Soc Trang speeds up sand mining, fuels expressway

PHƯƠNG ANH |

Soc Trang - Contractors and businesses are urgently speeding up the progress of sand exploitation to meet the demand for filling materials for the expressway project.

Hien tai, tinh Soc Trang da cap phep khai thac cho 4 mo cat song (MS 01, MS 03, MS 04 va MS 12) de phuc vu Du an Dau tu xay dung cong trinh duong bo cao toc Chau Doc - Can Tho - Soc Trang giai doan 1 (Du an thanh phan 4).
Currently, Soc Trang province has granted exploitation licenses to 4 river sand mines (MS 01, MS 03, MS 04 and MS 12) to serve the Chau Doc - Can Tho - Soc Trang Expressway Construction Investment Project Phase 1 (Component Project 4).
Sau Tet Nguyen dan 2025, cac nha thau, doanh nghiep khan truong huy dong thiet bi, phuong tien van chuyen de day nhanh tien do khai thac.
Immediately after the Lunar New Year, construction units mobilized maximum equipment and means of transportation, determined to complete the set goals.
Ghi nhan thuc te ngay 15.2, du la ngay nghi nhung khong khi lam viec khan truong tai cac mo cat. Tai mo cat MS 12 do Tong Cong ty Xay dung Truong Son khai thac phuc vu goi thau so 11. Cac phuong tien hoat dong lien tuc, xang cap miet mai dua cat len tau van chuyen ve cong trinh.
Recorded on February 15, although it is a day off, the working atmosphere is urgent at the sand mines. At MS 12 sand mine exploited by Truong Son Construction Corporation to serve package No. 11. Vehicles operate continuously, diligently carrying sand onto ships to transport to the construction site.
Theo thong ke, trung binh moi ngay mo MS 12 khai thac duoc khoang 1.700 m3 cat voi 2 xang cap va 23 phuong tien van chuyen.
According to statistics, on average, MS 12 mine exploits about 1,700 m3 of sand with 2 blades and 23 transport vehicles per day.
Tai mo cat MS 03 do Tong Cong ty Xay dung so 1 – CTCP dang khai thac phuc vu goi thau so 12 thuoc Du an thanh phan 4 hien co 4 tau hut va 33 phuong tien van chuyen. Trung binh hang ngay khai thac khoang 1.670 m3.
Similarly, at MS 03 sand mine exploited by Construction Corporation No. 1 - JSC to serve package No. 12, the exploitation capacity has also been increased. With 4 suction ships and 33 transport vehicles, the mine provides an average of 1,670 m3 of sand per day.
Ngoai 4 mo da khai thac, tinh Soc Trang con co 3 mo cat khac dang trong giai doan khao sat va danh gia tru luong, san sang bo sung nguon cung cho Du an thanh phan 4.
In addition to the 4 mines that have been exploited, Soc Trang province has 3 other sand mines in the survey and stock assessment stage, ready to supplement the supply for Component Project 4.
Lanh dao tinh Soc Trang da nhieu lan truc tiep den cac mo cat de kiem tra, don doc va kip thoi thao go nhung kho khan, vuong mac trong qua trinh khai thac.
Leaders of Soc Trang province have repeatedly visited the sand mines directly to inspect, urge and promptly remove difficulties and obstacles in the exploitation process.
Cat duoc van chuyen ve cong trinh phuc vu cong tac san lap.
The amount of sand exploited is continuously transported to the project, serving the work of leveling the roadbed.
Theo tinh toan cua So TNMT, den ngay 30.6.2025 (thoi han cuoi cung hoan thanh cong tac gia tai cho Du an thanh phan 4), tong khoi luong cat khai thac du kien dat khoang 2,4 trieu m³ (da tinh den viec tang cong suat khai thac tai cac mo MS 01, MS 03 va MS 04 tu dau thang 3).
According to calculations by the Department of Natural Resources and Environment of Soc Trang province, by June 30, 2025 (the deadline for completing the relocation work for Component Project 4), the total volume of sand exploited is expected to reach about 2.4 million m3 (increased exploitation capacity at MS 01, MS 03 and MS 04 mines since the beginning of March).

PHƯƠNG ANH
TIN LIÊN QUAN

Soc Trang speeds up sand mining for expressways

|

Soc Trang - Contractors and businesses need to exploit the correct capacity according to the license; increase sand exploitation capacity at mines to ensure the quantity of sand for the expressway.

76km road through Ho Chi Minh City and 3 provinces at risk of delay due to lack of sand

|

HCMC - The 76-km Ring Road 3 project through HCMC and three provinces is expected to open some sections this year but faces the risk of delays due to a lack of sand for filling.

Secretary, President of Soc Trang went to Cat Nhi mine to urge the supply

|

Soc Trang - leaders of Soc Trang province directly checked and urged sand mines to enhance exploitation, ensuring supply for the highway project.

Madam Pang apologizes for Thailand women's team's inability to compete in Asian tournament

|

President of the Football Association of Thailand (FAT) Madam Pang has written a letter of apology to fans after the Thai women's team could not participate in the 2026 Women's Asian Cup.

Difficult problem of real estate enterprises when calling for capital in bonds

|

The story of real estate businesses calling for capital through bonds will be very "hot" in the coming time with maturity pressure and new criteria.

In the middle of the night, a couple drowned while driving into a dam in Quang Ninh

|

Quang Ninh - A serious drowning incident occurred last night at Ben Chau dam, Binh Khe ward, Quang Ninh province, killing a couple.

Ministry of Health blocks self-declared road, tightens functional foods

|

Tightening the management of functional foods, businesses will no longer be allowed to self-declare products as before.

Ukrainian President Optimistic After Phone call with Trump

|

Ukrainian President Zelensky praised the July 5 phone call with President Trump, expressing optimism about the aid of patriot air defense systems.

Soc Trang speeds up sand mining for expressways

PHƯƠNG ANH |

Soc Trang - Contractors and businesses need to exploit the correct capacity according to the license; increase sand exploitation capacity at mines to ensure the quantity of sand for the expressway.

76km road through Ho Chi Minh City and 3 provinces at risk of delay due to lack of sand

MINH QUÂN |

HCMC - The 76-km Ring Road 3 project through HCMC and three provinces is expected to open some sections this year but faces the risk of delays due to a lack of sand for filling.

Secretary, President of Soc Trang went to Cat Nhi mine to urge the supply

PHƯƠNG ANH |

Soc Trang - leaders of Soc Trang province directly checked and urged sand mines to enhance exploitation, ensuring supply for the highway project.