16,914 billion VND for site clearance to double the central Hanoi road

SÓNG HỮU |

Hanoi - According to the Department of Construction, the total estimated investment to renovate and expand Lang road is more than 21,377 billion VND, of which site clearance costs are about 16,914 billion VND.

The Department of Construction has just reported to the Hanoi City People's Committee on the plan to renovate and expand the elevated and low-lying Ring Road 2, the section from Nga Tu So to Cau Giay.

Accordingly, the project to renovate and expand Ring Road 2 elevated and low-lying sections, from Nga Tu So to Cau Giay, belonging to group A, special-grade road traffic works, is expected to be implemented in the period 2025 - 2028.

The project has a total estimated investment of more than 21,377 billion VND, of which site clearance costs are about 16,914 billion VND, and the rest are construction and installation costs and related items.

The project is studied with 2 main options.

Option 1 is to build an elevated bridge with a center line coinciding with the center line of the low-lying road according to the plan, with a cross-section of about 53.5m for the low-lying road and 19m for the elevated road.

This option is assessed to have many advantages such as ensuring synchronous planning, convenient traffic connection, suitable for domestic construction capacity and lower investment costs.

Option 2 is to build a large diameter submersible tunnel combined with drainage to prevent flooding. However, according to the Department of Construction, this option faces many difficulties.

Specifically, the tunnel line is affected by the Cat Linh - Ha Dong railway bridge pier system, which does not ensure technical space to arrange 4-lane tunnels; and at the same time, there is a risk of impacting the Mieu Pagoda area and neighboring residential works.

In addition, the intersection with urban railway line No. 5 and the actual elevation conditions make the tunnel length limited and investment efficiency not high.

Đường Láng thường xuyên ùn tắc, đặc biệt vào giờ cao điểm. Ảnh: Sóng Hữu
Lang street is often congested, especially during rush hour. Photo: Song Huu

Based on analysis, the Department of Construction proposed choosing option 1 (overpass) as the optimal option for investment deployment. At the same time, it is proposed that the project be implemented initially in the form of public investment from the city budget to accelerate progress, and then it is possible to study converting to PPP (public-private partnership) to diversify capital sources.

Lang Street stretches from Nga Tu So to Cau Giay, about 3.8km long, 10.5m wide in each direction, and is often congested, especially during peak hours.

The project implementation is part of the plan to close down inner-city beltways, reduce traffic pressure for Nga Tu So intersection, and promote the effectiveness of Ring Road 2 elevated section Vinh Tuy - Nga Tu So has been completed.

SÓNG HỮU
RELATED NEWS

Finalizing the time to complete site clearance for the 120-180m wide road project in Hanoi

|

Hanoi - Before February 28, localities must hand over the entire site for the construction of the Thang Long Avenue expressway project, 6.7km long, with a capital of 5, 249 billion VND.

Road through 5 wards in Hanoi under construction, expected to be completed in 2026

|

The investor and construction unit set a target to complete the Linh Nam road expansion project in 2026. The project is 3.4km long, passing through 5 wards of Hanoi.

Ring Road 2.5 Project: Government and people exchange many contents on site clearance

|

Hanoi - During the Lunar New Year, Khuong Dinh ward still welcomes, listens to and answers people's petitions related to site clearance for the Ring Road 2.5 project.

Proposal to expand the "Three Assistance" model for Trade Unions to accompany workers

|

Dong Thap - Workers expect the "Three Assistants" model including support - assisted reproduction - capital support to be expanded, so that the Trade Union can accompany workers.

Can Miu Le continue to sing and act in movies when managed locally?

|

According to experts, whether Miu Le is allowed to continue singing and acting when being managed locally needs to be determined based on many factors.

Hanoi youth flock to hunt for the bright red sunset by West Lake

|

Hanoi - The brilliant red color of the sunset in the early summer days has turned West Lake into a stop that attracts a large number of young people.

Instructions on switching from old gasoline cars to electric cars at Green Transit Day 2026

|

On Green Transformation Day 2026, people can bring old gasoline cars to participate in the "gasoline to electricity exchange" program and directly experience new electric vehicle lines.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Finalizing the time to complete site clearance for the 120-180m wide road project in Hanoi

SÓNG HỮU |

Hanoi - Before February 28, localities must hand over the entire site for the construction of the Thang Long Avenue expressway project, 6.7km long, with a capital of 5, 249 billion VND.

Road through 5 wards in Hanoi under construction, expected to be completed in 2026

SÓNG HỮU |

The investor and construction unit set a target to complete the Linh Nam road expansion project in 2026. The project is 3.4km long, passing through 5 wards of Hanoi.

Ring Road 2.5 Project: Government and people exchange many contents on site clearance

SÓNG HỮU |

Hanoi - During the Lunar New Year, Khuong Dinh ward still welcomes, listens to and answers people's petitions related to site clearance for the Ring Road 2.5 project.