Bidding for 2 packages of Long Thanh airport project in the first quarter of 2025

HÀ ANH CHIẾN |

Dong Nai - Vietnam Airports Corporation is preparing to bid for package 7.8 of cargo terminal No. 1 and package 11.5 of Long Thanh airport parking lot.

Many bidding packages in Long Thanh airport project have been started.

On January 3, according to the reporter of Lao Dong Newspaper at the construction site of Long Thanh airport project in Long Thanh district, Dong Nai province, officers, engineers and workers are urgently working on package 4.6 of the runway and package 5.10 of the passenger terminal.

Goi thau 5.10 nha ga hanh khach san bay Long Thanh. Anh: HAC
Package 5.10 of Long Thanh airport passenger terminal. Photo: HAC

Here, the lotus-shaped passenger terminal is increasingly clearly shown, and labor safety work is seriously implemented.

Cong tac dam bao an toan lao dong duoc chu trong trong qua trinh thi cong o tren cao tai cong trinh nha ga hanh khach san bay Long Thanh. Anh: HAC
Ensuring labor safety is a priority during the construction process at the Long Thanh airport passenger terminal. Photo: HAC

Also on January 3, Vietnam Airports Corporation ACV informed about the implementation status of the remaining bidding packages being prepared for bidding in the first quarter of 2025.

According to ACV, package 7.8 - "Construction, equipment installation and construction drawing design for cargo terminal No. 1 and remaining auxiliary works" - has completed the appraisal work as a basis for ACV to select contractors according to regulations.

Package No. 11.5 - "Construction, equipment installation and construction drawing design for parking garage" - is organizing contractor selection, expected to complete contractor selection in the first quarter of 2025 to start construction in sync with other packages of the project.

Phan trung tam nha ga hanh khach san bay Long Thanh. Anh: HAC
The central part of Long Thanh airport passenger terminal. Photo: HAC

Previously, ACV continued to start many important packages at the Long Thanh airport project, Long Thanh district such as: Package 4.7 - Construction and installation of equipment for aircraft parking lots and other works; Package 4.9 - Construction and installation of equipment for aircraft fuel supply systems; Package 2.10 - Construction of Long Thanh airport fence...

In addition, package No. 4.8 also had ACV approve the contractor selection results on October 25, 2024.

April 30, 2025, Long Thanh airport runway exploitation

Currently, at the ACV construction site, hundreds of construction teams have been organized with nearly 7,000 experts, engineers, workers, and nearly 3,000 construction equipment.

Trung ta Le Van Tien - Chi huy truong lien danh nha thau goi thau 4.6 dang huong dan nguoi lao dong thi cong. Anh: HAC
Lieutenant Colonel Le Van Tien - Commander of the Joint Venture of Package 4.6 under the ACC Aviation Construction Corporation (right of the photo) is instructing workers on construction. Photo: HAC

Package 5.10 for construction and equipment installation of the passenger terminal has so far completed all underground reinforced concrete work.

Cong trinh nha ga hanh khach, doi voi ket cau thep, san xuat keo thep chinh hoan thanh 100% khu canh va 61% doi voi khu trung tam. Anh: HAC
Passenger terminal project, for steel structure, main steel truss production is 100% complete for the wing area and 61% for the central area. Photo: HAC

For steel structure, main steel truss production is 100% complete for the wing area and 61% for the central area. Secondary steel frame erection work has started in the central area.

Phan canh nha ga hanh khach san bay Long Thanh. Anh: HAC
The wing of Long Thanh airport passenger terminal. Photo: HAC

Package 4.6, construction of runways, taxiways, and aircraft parking lots, ACV is determined to direct construction units to complete and technically exploit the runways before April 30, 2025.

Package 6.12, construction of the traffic system connecting line 1 and line 2, put into use before September 2, 2025.

Thi cong goi thau 4.6 san bay Long Thanh. Anh: HAC
Construction of package 4.6 of Long Thanh airport. Photo: HAC

Mr. Duong Quang Dien - Permanent Deputy Director of Long Thanh Airport Project Management Board - said: "Following the direction of the Prime Minister, we determined that 2025 will be the year of acceleration and breakthrough, creating the premise to bring Long Thanh airport project to the earliest progress milestone."

HÀ ANH CHIẾN
TIN LIÊN QUAN

Bidding for 1 package of Long Thanh airport connecting road project

|

Dong Nai - A consortium of two contractors won a bid worth over 200 billion VND for the project to build provincial road 25C connecting Long Thanh airport.

Director of Aviation joins Long Thanh airport steering committee

|

The Director of the Civil Aviation Authority of Vietnam was assigned as the Deputy Standing Committee of the Steering Committee for preparations for the exploitation of Long Thanh airport.

Dong Nai auctions 282-hectare land plot next to Long Thanh airport

|

Dong Nai Province Land Fund Development Center proposed to auction a 282-hectare land plot in Binh Son Commune, Long Thanh District, near Long Thanh Airport, worth VND7,400 billion.

Air pollution unexpectedly decreased, Hanoi people were excited

|

Recorded on January 10, air pollution levels in Hanoi decreased significantly due to cold winds.

Faulty traffic lights, motorbikes pushed, cars lined up waiting

|

HCMC - On January 10, the traffic light at the intersection of National Highway 22 - Giap Hai (Cu Chi district) was faulty, causing people to not dare to drive through the intersection.

Ensuring food safety during Lunar New Year 2025

|

Ho Chi Minh City - To ensure food safety during the 2025 Lunar New Year, the city will strengthen control and prevent the production and trading of poor quality food.

Capital Youth Park is about to be "revived"

|

Currently, the Capital Youth Park (Hai Ba Trung District, Hanoi) has had its surrounding fence system removed to create an open space to serve the people.

Bidding for 1 package of Long Thanh airport connecting road project

HÀ ANH CHIẾN |

Dong Nai - A consortium of two contractors won a bid worth over 200 billion VND for the project to build provincial road 25C connecting Long Thanh airport.

Director of Aviation joins Long Thanh airport steering committee

Xuyên Đông |

The Director of the Civil Aviation Authority of Vietnam was assigned as the Deputy Standing Committee of the Steering Committee for preparations for the exploitation of Long Thanh airport.

Dong Nai auctions 282-hectare land plot next to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai Province Land Fund Development Center proposed to auction a 282-hectare land plot in Binh Son Commune, Long Thanh District, near Long Thanh Airport, worth VND7,400 billion.