The land use extension period for VNPT projects in Hanoi has expired

Nhóm phóng viên |

Lao Dong Newspaper has just published an article reflecting the abandoned VNPT project in Cau Giay, Hanoi, which increased its capital by more than 1,417 billion VND compared to 2024.

Department of Agriculture and Environment responds to information

After the newspaper was published, the Hanoi Department of Agriculture and Environment issued a written response to Lao Dong Newspaper.

On May 26, 2025, Mr. Nguyen Minh Tan, Deputy Director of the Hanoi Department of Agriculture and Environment signed document No. 2580/SNNMT-TTr on information on the use of land lot A3 of Cau Giay new urban area, Dich Vong ward, Cau Giay district.

According to the Department of Agriculture and Environment, on October 13, 2021, the Hanoi People's Committee issued Decision No. 4438/QD - People's Committee on extending land use for 24 months for the Vietnam Post and Telecommunications Group (VNPT) for the National Telecommunications Trading and Operation Center Construction Investment Project at Lot A3 of Cau Giay New Urban Area, Dich Vong Hau Ward.

The Hanoi Department of Agriculture and Environment chaired an interdisciplinary team to conduct a post-inspection on this issue. According to the post-inspection results, up to now, the land has been allocated to VNPT for an extension period without putting the land into use.

However, the Department of Agriculture and Environment has advised and was decided by the Chairman of the City People's Committee to apply the force majeure time not to be included in the time of extension of land use for investment projects to build the National Telecommunications Transaction Center at Lot A3 of Cau Giay New Urban Area, Dich Vong Hau Ward, invested by the Vietnam Post and Telecommunications Group as the investor (as prescribed at Point e, Clause 1, Article 31 of Decree No. 31/ND-CP dated 30.2024 coverage).

According to the provisions of Point e, Clause 1, Article 31 of Decree No. 102/2024/ND-CP, it is stipulated as follows: Administrative decisions and administrative acts of competent state agencies are objective obstacles, not due to the fault of the land user, directly affecting land use.

Regarding the issue of land allocation, VNPT representative also said that on April 2, 2025, the Hanoi Department of Agriculture and Environment (DONRE) issued Inspection Conclusion No.7/KL-SNNMT on the implementation of the Inspection Conclusion and Decision to extend land use for 24 months for VNPT Group in using land at lot A3. On April 10, 2025, the Hanoi People's Committee issued Document No. 1352/UBND-NNMT on the management and use of land by VNPT at lot A3, Cau Giay new urban area, Dich Vong Hau ward, Cau Giay district, Hanoi.

VNPT said that in 2025, if the Hanoi People's Committee extends the land use period, VNPT will review and adjust the contents of the project in accordance with current regulations with the scale and total investment as approved.

Thus, it can be seen that by the time the Department of Agriculture and Environment responded to Lao Dong Newspaper, VNPT's land plot was not clear whether it could be extended or not? and when will it be extended? Because a prime land plot located in the middle of the capital has been cleared, has been allocated land, extended land use but has not been implemented, it both causes loss of urban beauty and poses a potential risk of increasing costs and causing waste?

No response to capital increase

Previously, Lao Dong Newspaper reported that the National Telecommunication Trading and Operation Center Project, invested by Vietnam Post and Telecommunications Group (VNPT), was planned to be implemented in 2010.

The project is located on lot A3, Cau Giay new urban area, Dich Vong Hau ward, Cau Giay district, Hanoi, and is expected to play a central role in the management and operation of the national telecommunications network.

However, according to a survey by Lao Dong Newspaper reporters in April and May 2025, this land is still an empty lot fenced with corrugated iron. Observation from above shows overgrown weeds, inside there are many scraps such as old rubber tires, household waste, there is no sign that the construction site is under construction.

According to documents from Lao Dong Newspaper, this project has a sudden increase in capital compared to 2024. According to VNPT's general target report and 2024 business plan, the project at lot A3 is included in the list of unfinished group A projects, and will be transferred to 2024 for continued implementation, with a total investment (including VAT) of more than VND 2,796 billion.

However, in the general target report and business plan for 2025, VNPT said that the total investment of this project is more than VND 4,213 billion, an increase of more than VND 1,417 billion compared to 2024.

Not only increasing capital, the disbursement progress of the project also has a notable adjustment in VNPT's own reports.

At the report on evaluation of the results of the implementation of the production and business plan in 2022 (signed on June 29, 2023), the total value of the project was recorded as VND 94 billion. However, in the report in 2023 (signed on 24.6.2024) after 1 year, the value of implementation decreased to 68 billion dong - ie by 26 billion dong compared to the previous year report.

Reporters of Lao Dong Newspaper have contacted VNPT many times to learn about the total investment of the project and the disbursement process, but so far the unit has not responded to this issue.

Nhóm phóng viên
TIN LIÊN QUAN

VNPT's abandoned project increases capital by more than 1,417 billion VND compared to 2024

|

An abandoned VNPT project with a total investment of VND2,796 billion announced in 2024 has been adjusted to VND4,213 billion in 2025.

VNPT's responsibility when fishermen lose connection to the journey

|

Quang Binh - The satellite disconnection incident has made it difficult for fishermen to submit documents, VNPT has not yet provided data on the disconnected journey.

Fire at VNPT Tien Giang building: Mobile bag rental is in operation

|

Tien Giang - VNPT's staff have made efforts to fix the problem and have restored VinaPhone, 3G, 4G mobile subscriber services on March 16.

Home team Da Nang shines brightly on the opening night of DIFF 2025

|

Da Nang - The fireworks display "Cultural quintessence" by the home team Da Nang caused an explosion of emotions at DIFF 2025.

Relieve summer heat at the beach of a pristine church in Nam Dinh

|

Nam Dinh - The beach of the church in Hai Ly commune, Hai Hau district is famous for its wild beauty, suitable for visitors to experience and avoid the heat of summer.

Y Nhi stops at top 40, Thai Beauty crowned Miss World 2025

|

Thai beauty - Opal Suchata Chuangsri crowned Miss World 2025. Meanwhile, the representative of Vietnam - Huynh Tran Y Nhi stopped at the top 40.

Clip of husband assaulting wife in front of elderly father and young child appears

|

Tuyen Quang - Originating from a family conflict, a woman in Vinh Loi commune (Son Duong district) was assaulted by her husband to the point of hospitalization.

A new breeze for Vietnamese women's volleyball at AVC Nations Cup 2025

|

The combination of experience and youth promises to create a new look for the Vietnam women's volleyball team at the AVC Nations Cup 2025.

VNPT's abandoned project increases capital by more than 1,417 billion VND compared to 2024

Nhóm Phóng viên |

An abandoned VNPT project with a total investment of VND2,796 billion announced in 2024 has been adjusted to VND4,213 billion in 2025.

VNPT's responsibility when fishermen lose connection to the journey

CÔNG SÁNG |

Quang Binh - The satellite disconnection incident has made it difficult for fishermen to submit documents, VNPT has not yet provided data on the disconnected journey.

Fire at VNPT Tien Giang building: Mobile bag rental is in operation

Thành Nhân |

Tien Giang - VNPT's staff have made efforts to fix the problem and have restored VinaPhone, 3G, 4G mobile subscriber services on March 16.