New information on the progress of the Nam Thang Long urban railway project

PHẠM ĐÔNG |

Hanoi has completed and submitted to the Prime Minister an adjustment to the investment policy for the Nam Thang Long - Tran Hung Dao urban railway project.

This afternoon (December 6), Prime Minister Pham Minh Chinh chaired the 15th meeting of the State Steering Committee for important national projects and works, key to the transport sector.

The meeting aims to review and urge the work after the 14th meeting and discuss solutions, continue to remove difficulties and obstacles, and speed up the progress of works and projects.

According to the report of the Ministry of Transport, at the 14th meeting, the Prime Minister assigned 83 tasks to ministries, branches and localities, focusing on removing difficulties and obstacles, and speeding up procedures for preparing investment projects.

Of these, 33 tasks are regular direction and management tasks, currently being actively coordinated and implemented by agencies and units.

Regarding the remaining 50 specific tasks, 41 tasks have been completed on time, including key tasks such as the Ministry of Planning and Investment completing the appraisal of the Ninh Binh-Hai Phong project through Nam Dinh and Thai Binh and the North-South high-speed railway project.

The Ministry of Natural Resources and Environment guides Lang Son province on traffic land indicators at the Dong Dang-Tra Linh project; guides Tien Giang province on sand mining in areas overlapping with the waterway and waterway protection corridor; approves the environmental impact assessment report of the Ninh Binh-Hai Phong project through Nam Dinh and Thai Binh.

The Ministry of Agriculture and Rural Development will guide localities on changing forest use purposes immediately after the National Assembly Standing Committee passes a Resolution on adjusting the policy on changing forest use purposes for the North-South expressway project in the eastern region for the 2020-2025 period.

The Ministry of Transport, on behalf of the Government, authorized by the Prime Minister, submitted and received approval from the National Assembly for the investment policy of the high-speed railway project on the North-South axis and adjusted the investment policy of the Long Thanh International Airport project; advised the Government to issue a Resolution on the implementation of the Gia Nghia-Chon Thanh project.

Report to the Government Standing Committee on the investment policy to expand the Ho Chi Minh City-Long Thanh expressway; coordinate with the Central Committee of the Ho Chi Minh Communist Youth Union to launch a voluntary emulation campaign to support the completion of 3,000km of expressway.

Ho Chi Minh City completes pre-feasibility study report for Ho Chi Minh City Ring Road 4 project and submits to the Prime Minister.

Hanoi City and Cao Bang Province have completed and submitted to the Prime Minister adjustments to the investment policy for the Nam Thang Long-Tran Hung Dao urban railway project and the Dong Dang-Tra Linh expressway; the Prime Minister has approved adjustments to the investment policy for the Dong Dang-Tra Linh expressway project.

Ha Noi da hoan thien va trinh Thu tuong Chinh phu dieu chinh chu truong dau tu du an duong sat do thi Nam Thang Long - Tran Hung Dao. Anh: VGP
Hanoi has completed and submitted to the Prime Minister an adjustment to the investment policy for the Nam Thang Long-Tran Hung Dao urban railway project. Photo: VGP

Binh Duong, Son La and Thai Binh provinces approved the Feasibility Study Report for the Ho Chi Minh City-Thu Dau Mot-Chon Thanh, Hoa Binh-Moc Chau, Ninh Binh-Hai Phong expressway projects through Nam Dinh and Thai Binh.

Regarding the implementation of projects, in recent times, ministries, branches and localities have made efforts and proactively overcome difficulties to carry out work. Most projects are being implemented closely following the set plan.

With the strong direction of the Prime Minister at the 14th meeting, localities have actively implemented site clearance work and there have been significant changes, with the handed-over area increasing by over 20%.

PHẠM ĐÔNG
TIN LIÊN QUAN

Reduce the ideological and psychological pressure of civil servants when arranging the apparatus

|

According to the Government, to limit the impact of the restructuring and streamlining of the apparatus on cadres and civil servants, there needs to be strong and outstanding policies.

Decentralization and complete decentralization when building urban railways

|

On December 5, Politburo member, Prime Minister Pham Minh Chinh, Head of the State Steering Committee for important national projects and works, key to the transport sector, chaired a meeting of the Government Standing Committee with the Ministry of Transport, the People's Committees of Hanoi and Ho Chi Minh City and relevant ministries and branches on the urban railway system project in Hanoi and Ho Chi Minh City.

Prime Minister directs investigation to clarify accident in Military Region 7

|

The Prime Minister requested to quickly overcome the consequences and clarify the cause of the accident during the exercise in Military Region 7.

Why was Vietnam not awarded a penalty against the Philippines?

|

The impact of Ugelvik from the Philippines on Vu Van Thanh was not big enough for the referee to award a penalty to the Vietnamese team.

Vietnam team draws with Philippines thanks to goal in extra time

|

On the evening of December 18, the Vietnamese team drew 1-1 with the Philippines in Group B - ASEAN Cup 2024.

Hai Phong invests 6,235 billion VND to build a bridge to Thuy Nguyen city

|

Hai Phong - National Assembly Chairman Tran Thanh Man attended the groundbreaking ceremony of Nguyen Trai Bridge organized by Hai Phong City People's Committee.

Plan to reorganize and streamline the Foreign Affairs Committee

|

The Standing Committee of the National Assembly's Foreign Affairs Committee has just proposed two options to reorganize and streamline the Foreign Affairs Committee.

Mr. Do Van Chien wants 9 organizations to take the lead in streamlining their apparatus

|

Chairman of the Central Committee of the Vietnam Fatherland Front Do Van Chien expressed his hope that the bloc of 9 organizations in the emulation cluster would take the lead in streamlining the apparatus.

Reduce the ideological and psychological pressure of civil servants when arranging the apparatus

PHẠM ĐÔNG |

According to the Government, to limit the impact of the restructuring and streamlining of the apparatus on cadres and civil servants, there needs to be strong and outstanding policies.

Decentralization and complete decentralization when building urban railways

Hà Vinh |

On December 5, Politburo member, Prime Minister Pham Minh Chinh, Head of the State Steering Committee for important national projects and works, key to the transport sector, chaired a meeting of the Government Standing Committee with the Ministry of Transport, the People's Committees of Hanoi and Ho Chi Minh City and relevant ministries and branches on the urban railway system project in Hanoi and Ho Chi Minh City.

Prime Minister directs investigation to clarify accident in Military Region 7

PHẠM ĐÔNG |

The Prime Minister requested to quickly overcome the consequences and clarify the cause of the accident during the exercise in Military Region 7.