Soc Trang speeds up sand mining for expressways

PHƯƠNG ANH |

Soc Trang - Contractors and businesses need to exploit the correct capacity according to the license; increase sand exploitation capacity at mines to ensure the quantity of sand for the expressway.

Not yet fully exploited the licensed capacity

Mr. Ngo Thai Chan - Director of the Department of Natural Resources and Environment (TNMT) of Soc Trang province, said that the province currently has 4 river sand mines licensed for exploitation (MS 01, MS 03, MS 04 and MS 12) to serve the Chau Doc - Can Tho - Soc Trang Expressway Construction Investment Project Phase 1 (Component Project 4).

However, the exploitation capacity of the 3 mines (MS 03, MS 04 and MS 12) has not yet reached the maximum level according to the license. MS 04 mine is currently only exploiting an average of 700 m3/day (licensed capacity of 1,850 m3/day), MS 03 mine is 1,670 m3/day (capacity of 2,695 m3/day) and MS 12 mine is 1,700 m3/day (capacity of 3,000 m3/day).

According to the calculation of the Department of Natural Resources and Environment, by June 30, 2025 (the deadline for completing the relocation work for Component Project 4), the total volume of sand exploited is expected to reach about 2.4 million m3, (calculated for increasing the exploitation capacity at MS 01, MS 03 and MS 04 mines from the beginning of March).

Mot mo cat duoc khai thac phuc vu Du an thanh phan 4. Anh: Phuong Anh
A sand mine is exploited to serve Component Project 4. Photo: Phuong Anh

A representative of a contractor said that the slow exploitation came from many causes, including lack of transportation and exploitation equipment, prolonged sand transportation time to the project and the impact of tides.

Increasing mining capacity

Faced with the above situation, the Department of Natural Resources and Environment of Soc Trang province has proposed that the Provincial People's Committee direct investors, construction contractors and enterprises to ensure correct exploitation capacity according to the license. The Department also proposed to urgently complete procedures related to increasing sand mining capacity at mines and conduct surveys of areas proposed by contractors for expansion.

Chu tich UBND tinh Soc Trang Tran Van Lau yeu cau cac nha thau, doanh nghiep day nhanh tien do, khai thac dung cong suat cap phep. Anh: Phuong Anh
Chairman of Soc Trang Provincial People's Committee Tran Van Lau requested contractors and enterprises to speed up progress and exploit licensed capacity properly. Photo: Phuong Anh

On February 14, during a working session on the sand exploitation situation for Component Project 4, Chairman of Soc Trang Provincial People's Committee Tran Van Lau emphasized the completion of the relocation work by June 30, 2025 and requested relevant units to make every effort to achieve this goal.

"Investors and contractors must speed up the progress, considering the option of working a full day off. If there are any difficulties, we must give opinions to competent authorities for timely consideration and resolution," said Mr. Lau.

The Chairman of the People's Committee of Soc Trang province requested contractors and enterprises to speed up the exploitation progress at the mines, prepare adequate means to ensure that when increasing the exploitation capacity, there will be vehicles immediately.

"Contractors and mine owners must comply with the law, have strict commitments and exploitation regulations, avoid taking advantage of special mechanisms to exploit for the wrong purpose, and not bringing sand to the expressway," Mr. Lau noted.

The leaders of Soc Trang Provincial People's Committee also requested investors to launch a peak period of emulation, study reward mechanisms and sanctions for cases of delays and lack of responsibility of contractors in performing their tasks.

PHƯƠNG ANH
TIN LIÊN QUAN

Secretary, President of Soc Trang went to Cat Nhi mine to urge the supply

|

Soc Trang - leaders of Soc Trang province directly checked and urged sand mines to enhance exploitation, ensuring supply for the highway project.

Tien Giang approves environmental impact assessment of 3 sand mines

|

Tien Giang - Tien Giang Provincial People's Committee has approved the environmental impact assessment for 3 sand mining projects on Tien River, with a total exploitation capacity of 968,899 m3/year.

The total donation fee of Yen Tu Relic Management Board for the year is only over 300 million VND

|

Quang Ninh - In 2024, the total amount of donations to the Yen Tu National Monuments and Forest Management Board will be only about 320 million VND.

The Ministry of Home Affairs talks about the bonus regime for education civil servants

|

The Ministry of Home Affairs has responded to readers regarding the implementation of the bonus regime for cadres, civil servants, and public employees, including civil servants in the education sector.

Then it's time for major US oil and gas corporations to return to Russia

|

Major US oil and gas corporations will soon return to Russia in the future, according to Director of the Russian Direct Investment Fund (RDIF) Kirill Dmitriev.

Female workers struggle to find a job when over 40 years old

|

Losing jobs is the most difficult thing for workers, especially for older female workers, it is an even more difficult challenge to overcome...

Car overturned, road blocked to La Lay International Border Gate

|

Quang Tri - The truck overturned across the road, causing a blockage of the road to La Lay International Border Gate.

Quang Nam - Thanh Hoa match has no coach

|

Both Quang Nam and Thanh Hoa teams do not have the direction of the head coach in the make-up match of round 11 of V.League 2024-2025.

Secretary, President of Soc Trang went to Cat Nhi mine to urge the supply

PHƯƠNG ANH |

Soc Trang - leaders of Soc Trang province directly checked and urged sand mines to enhance exploitation, ensuring supply for the highway project.

Tien Giang approves environmental impact assessment of 3 sand mines

Thành Nhân |

Tien Giang - Tien Giang Provincial People's Committee has approved the environmental impact assessment for 3 sand mining projects on Tien River, with a total exploitation capacity of 968,899 m3/year.

Bắt quả tang 2 tàu sang mạn cát lậu trên sông Hậu

PHƯƠNG ANH |

Sóc Trăng - Lực lượng chức năng vừa bắt quả tang 2 tàu vỏ thép đang thực hiện sang mạn, mua bán cát không rõ nguồn gốc trên sông Hậu.