Ensuring conditions to start construction of the North - South high-speed railway before December 31, 2026

PHẠM ĐÔNG |

The North-South high-speed railway project will be organized to select contractors, sign contracts and ensure conditions to start construction before December 31, 2026.

The Government has just issued Resolution No. 106/NQ-CP dated April 23, 2025 on the plan to implement Resolution No. 172/2024/QH15 of the National Assembly on the investment policy for the high-speed railway project on the North-South axis.

According to the resolution, the scale of the construction of the high-speed railway line on the North - South axis with a total length of about 1,541km, a design speed of 350 km/h, a load of 22.5 tons/axle; 23 passenger stations, 5 freight stations; investment in vehicles and equipment to transport passengers, meeting dual-use requirements for national defense and security, and being able to transport goods when necessary.

The Resolution clearly states the development and promulgation of Government Decrees, including:

1. The Decree stipulates the contents, requirements for surveying, creating overall technical designs (Feed designs) instead of the basic design in the project feasibility study report and the design steps after the Feed design, making and managing construction investment costs of the project application of Feed design;

Guidelines on the obligations and powers of the parties participating in the implementation of the contract under the form of an EPC contract (investor, contractor/general contractor EPC, supervision consultant...); detailed regulations and instructions on planning, adjusting zoning plans, and detailed planning of areas adjacent to high-speed railway stations.

2. The Decree stipulates the criteria for selecting organizations and state-owned enterprises assigned tasks or Vietnamese organizations and enterprises allowed to order the provision of railway industrial services and goods.

3. The Decree guides the implementation of railway science and technology development and details the research, application and receipt of technology transfers for railway projects.

4. Decree guiding the temporary use of forests and forest return for temporary construction to serve railway projects.

In addition, develop and promulgate a Decision of the Prime Minister regulating the list of railway industrial services and goods assigned to state-owned organizations and enterprises or ordered from Vietnamese organizations and enterprises.

Regarding project implementation, the resolution clearly states that the Ministry of Construction is the governing body, coordinating with relevant ministries, branches and localities, organizing the preparation and submission to the Prime Minister for decision to approve the project and organizing implementation to meet the required progress.

The progress milestones for implementing some main tasks and tasks are as follows:

Organize the selection of consulting contractors to conduct surveys, prepare feasibility study reports and carry out related work, and submit the Feasibility Study Report to the Prime Minister in August 2026.

The State Appraisal Council appraised and submitted to the Prime Minister for decision to approve the Project Feasibility Study Report in September 2026.

Localities and Vietnam Electricity Group will carry out compensation, support, resettlement, and relocation of power lines affected by the project, basically completing before December 2026 to hand over the site to the construction contractor.

Organize the selection of contractors for the project implementation phase, sign contracts and ensure conditions to start construction before December 31, 2026.

Deploy construction, procurement, equipment installation, basically complete the project and put it into operation from 2035 according to Resolution No. 172/2024/QH15 of the National Assembly.

PHẠM ĐÔNG
RELATED NEWS

Submitting to the National Assembly the mechanism for appointing the North-South high-speed railway bidding in May

|

The Ministry of Construction was assigned to the Government to supplement the mechanism for appointing bids for the North-South high-speed railway project; the Government submitted to the National Assembly in May.

The Prime Minister asked Thaco to research and produce high -speed railway wagon

|

The Prime Minister proposed Thaco to participate in research, technology transfer, producing high -speed railway cars.

Specific policies for the North-South high-speed railway

|

National Assembly Chairman Tran Thanh Man has just signed and issued Resolution No. 172/2024/QH15 of the National Assembly on the investment policy for the North-South high-speed railway project.

Hon Vong Phu faces debate, functional sectors get involved

|

Thanh Hoa - After public opinion paid attention to reinforcing the Hon Vong Phu relic, functional agencies intervened to inspect and clarify information.

Failing in the semi-finals, the father of the U23 Vietnam captain sends his belief in the journey ahead

|

After the defeat in the semi-finals, people in the hometown of the U23 Vietnam captain have faith in the future journey of the team.

Trung Kien admits U23 China played differently in the semi-final

|

Goalkeeper Trung Kien admitted that U23 China played tightly and sharply and said that U23 Vietnam will make efforts to recover for the third-place match.

Old Tet atmosphere recreated in the Old Quarter of Hanoi

|

Hanoi - "Vietnamese Spring Tet Market - Tet Pho 2026" recreates the old Northern Tet space, attracting tourists and young people to find traditional Tet values.

Hieu Minh at risk of ligament injury

|

In the 2026 AFC U23 Championship semi-final match between U23 Vietnam and U23 China on the evening of January 20, central defender Hieu Minh suffered an injury and was forced to leave the field early.

Submitting to the National Assembly the mechanism for appointing the North-South high-speed railway bidding in May

PHẠM ĐÔNG |

The Ministry of Construction was assigned to the Government to supplement the mechanism for appointing bids for the North-South high-speed railway project; the Government submitted to the National Assembly in May.

The Prime Minister asked Thaco to research and produce high -speed railway wagon

PHẠM ĐÔNG - Hoàng Bin |

The Prime Minister proposed Thaco to participate in research, technology transfer, producing high -speed railway cars.

Specific policies for the North-South high-speed railway

CAO NGUYÊN |

National Assembly Chairman Tran Thanh Man has just signed and issued Resolution No. 172/2024/QH15 of the National Assembly on the investment policy for the North-South high-speed railway project.