70% of construction workers work through Tet at Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - To speed up the progress of the Long Thanh airport project, on the occasion of the Lunar New Year 2025, thousands of cadres, engineers, and workers worked through Tet.

Creating a warm atmosphere for construction workers during Tet

According to the Vietnam Airports Corporation (ACV), for the main packages being implemented at the Long Thanh airport project site in Dong Nai province, ACV has directed construction units to speed up the construction progress of the packages. Hundreds of construction teams have been organized at the site with nearly 7,000 experts, engineers, workers, and laborers and nearly 3,000 construction equipment. At the same time, the construction site has been organized scientifically, professionally, and orderly, ensuring security and safety during the construction process.

Phan trung tam nha ga hanh khach san bay Long Thanh. Anh: HAC
The central part of Long Thanh airport passenger terminal. Photo: HAC
Thi cong nha ga hanh khach san bay Long Thanh. Anh: HAC
Construction of Long Thanh airport passenger terminal. Photo: HAC

Speaking with Lao Dong reporters, a representative of the Long Thanh Airport Project Management Board said that according to the project's progress, in the coming time, the construction site will continue to increase the construction force, taking advantage of favorable dry season weather to speed up and urgently carry out construction.

According to schedule, in 2025, the Project Management Board is determined to basically complete the construction work of the Long Thanh airport project phase 1.

Therefore, ACV requires that the construction site maintain over 70% of construction workers during the Lunar New Year 2025.

In addition to working during holidays, contractors also work at night at the construction site.

Phan canh nha ga hanh khach san bay Long Thanh. Anh: HAC
The wing of Long Thanh airport passenger terminal. Photo: HAC

Mr. Duong Quang Dien - Permanent Deputy Director of Long Thanh Airport Project Management Board said: The Lunar New Year is a traditional holiday, so the Long Thanh Airport Project Management Board will visit, encourage and give gifts to officers, workers and laborers working at the construction site.

At the same time, ACV also requires contractors to plan construction throughout Tet, ensuring the best construction volume, but also creating a favorable environment for workers to be happy, warm, and feel the care of the units during the project implementation process.

Main packages at Long Thanh airport "racing" ahead of schedule

Mr. Nguyen Duc Thuan - Deputy Executive Director of the Joint Venture for Package 5.10 to construct the Long Thanh Airport Passenger Terminal said that to ensure the progress of the project, the joint venture has planned to mobilize workers and engineers to work through the 2025 Lunar New Year, maintaining 70% of the workforce throughout the holiday.

Thi cong goi thau 4.6 san bay Long Thanh. Anh: HAC
Construction of package 4.6 of Long Thanh airport. Photo: HAC

Lieutenant Colonel Le Van Tien - of the Aviation Construction Corporation (ACC) - Commander of the Joint Venture of Package 4.6 for the construction of the Long Thanh Airport runway - said: The Joint Venture of Contractors has come up with a plan, the construction teams will be on duty during Tet and will work through Tet, the manpower, machinery and equipment will be maintained and the construction teams will be divided to ensure that the construction work meets and exceeds the schedule, ensuring security and safety at the construction site. Welfare policies for workers are also guaranteed to be able to work while enjoying a warm Tet holiday at the construction site.

Currently, at the Long Thanh airport project site, the main packages are being accelerated.

Package 5.10 is for construction and installation of equipment for the passenger terminal, which is considered the heart of the Long Thanh airport project, phase 1. To date, this package has completed all underground reinforced concrete work and is currently assembling the steel structure.

Package 4.6, construction of runways, taxiways, and aircraft parking lots, ACV is determined to direct construction units to complete and technically exploit the runways before April 30, 2025.

Package 6.12, construction of the traffic system connecting line 1 and line 2, put into use before September 2, 2025.

HÀ ANH CHIẾN
RELATED NEWS

New Year's Eve fireworks at Long Thanh airport resettlement area

|

Dong Nai will set off fireworks on New Year's Eve at 5 locations, including Loc An - Binh Son Resettlement Area (resettlement of Long Thanh airport project).

Hot in Saigon: The "heart" of Long Thanh airport gradually revealed

|

Hot News Saigon January 4: The "heart" of Long Thanh airport is gradually revealed; Images of 2 important bridges at An Phu intersection are about to be completed;...

Bidding for 2 packages of Long Thanh airport project in the first quarter of 2025

|

Dong Nai - Vietnam Airports Corporation is preparing to bid for package 7.8 of cargo terminal No. 1 and package 11.5 of Long Thanh airport parking lot.

113 prefixes are used for fire fighting, emergency, and security

|

It is expected that from the third quarter, the 113 prefix will receive, classify and coordinate all emergency situations such as emergency, firefighting, security support - applied nationwide.

Ho Chi Minh City assigns research to expand Rung Sac road to 10 lanes

|

Ho Chi Minh City assigned research to expand Rung Sac road to 10 lanes to meet traffic demand and anticipate the development wave in Can Gio.

Opening of the preliminary round of the 20th National Press Award

|

Hanoi - On April 17, the Vietnam Journalists Association opened the preliminary round of the 20th National Press Award in 2025.

Mr. Trump reveals when the US and Iran may meet

|

The prospect of US-Iran talks is increasing as Mr. Trump wants Middle East tensions to cool down and the parties seek an agreement to end the conflict.

Discovery of a 2-year-old girl dead in a car

|

Nghe An - A girl over 2 years old was left in a car for many hours leading to death, relatives were shocked when they discovered the incident.

New Year's Eve fireworks at Long Thanh airport resettlement area

HÀ ANH CHIẾN |

Dong Nai will set off fireworks on New Year's Eve at 5 locations, including Loc An - Binh Son Resettlement Area (resettlement of Long Thanh airport project).

Hot in Saigon: The "heart" of Long Thanh airport gradually revealed

NGỌC ÁNH - CHÂN PHÚC |

Hot News Saigon January 4: The "heart" of Long Thanh airport is gradually revealed; Images of 2 important bridges at An Phu intersection are about to be completed;...

Bidding for 2 packages of Long Thanh airport project in the first quarter of 2025

HÀ ANH CHIẾN |

Dong Nai - Vietnam Airports Corporation is preparing to bid for package 7.8 of cargo terminal No. 1 and package 11.5 of Long Thanh airport parking lot.