting from Cao Bang to Ca Mau.

122 photos that could turn the Nord Stream investigation around

|

There are opinions that Russia has the motive and opportunity to sabotage Nord Stream with images showing the activities of the Russian Navy near the explosion site.

Empty-handed after the flood, Da Nang farmers re-sow vegetables, race for Tet

|

Da Nang - The recent severe flood has submerged all the labor results of many households growing vegetables, pushing them into a state of total loss as the Tet crop is approaching.

A small alley in Hanoi suddenly became famous because of its very special name

|

In the heart of Hanoi, a small alley suddenly attracted attention because of its very special name "Happy Alley".

Haaland set a historic record in Man City's 5-4 win over Fulham

|

In the early morning of December 3 (Vietnam time), Man City won a dramatic victory over Fulham with a score of 5-4 on the day Erling Haaland entered the history of the Premier League.

Electric rice cooker assembly workshop in Hung Yen caught fire

|

Hung Yen - A fire broke out at a 300 m2 factory in Yen My commune, Hung Yen province and was extinguished promptly, causing no human casualties.

Commitment to handing over 100% of Ca Mau - Dat Mui expressway site before December

NHẬT HỒ |

Ca Mau province commits to handing over 100% of the Ca Mau - Dat Mui expressway site before December 2025.

Officials wade through water to bring public services to people's homes in Can Tho

Tạ Quang |

Can Tho - The model of bringing public services to people's homes helps people more conveniently in handling procedures and spreading the image of the government to the people.

40-day peak of connecting the expressway from Cao Bang to Ca Mau

NHÓM PV |

Recently, at a meeting of the State Steering Committee for important national and key projects and works in the transport sector, Politburo member and Prime Minister Pham Minh Chinh said that the entire North-South expressway network and the connecting routes at both ends of the country will have to be completed on December 19. Thus, there are only about 40 days left for unfinished projects to speed up traffic opening, connecting from Cao Bang to Ca Mau.