These days, at the construction site of the Dong Dang - Tra Linh expressway project, nearly 400 personnel and 125 construction machines and equipment are focusing on speeding up the progress of the 2 tunnels, the approach road, drilling bored piles, and casting I-beams according to the handed-over sections of the site. "This is an extremely difficult project, which has been expected by the people and local authorities for many years. Therefore, we are always conscious of taking advantage of every hour, encouraging each other to work with the determination to bring the project to the finish line on time" , Mr. Nguyen Duc Tuan - Director of the Dong Dang - Tra Linh Project Management Board shared.
At the Quang Ngai - Hoai Nhon project, thousands of workers are working day and night at the construction site. Mr. Tran Van Chi - Director of the XL01 Package Management Board said that the joint venture contractor is currently paving the first meters of asphalt concrete through Hanh Thuan commune, Nghia Hanh district, Quang Ngai province. At the construction site, 3 asphalt concrete paving units have been mobilized, each consisting of a paver, four rollers, 30 asphalt concrete transport trucks, and dozens of engineers and workers working continuously to ensure progress.
"Taking advantage of favorable weather, the remaining workload is also very large and the rainy season is coming, so the contractor has encouraged staff and workers to be on duty 100% and work overtime during the holidays. Besides, the benefits for workers receiving 300% salary during these holidays are still guaranteed," said Mr. Chi.
Also on this occasion, the Management Board of Package XL01 of the Chi Thanh - Van Phong project arranged 50 workers to be on duty day and night at the construction site to ensure that the construction progress is not interrupted. The workers worked with a high spirit of determination, ensuring both work and maintaining a safe working environment.
Mr. Truong Cong Dat - Director of the XL1 Package Management Board said: “Each project always has its own specific difficulties. Here, the construction encountered complex geology, but that did not discourage the team. With the common spirit of determination to bring the project to the finish line on schedule, in addition to finding solutions to overcome difficulties, the Management Board always focuses on caring for and encouraging the staff, engineers and workers to compete to work effectively” .
In addition to focusing on the main construction points, many groups of workers also actively participate in checking, maintaining equipment, cleaning the construction site, creating favorable conditions for the next construction activities. "We always try our best to complete the assigned tasks at the construction site. During the holidays, we are divided into groups to work on duty, not afraid of difficulties or hardships to speed up the project" , Mr. Nguyen Van Dan - a contractor worker shared.
Taking advantage of the favorable weather, nearly 80 engineers and workers of the XL1 package of the Khanh Hoa - Buon Ma Thuot expressway were busy constructing two tunnels, Phuong Hoang tunnel, Song Cho bridge and Cua Tay bridge. Mr. Nguyen Viet Chung - Commander of Phuong Hoang tunnel expressed: "Even though it is a holiday, we still maintain a serious and urgent working spirit, because each day completing a part of the work is a step closer to the goal".
At the XL24 package of the Ha Giang - Tuyen Quang expressway project, Mr. Nguyen Thien Tuyen - Director of the Project Management Board of Traffic Construction Projects of Tuyen Quang province surveyed the implementation of the package, highly appreciated the proactive spirit of the contractor in solving difficulties, and at the same time, encouraged and motivated the staff to put aside the joy of family reunion to stay at the construction site to work during the holidays.
While the whole country is on the National Day holiday on September 2, the working atmosphere at the "non-stop" construction sites of Deo Ca Group is still very exciting and urgent with thousands of cadres, engineers and workers working diligently in shifts. Each person has a different task, but all are determined for the common goal of bringing the projects to the finish line on time.