The hundred-billion residential area in Lang Son is unfinished and in ruins

Nhóm PV |

Lang Son - The central residential area of ​​Huu Lung town, after nearly 8 years of implementation, is still unfinished, with overgrown weeds in a desolate and unkempt scene .

1
Huu Lung Town Center Residential Area (Lang Son) has an area of ​​4 hectares, expected to accommodate more than 1,000 people. The project was approved by Lang Son Provincial People's Committee in October 2016 and implemented the same year. By the end of 2019, it was withdrawn, canceled, and re-bidding was organized.
By May 2020, the People's Committee of Lang Son province organized a bidding and selected the investor to implement the project, a joint venture of SDN Construction and Investment Design Consulting Joint Stock Company - Licogi Joint Stock Company13 construction foundation (in the district). Thanh Xuan, Hanoi City). Estimated implementation cost is 138 billion VND, this is a prime location in the center of Huu Lung town.
By May 2020, the People's Committee of Lang Son province organized a bidding and selected the investor to implement the project, a joint venture of SDN Construction and Investment Design Consulting Joint Stock Company - Licogi Joint Stock Company13 construction foundation (in the district). Thanh Xuan, Hanoi City). The estimated implementation cost is over 138 billion VND. This is a project with a prime location in the center of Huu Lung town.
Dxx
In July 2020, Lang Son Provincial People's Committee and the investor signed Contract No. 68 to implement the project with completion time in 30 months (ie January 2023). However, after completing some items, the project temporarily stopped implementation and fell into a state of inactivity.
As noted by the reporter at the beginning of August 2024, the project is still in disarray, unfinished, and in ruins. Many technical items have not been completed, and weeds are overgrown, causing loss of urban aesthetics.
As noted by the reporter at the beginning of August 2024, the central residential area of ​​Huu Lung town was still messy and unfinished. Many technical works have not been completed, weeds are overgrown in desolation, causing loss of urban beauty.
Some areas have become places where people gather materials.
Up to now, this residential area has shown no signs that construction will resume.
H
A resident of the project said that his family had more than 389 square meters of land recovered. Previously, thanks to livestock raising, each year they earned nearly 350 million. From 2016 until now, people have not dared to invest in livestock, leading to economic losses and unstable lives.
Materials are lying on the sidewalk, potentially unsafe for people and vehicles when traveling.
Meanwhile, many other households are living in degraded houses that cannot be repaired. Heavy rains flood them due to incomplete drainage systems and materials are scattered on walkways, making them unsafe.
6
Household waste is scattered widely in many places in unfinished residential areas, polluting the living environment for those who are still living there.
Some land areas have no people to live in, so they are used and covered with nets to create vegetable growing areas.
Currently, out of a total of 90 households and individuals affected by the project, more than half have not yet been handed over and coordinated with the inventory. Many households disagree because they think the compensation price for site clearance is not satisfactory.
Most of the project areas are overgrown with grass for a long time, wasting land resources and investment resources.
Over the past many years, households whose land was confiscated for the project have continuously reported and made recommendations to the authorities, hoping to soon resolve the project's problems so that people can soon stabilize their lives. However, to date the project is still unfinished.
On August 12, talking to reporters, Mr. Nguyen Quang Nhue - Chairman of Huu Lung Town People's Committee confirmed that the Central Residential Area project has not yet been completed.
On August 12, talking to reporters, Mr. Nguyen Quang Nhue - Chairman of Huu Lung Town People's Committee confirmed that up to now, the Huu Lung Town Center Residential Area Project has not been completed due to problems with land prices and solutions. ground clearance.
Hxbx
"In the new residential area, there are 2 households coming to build, the electricity and water lines are being done by the people themselves. The project has just been adjusted and the time limit extended, in addition, the competent authorities are actively removing the problems. Difficulties and problems with the premises", informed the leader of Huu Lung town.

Extend implementation time

In November 2023, the Department of Construction of Lang Son province issued report 414 on the proposal to sign an appendix to the Contract to implement the Huu Lung Town Center Residential Area Project. In particular, it is proposed that the People's Committee of Lang Son province amend the contract implementation term from 30 months to 62 months.

Accordingly, by October 2024, land will be forcibly recovered in cases where households do not hand over the premises. By the end of December 2024, land will be allocated to investors for implementation and acceptance and handover of the project from July to August 2025.

Nhóm PV
TIN LIÊN QUAN

Cảnh hoang tàn ở xã có 6 người chết và mất tích do mưa lũ

Khánh Linh |

Sơn La - Mưa lũ đã khiến 6 người chết và mất tích ở xã Chiềng Nơi, huyện Mai Sơn. Cảnh hoang tàn và tiếng khóc xé lòng của người ở lại khiến ai cũng xót xa.

Khu nhà công nhân hoang tàn thành tụ điểm hút chích ma túy

Lam Thanh |

Sau nhiều năm, dãy nhà công nhân, khu điều hành của Nhà máy xi măng Bắc Kạn (phường Xuất Hóa) đã trở thành bãi hoang tàn, cỏ dại mọc um tùm.

Hoang tàn dự án nhà máy sản xuất ôtô ở tỉnh nghèo nhất nước

Văn Tùng |

Dù được đầu tư 42 tỉ đồng nhưng Nhà máy sản xuất ôtô Tralas (TP Bắc Kạn) vẫn không thể hoạt động sau gần 20 năm, rơi vào cảnh hoang tàn và được chuyển đổi thành xưởng gỗ bóc gây lãng phí tài nguyên đất, ô nhiễm môi trường.

Trực tiếp bóng đá Argentina 3-0 Bolivia: Alvarez ghi bàn thứ ba

tam nguyên |

Trực tiếp trận Argentina vs Bolivia lúc 07h00 ngày 16.10, tại vòng loại World Cup 2026 khu vực Nam Mỹ.

Ngoài cầu Phong Châu, Phú Thọ còn rất nhiều cây cầu yếu

Bài và Ảnh: Tô Công |

Phú Thọ - Rất nhiều cây cầu nằm trên các tuyến tỉnh lộ đã cũ, yếu nhưng nhiều năm chưa được sửa chữa, hàng ngày vẫn "cõng" vô số loạt xe trọng tải lớn.

Ông Trump nhún nhảy 40 phút trong cuộc vận động tranh cử

Song Minh |

Cựu Tổng thống Donald Trump kết thúc cuộc vận động tranh cử ở Pennsylvania bằng cách nhún nhảy theo nhạc suốt 40 phút.

Vàng phát huy vai trò như một loại tiền tệ toàn cầu

Phương Anh (Theo Kitco) |

Theo Kitco - trước diễn biến căng thẳng địa chính trị, các ngân hàng trung ương có thể sử dụng vàng để thanh toán thương mại quốc tế.

Hezbollah kêu gọi ngừng bắn, nếu không sẽ giáng đòn "đau đớn"

Bùi Đức |

Hezbollah quyết giáng một đòn “đau đớn” lên Israel nếu chiến tranh vẫn tiếp tục ở Lebanon.

The scene of devastation in the commune has 6 people dead and missing due to floods

Khánh Linh |

Son La - Floods have left 6 people dead and missing in Chieng Noi commune, Mai Son district. The scene of devastation and the heart-wrenching cries of those left behind made everyone sad.

The ruined workers' housing area has become a drug gathering spot

Lam Thanh |

After many years, the row of workers' houses and the operating area of ​​the Bac Kan Cement Factory (Xuat Hoa ward) have become desolate , overgrown with weeds.

Desolate car factory project in the poorest province in the country

Văn Tùng |

Despite an investment of 42 billion VND, the Tralas Automobile Factory (Bac Kan City) still cannot operate after nearly 20 years, falling into ruin and being converted into a peeling wood factory, wasting land and air resources. environmental contamination.