Failure to disburse public investment capital is also a big waste

Lê Thanh Phong |

Regarding the delayed implementation of investment projects, speaking at the National Assembly's group discussion session on the afternoon of October 26, General Secretary To Lam commented: "Whose fault is it? It's all our fault, why do we keep making things difficult for ourselves when we see obstacles? Solve them one by one, look at each one and solve them. What kind of regulations are there that even the State can't do, how can businesses do it?"

The General Secretary pointed out that what people and businesses are concerned about is that regulations are set by humans, so why not remove them?

Public investment capital left in the “pocket” is a huge waste. The General Secretary gave an example, that is the flood prevention project in Ho Chi Minh City after 2 terms but people still suffer from flooding.There are many projects across the country, due to land clearance problems, for example, some localities have completed a bridge, but there is no access road so the bridge is exposed to the sun and rain.

Many roads are almost completed, but because a section has not been compensated for clearance, they are not finished for exploitation, which is a huge waste.Public hospitals and public facilities, unfinished construction, have been left to deteriorate seriously, becoming abandoned sites and scrap warehouses.

On October 21, 2024, Lao Dong Newspaper published an article "Dozens of billions of dong worth of office buildings unfinished for many years in Nghe An" reflecting that some agency and unit headquarters were invested with tens and hundreds of billions of dong, but the unfinished construction lasted for a long time, causing waste.Many other localities have similar projects, not only money is spent, but land is wasted month after month and year after year.

In addition to problems with site clearance, investment projects cannot be implemented because local leaders are afraid of making mistakes and avoid responsibility.Regarding this situation, it is partly due to the capacity of officials, but partly due to unclear legal regulations.Therefore, there must be sufficient legal regulations for individuals to determine their authority and responsibility in a transparent manner, only then will they dare to do it, dare to take responsibility, not push it around or avoid it.

The law clearly stipulates decentralization, delegation of authority, which tasks belong to the central level, the local level, which is also the basis for assessing management and operation capacity.If a project is not implemented or delayed, it will immediately point out where the bottleneck is, who, which agency is responsible.

If we want investment projects to be implemented quickly and smoothly, what needs to be done is to minimize administrative procedures, reduce unnecessary regulations, and request-grant procedures.These procedures hinder the progress of projects and generate negative costs, affecting the quality of projects and works.

Lê Thanh Phong
RELATED NEWS

The thing social housing investors fear most is the procedures

|

Investment procedures for social housing projects are still complicated and lengthy, with some regulations overlapping, leading to congestion.

Urgently remove investment obstacles, resolve "having money but not being able to spend it"

|

Reviewing and removing obstacles in project investment in localities across the country is an urgent requirement, as General Secretary To Lam emphasized, we must coordinate, not blame each other or wait for each other.

Prime Minister welcomes UAE businesses to invest in Vietnam

|

Prime Minister Pham Minh Chinh supports and welcomes the cooperation plan of UAE corporations with Vietnam.

President Trump declares the US will win very quickly if there is a renewed conflict with Iran

|

US President Donald Trump left open the possibility of a recurrence of conflict with Iran, while affirming that the US will "win very quickly" if that happens.

In 6 months, the Traffic Police Department received more than 10,600 violation complaints from people

|

In 6 months, the Traffic Police Department received more than 10,600 traffic violation complaints from people, thereby fining more than 2,800 cases.

Forecast of heavy rain in the area from today to July 10, with some places over 200mm

|

From July 9th to the end of July 10th, it is forecast that the mountainous and midland areas of the Northern region and Quang Ninh will have moderate rain, heavy rain and thunderstorms, with locally very heavy rain over 200mm.

Barricating many sections of Thang Long Avenue for construction until the end of 2026

|

Hanoi barricades and diverts traffic on many sections of Thang Long Avenue to construct Ring Road 3.5 intersection. Traffic organization plan extended until the end of 2026.

What is special about the first patients at Viet Duc Friendship Hospital, Ninh Binh facility

|

On the first day of operation, Viet Duc Friendship Hospital Ninh Binh facility organized free health check-ups and presented gifts to nearly 300 people with meritorious services and policy families.

The thing social housing investors fear most is the procedures

Bảo Chương |

Investment procedures for social housing projects are still complicated and lengthy, with some regulations overlapping, leading to congestion.

Urgently remove investment obstacles, resolve "having money but not being able to spend it"

Lam Duy |

Reviewing and removing obstacles in project investment in localities across the country is an urgent requirement, as General Secretary To Lam emphasized, we must coordinate, not blame each other or wait for each other.

Prime Minister welcomes UAE businesses to invest in Vietnam

Thanh Hà |

Prime Minister Pham Minh Chinh supports and welcomes the cooperation plan of UAE corporations with Vietnam.