Hai Tien sea dyke continues to subside for hundreds of meters

QUÁCH DU |

Thanh Hoa - In recent months, Hai Tien sea dyke has continuously experienced subsidence, one place is filled, another appears and extends hundreds of meters.

According to records of Lao Dong Newspaper reporters as of June 17, the subsidence situation in the Hai Tien sea dyke area is still continuing.

At the scene, new subsidence points have appeared, and the construction unit is currently arranging excavators and vehicles to level the damaged locations.

Đơn vị thi công huy động máy xúc, phương tiện để lấp đất tại các vị trí bị sụt lún. Ảnh: Quách Du
The construction unit mobilized excavators and vehicles to fill soil at subsided locations. Photo: Quach Du

Also according to records, the eroded embankment section is hundreds of meters long. Most of the sinkholes are temporarily filled with soil, making the construction area untidy. Notably, there are currently no fundamental remedial measures, while the subsidence phenomenon continues to occur.

Especially, at this time, Hai Tien beach area is receiving a lot of tourists and people coming to swim. The continued subsidence of the embankment not only affects the landscape but also poses a potential risk of unsafety for people and tourists.

Bờ kè biển Hải Tiến trở nên nhếch nhác sau khi san lấp đất tại các vị trí sụt lún. Ảnh: Quách Du
Hai Tien sea dyke becomes messy after land leveling at subsidence locations. Photo: Quach Du

Talking to a reporter of Lao Dong Newspaper, a representative of the leadership of Hoang Tien Commune People's Committee said that the construction unit is still leveling the land at the subsided locations. The specific remedial and handling plan is still waiting for the Provincial People's Committee to consider and decide.

It is known that, according to the assessment of the Thanh Hoa Provincial Department of Agriculture and Environment, the cause of the subsidence is due to sand at the foot of the breakwater wall being eroded by sea waves, losing the foundation, leading to landslides of the sidewalk behind the breakwater wall.

Theo đánh giá của ngành chức năng, nguyên nhân dẫn đến việc sụt lún là do  cát tại chân tường chắn sóng bị xói mòn. Ảnh: Quách Du
According to the assessment of functional sectors, the cause of subsidence is due to erosion of sand at the foot of the wave-breaking wall. Photo: Quach Du

Regarding handling responsibility, the Department of Agriculture and Environment of Thanh Hoa province identified the Hoang Hoa District Construction Investment Project Management Board as the investor from the time of approval of the policy to August 2025. Currently, this unit has merged into the Thanh Hoa Agricultural and Rural Development Construction Investment Project Management Board. Up to now, the People's Committee of Hoang Tien commune is receiving the task of investor.

For VINASEAN Construction Consulting Joint Stock Company, this is a design and construction supervision consulting unit according to contracts signed with the Hoang Hoa District Construction Investment Project Management Board before that.

The joint venture of Tuan Linh Investment and Construction Joint Stock Company - Hoang Tuan Co., Ltd. is the construction unit. The Department of Construction is the unit inspecting the acceptance of the completed project.

QUÁCH DU
RELATED NEWS

Hai Tien sea dyke subsides, requesting review of construction documents

|

Thanh Hoa - Chairman of the Provincial People's Committee requests review of procedures, design documents, and construction of Hai Tien sea embankment.

More than 1km of Co Chien river embankment subsided, lighting system stolen about 800m of electrical wires

|

Vinh Long - The Co Chien river embankment line through Tan Ngai ward has more than 1km of subsidence, and the lighting system about 800m long has lost electrical wires.

Hai Tien sea dyke seriously subsides: No basis to confirm due to natural disaster

|

Thanh Hoa - Regarding the incident of Hai Tien sea dyke subsidence, functional agencies have initially identified the initial cause and responsibilities of relevant parties.

Link to watch Portugal vs DRC football live at World Cup 2026

|

Link to watch live the match between Portugal and DRC at the 2026 World Cup, taking place at 00:00 on June 18 (Vietnam time).

Land plots under pressure, apartments enter price adjustment phase

|

Apartment prices in some major cities have begun to adjust, but this segment is still leading in terms of interest, far exceeding land plots and villas.

Spreading the education promotion movement in Nghe An homeland

|

Nghe An - The movement to encourage learning is continuing to spread strongly from grassroots levels to key schools, contributing to building a lifelong learning spirit.

Hai Tien sea dyke subsides, requesting review of construction documents

QUÁCH DU |

Thanh Hoa - Chairman of the Provincial People's Committee requests review of procedures, design documents, and construction of Hai Tien sea embankment.

More than 1km of Co Chien river embankment subsided, lighting system stolen about 800m of electrical wires

HOÀNG LỘC |

Vinh Long - The Co Chien river embankment line through Tan Ngai ward has more than 1km of subsidence, and the lighting system about 800m long has lost electrical wires.

Hai Tien sea dyke seriously subsides: No basis to confirm due to natural disaster

QUÁCH DU |

Thanh Hoa - Regarding the incident of Hai Tien sea dyke subsidence, functional agencies have initially identified the initial cause and responsibilities of relevant parties.