Is the Management Board of Quang Binh Economic Zone properly handling suspended projects according to regulations?

CÔNG SÁNG |

The Quang Binh Energy Pellet Factory project was applied for extension by the Management Board of Quang Binh Economic Zone even though it was previously said it was not in accordance with regulations.

Not a force majeure reason

Lawyer Doan Trong Bang, Black & White Law Firm - Hanoi Bar Association, said that document 780 dated June 17, 2024 of the Management Board of Quang Binh Economic Zone reported to the People's Committee of Quang Binh province, has the content of the report. not in accordance with the law.

Lawyer Bang said that the basis for adjusting the project implementation progress in the document clearly stated that due to the prolonged impact of the COVID-19 epidemic and the impact of the world economic and financial crisis; Investors overcome consequences in cases of force majeure (according to the provisions of Point a, Clause 4, Article 41 of the Investment Law 2020 and the provisions of Clause 1, Article 15 of Decree No. 43/2014/ND-CP of the Government ).

According to the provisions of Point a, Clause 4, Article 41 of the Investment Law: "For investment projects with approved investment policies, investors are not allowed to adjust the progress of the investment project by more than 24 months compared to the progress of the investment project. The level of investment project implementation is specified in the initial investment policy approval document, except for one of the following cases:

To overcome the consequences in cases of force majeure according to the provisions of civil law and land law.

However, the above basis is completely unfounded because all of the events mentioned are not force majeure events according to the provisions of civil law and land law.

The time the COVID-19 epidemic is considered a force majeure event can be calculated from January 23, 2020 (the date the COVID-19 epidemic was announced according to Decision No. 447 dated April 1, 2020 of the Prime Minister) to October 11. .2021 (the date the Government issued Resolution No. 128 temporarily regulating safe, flexible adaptation and effective control of the COVID-19 epidemic).

Therefore, the force majeure event of the COVID-19 epidemic according to the provisions of the Land Law has ended from October 11, 2021.

There is no basis for confirmation

If it is determined that the Project belongs to the case of "remediation of consequences in case of force majeure according to the provisions of civil law and land law", it is understood that the remediation of consequences lasts nearly 3 years. But the Quang Binh Economic Zone Management Board does not have any basis to confirm this.

Conditions to be considered a force majeure event according to the provisions of Article 156 of the Civil Code: A force majeure event is an event that occurs objectively, is unpredictable and cannot be overcome even though it has been resolved. Apply all necessary and permissible measures.

Regarding the reasons for the impact of the world economic and financial crisis, this event does not meet the elements of a force majeure event as prescribed in Clause 1, Article 156, 2015 Civil Code as follows: above, because how does this event affect Investors? If it only affects the issue of lack of capital, inability to mobilize capital leading to inability to implement the project, it is not considered a force majeure reason.

Previously, as Lao Dong Newspaper reported, on February 22, 2024, Deputy Head of the Management Board of Quang Binh Economic Zone Hoang Dang Anh sent to the Provincial People's Committee a report on the implementation of the Dohwa Project, clearly stating what the project needs to see. Consider terminating operations.

The document clearly states that this project does not fall under the provisions of the Investment Law to adjust project implementation progress, therefore, the Economic Zone Management Board requests to terminate the project's operations.

However, on June 17, 2024, the Management Board of Quang Binh Economic Zone sent another document to the Provincial People's Committee about adjusting the extension for this company until December 2025.

At the conclusion notice of the Party Committee of the Provincial People's Committee at the meeting on August 13, it was agreed to extend the 5th time for the Quang Binh Energy Pellet Plant Project of Dohwa Resource Development Company Limited despite public opinion being negative. very frustrated about the implementation of this project.

CÔNG SÁNG
TIN LIÊN QUAN

Chuyện ăn nói hai lời liên quan đến dự án treo ở Quảng Bình

Lê Thanh Phong |

Tỉnh Quảng Bình đồng ý đề xuất gia hạn lần thứ 5 dự án treo Dohwa rất tai tiếng tại địa phương.

Quảng Bình yêu cầu báo cáo về gia hạn dự án treo của Dohwa

CÔNG SÁNG |

Xét thấy có nhiều ý kiến khác nhau liên quan đến dự án "treo" sản xuất viên nén năng lượng Dohwa, tỉnh Quảng Bình chỉ đạo làm rõ để có quyết định chính thức.

Sự bất nhất của Ban Quản lý Khu kinh tế Quảng Bình trong việc xử lý dự án "treo"

CÔNG SÁNG |

Sau khi có văn bản báo cáo đề nghị UBND tỉnh cho chủ trương về việc chấm dứt dự án treo Nhà máy sản xuất viên nén năng lượng vì không đúng Luật Đầu tư, Ban Quản lý Khu kinh tế Quảng Bình sau đó lại có văn bản khác xin gia hạn dự án.

Arsenal giành 3 điểm trên sân Tottenham

Nhóm PV |

Bàn thắng duy nhất của Gabriel giúp Arsenal thắng trên sân Tottenham ở vòng 4 Premier League tối 15.9.

Chủ tịch Tổng LĐLĐVN động viên, hỗ trợ người lao động tại Tuyên Quang

Lam Thanh |

Sáng 15.9, ông Nguyễn Đình Khang - Ủy viên Trung ương Đảng, Chủ tịch Tổng LĐLĐ Việt Nam cùng đoàn công tác đến thăm hỏi, động viên, trao hỗ trợ cho đoàn viên, NLĐ bị ảnh hưởng bởi bão số 3 tại Tuyên Quang.

Tin 20h: Có gì bên trong xe đầu kéo vụ sập cầu Phong Châu?

NHÓM PV |

Tin 20h: Cảnh sát cơ động cõng đồ tiếp tế, vượt núi vào vùng sạt lở; Không phát hiện thi thể trong xe đầu kéo vụ sập cầu Phong Châu...

Ngang nhiên rào tôn chắn cửa sổ nhà dân giữa Hà Nội

Minh Hạnh |

Hà Nội - Một nhóm người tự ý rào tôn chắn cửa sổ nhà dân, khiến căn nhà bị thiếu ánh sáng, thiếu không khí, và tiềm ẩn nguy cơ cháy nổ, khó cứu nạn, cứu hộ.

Cơn bão mạnh nhất 75 năm sắp đổ bộ Thượng Hải, Trung Quốc

Song Minh |

Bão Bebinca có thể trở thành một trong những cơn bão mạnh nhất đổ bộ vào Thượng Hải, Trung Quốc kể từ năm 1949.