The Chairman of Bac Ninh Provincial People's Committee has just issued 2 decisions approving the adjustment of the implementation time of road construction investment projects in the province.
First, the Chairman of Bac Ninh Provincial People's Committee approved the adjustment of the implementation time of the Project to Invest in the construction of the road connecting Ring Road IV with Ha Bac 1 bridge, Viet Yen district, Bac Giang province (old).
The project was approved in 2023 with a implementation period from 2023 - 2025.
However, to date, the project has not been completed because the weak soil treatment item of the construction and equipment installation package is in the process of monitoring and waiting for subsidence.
At the same time, in the process of implementation, difficulties were encountered in relocating and returning Huu Nghi pumping station to serve pumping and drainage for the area.
Therefore, adjust the project implementation time to the end of 2026 to ensure sufficient time to complete the project, promote efficiency and project investment goals.
Second, the Chairman of Bac Ninh Provincial People's Committee approved the adjustment of the implementation time of the Project to Invest in the new construction of the road connecting the ring road of Bich Dong town with National Highway 37, Viet Yen district, Bac Giang province (old).
The project was approved in 2018 with a implementation time of 2019 - 2021. To date, the project has not been completed due to site problems of Toan Sang Co., Ltd.
Therefore, adjust the project implementation time to the end of June 2026 to ensure sufficient time to complete the project, promote efficiency and project investment goals.
The Chairman of the Provincial People's Committee assigned the People's Committee of Viet Yen ward to urgently coordinate with the Viet Yen Construction Investment Project Management Board to strengthen propaganda and mobilize people to agree and hand over land to ensure the project implementation progress is extended.
In case the extended term expires but there are still problems with land, the Viet Yen Construction Investment Project Management Board completes the procedures and reports to the investor to terminate the project; Viet Yen Ward People's Committee is responsible for allocating funds to continue site clearance and complete the remaining scope of the project according to the approved scale.