In Mai Son Industrial Park, BHL Food Ingredients Processing Joint Stock Company is rushing to complete the bien the starch processing factory with a total investment of 244 billion VND, capacity of 90,000 tons/year.
After nearly 5 months of construction, the project has reached about 90% of the volume, completing the factory, chemical area, refinery, clean water supply system...Currently, the investor and contractor are mobilizing human resources to install machinery, complete wastewater treatment, electrical system, striving to inaugurate in September 2025.

Ms. Chu Thi Kim Oanh - Deputy Director of BHL Son La Agricultural Products Processing Joint Stock Company said that the Company has basically completed the construction of factories, operating houses, clean water supply systems and fire prevention and fighting.
"We are mobilizing maximum human resources and equipment to speed up progress, complete wastewater treatment tanks, electricity and drainage systems, determined to inaugurate in September 2025, in accordance with our commitment to the province" - Ms. Oanh affirmed.
Also included in the group of projects to celebrate the 16th Provincial Party Congress, the Son La Central Province Wastewater Drainage and Treatment System Project in Tong village, Chieng An ward, with a total capital of more than 900 billion VND is also being urgently constructed to inaugurate on the occasion of the National Day on September 2.

In addition to the above 2 projects, Son La province also selected 6 other projects to start construction to celebrate the 16th Provincial Party Congress, including: Provincial Road 120C Project (Yen Chau - Ta Khoa), Provincial Road 107C Project (Muong Chien - Nam So, Lai Chau), Hua Chien village road project - Nam Chien hydropower plant, Chieng Mai - Phieng Cam road project, Mavin Mai Son animal feed production and processing complex project and Moc Chau - Mai Chau 110kV transmission line relocation project (old Hoa Binh province).
Mr. Nguyen Anh Tuan - Director of Mavin Mai Son Company Limited shared, "We have received active support from the Provincial People's Committee and the Industrial Park Management Board. The goal is to complete the project on schedule and put it into production in early 2026".
Notably, the provincial road project 120C is 34.3km long, with a total investment of 700 billion VND. The project is expected to break the monopoly of National Highway 37, connect inter-regionalally, and expand development space.
Up to now, Yen Chau commune and the Project Management Board have counted and set land clearance markers for 179 affected households.
Currently, contractors are gathering equipment, implementing construction, striving to complete ahead of schedule.
With high political determination and the synchronous participation of all levels, sectors and people, Son La is accelerating the progress of bringing key projects to the finish line, creating a solid foundation for the development of the period 2025 - 2030, welcoming the 16th Provincial Party Congress.