Close-up of two dams turning the Nam Rom river section into a reservoir

Thành An |

Dien Bien - Two upstream dams are turning the Nam Rom River into a reservoir in the central area together.

On September 12, actual records at dam No. 1 showed that the project was built next to Regiment 82 in Dien Bien Phu ward.

The project has 6 valve gates, playing the role of discharging and retaining water when needed, besides, a solid operating house project is also built.

Along with the water-raising dam that has appeared near Muong Thanh bridge, the river section between these 2 dams has now become a reservoir.

Đập dâng số 1 được hoàn thành mới đây. Ảnh: Thành An (chụp ngày 12.9)
Dam No. 1 was recently completed. Photo: Thanh An (taken on September 12)

When put into operation, the two projects will raise water on a river section about 7km long, creating a more continuous water surface during the dry season, opening up expectations for a landscape and ecological space in the central area of the province.

Water still flows along the riverbed, but the water level can be controlled through the valve gate system and operating procedures.

This is a solution that both serves to regulate flow and create conditions to maintain water surface in the dry season.

A noteworthy point is that about 7km of river located between the two dams will have a clear change in the water surface morphology.

Đập dâng nước phía cầu Mường Thanh được xây dựng từ trước. Ảnh: Thành An (chụp ngày 12.9).
The flooding dam on the Muong Thanh bridge side was built earlier. Photo: Thanh An (taken on September 12)

At times of little rain, the water level of the Nam Rom River is often low, and some sections of the riverbed may have shallow sections. When the dam rises and operates, the water level is maintained at an appropriate elevation, helping the water surface to be more continuous.

From a shore view, the river at that time may have the shape of a lake stretching in the middle of the city. The water surface in the middle creates an opening, contributing to changing the landscape of the central area of Dien Bien.

Sông Nậm rốm có thời điểm trơ đáy vào mùa khô. Ảnh: Thanh Bình (chụp năm 2023).
Nam Rom River sometimes has a dry bottom in the dry season. Photo: Thanh Binh (taken in March 2023)

Along with the two dams, many sections of the riverbank have been built with embankments. Drainage ditches, railings, lighting poles and renovation items are also being implemented.

When completed synchronously, people can get closer to the river through walking paths and coastal spaces.

Mr. Tong Van Sang (Dien Bien Phu ward) said that the renovation of the riverbank will help the central area become more spacious.

“Renovating the riverbank like this is very reasonable, the water in the central area rising will look beautiful, and in the afternoon people will take a walk and exercise, it will also be cool” - Mr. Sang shared.

Sau khi các đập dâng vận hành, mực nước đã dâng cao hơn. Ảnh: Thành An (chụp 12.9)
After the dams started operating, the water level rose higher. Photo: Thanh An (taken on September 12)

However, to turn the river section into an attractive public space, the organization of both banks plays an important role.

Green trees, walking paths, rest stops, lighting and connectivity with residential areas will determine whether people actually use this space or not.

Cảnh quan hai bên sông đang được cải tạo nhanh chóng. Ảnh: Thành An (chụp 12.9)
The landscape on both sides of the river is being quickly renovated. Photo: Thanh An (taken on September 12)

The Nam Rom River basin disaster management project was started in July 2023, with a total investment of more than 981 billion VND. The Project Management Board for Agricultural and Rural Development Works of Dien Bien province is the investor.

As of September 4, 2026, the total value of construction packages reached approximately 535 billion VND, equivalent to 70.58%. The work of inventorying, land recovery, compensation and site clearance is basically completed.

The project to manage multiple natural disasters in the Nam Rom river basin in Dien Bien province was approved for investment policy by the Prime Minister in Decision 170/QD-TTg, dated February 4, 2021.

The total capital for the project is over 981 billion VND, of which ODA loans from the French Development Agency AFD are 665.5 billion VND (24.65 million Euros); counterpart funds are 275.028 billion VND (10.19 million Euros) and non-refundable EU aid is 40.5 billion VND (1.5 million Euros).

Thành An
RELATED NEWS

Nam Rom Dai irrigation and 60 years of water management operation

|

Dien Bien - Nam Rom Great Irrigation - a symbolic work of youth volunteers still diligently leading the source after more than half a century.

Nam Rom - the historical river that witnessed the changes of Dien Bien

|

Dien Bien - Nam Rom is not a large river, but in this westernmost land, the flow is the spiritual source of many people.

Close-up of two dams turning the Nam Rom river section into a reservoir

|

Dien Bien - Two upstream dams are turning the Nam Rom River into a reservoir in the central area together.

Nearly 100 households in Son La are waiting anxiously for clean water

|

Son La - Nearly 100 households in group 1, Chieng Coi ward have not had clean water for many years, having to use source water, rainwater and irrigation dam water.

Diva My Linh's daughter: I don't try to separate from my parents' shadow

|

At the age of 24, diva My Linh's daughter - singer My Anh - is gradually affirming her own mark in music, preparing to carry out a solo tour in the US.

Nam Rom Dai irrigation and 60 years of water management operation

Thành An |

Dien Bien - Nam Rom Great Irrigation - a symbolic work of youth volunteers still diligently leading the source after more than half a century.

Nam Rom - the historical river that witnessed the changes of Dien Bien

Thành An |

Dien Bien - Nam Rom is not a large river, but in this westernmost land, the flow is the spiritual source of many people.