Ninh Binh - Hai Phong expressway completes site clearance, construction speeds up

NGUYỄN TRƯỜNG |

Ninh Binh - After nearly 1 year of implementation, the Ninh Binh - Hai Phong expressway project, the section passing through the old Ninh Binh province, many items of the Project have gradually been completed.

Started on April 19, 2025, the Ninh Binh - Hai Phong expressway project, the section passing through the old Ninh Binh province (hereinafter referred to as the Project) is gradually reaching its finish line, striving to be completed and put into operation by the end of this year.

Nhiều hạng mục của Dự án đang dần hoàn thiện. Ảnh: Nguyễn Trường
Many items of the Project are gradually being completed. Photo: Nguyen Truong

The project has a total investment of 6,865 billion VND, of which the central budget is 4,865 billion VND and Ninh Binh province's budget is 2,000 billion VND. The entire road has a total length of 25.3km, a design speed of 120km/h, a roadbed width of 24.75m and auxiliary works on the route.

Toàn tuyến đã hoàn thành. Ảnh: Nguyễn Trường
The entire route has completed 90% of the volume of roadbed filling with sand. Photo: Nguyen Truong

Up to now, the entire route has completed site clearance and removed difficulties in materials. Contractors are focusing on promoting overtime, increasing crews, and increasing construction teams to shorten project construction time.

Talking to a reporter from Lao Dong Newspaper, Mr. Nguyen Quang Minh - Deputy Director of Ninh Binh Province Construction Investment Project Management Board No. 1 (Project investor) - said that as of now (March 28 - PV), the project construction volume has reached nearly 30% and strives to complete it ahead of schedule. It is expected that the Project will be completed around the end of November 2026.

Máy móc thi công trên công trường Dự án. Ảnh: Nguyễn Trường
Construction machinery on the Project site. Photo: Nguyen Truong

On the main route of the Project, the contractor is currently deploying 7 construction fronts simultaneously, performing tasks such as excavating soil, filling the roadbed with sand... The bridge part is deploying 12 construction fronts simultaneously at 12/12 bridge construction locations. In which, the workload has completed 90% of the sand filling foundation.

Contractors have mobilized about 500 machines, equipment and nearly 1,000 workers, taking advantage of the weather to support, maintaining 3 shifts/day and lasting until 10 pm daily" - Mr. Minh said.

Theo dự kiến, Dự án sẽ hoàn thành và đưa vào khai thác vào tháng 11.2026. Ảnh: Nguyễn Trường
According to the plan, the Project will be completed and put into operation in November 2026. Photo: Nguyen Truong

Also according to Mr. Minh, this is a key national transport project built to create new momentum for socio-economic development of Ninh Binh province and the provinces of the Red River Delta.

Ninh Binh province has shortened the construction time of the project from 6 years (2024 - 2029) to 3 years (2024 - 2026), therefore, the province has directed to complete site clearance and complete construction in 2026.

Currently, we have also assigned officials to closely monitor the construction site, and promptly handle difficulties. At the same time, direct contractors to increase shifts, increase crews, and supplement human and material resources at lightning speed to complete the Project" - Mr. Minh said.

NGUYỄN TRƯỜNG
RELATED NEWS

Scattered construction, Noi Bai - Lao Cai expressway poses risk of accidents

|

The construction process of expanding the Noi Bai - Lao Cai expressway is revealing a series of inadequacies, posing a potential risk of traffic unsafety.

Promoting the progress of the Bao Ha - Lai Chau expressway, raising regional connectivity

|

Lao Cai - The Bao Ha - Lai Chau expressway project is being jointly promoted, aiming to complete the transportation network and strengthen regional development links.

Russia refutes accusations that Moscow is making money from the Iran war

|

Russia affirms that it does not want the Iranian war to escalate and does not seek to profit from the issues of other countries.

Rabies diễn biến phức tạp, strengthen control measures

|

Dak Lak - Faced with the increasing risk of rabies, local authorities set a target of vaccinating dogs and cats to over 80%.

Europe plans to escort oil tanker after Iran conflict

|

Europe plans to escort oil tankers through the Strait of Hormuz after the Iranian conflict.

Tourists are satisfied with the music feast opening the National Tourism Year

|

Gia Lai - National Tourism Year - Gia Lai 2026 officially opened on the night of March 28 with a grand art program, attracting tens of thousands of tourists.

Male student dies after falling in Bai Tho mountain area, Quang Ninh

|

Quang Ninh - On the evening of March 28, a male student died after falling in the Bai Tho mountain area (Hong Gai ward).

Encircling 1 project with corrugated iron, refusing to relocate to implement the renovation of apartment building 51 Huynh Thuc Khang

|

Hanoi - Functional forces of Lang ward decided to cordon off a project to accelerate the implementation of the 51 Huynh Thuc Khang apartment renovation project.

Cục Đường bộ chấn chỉnh thi công cao tốc Nội Bài - Lào Cai do nguy cơ mất an toàn

Minh Hạnh |

Thi công mở rộng cao tốc Nội Bài - Lào Cai nhiều bất cập, tiềm ẩn nguy cơ mất an toàn giao thông. Cục Đường bộ Việt Nam yêu cầu khẩn trương khắc phục.

Scattered construction, Noi Bai - Lao Cai expressway poses risk of accidents

Bảo Nguyên |

The construction process of expanding the Noi Bai - Lao Cai expressway is revealing a series of inadequacies, posing a potential risk of traffic unsafety.

Promoting the progress of the Bao Ha - Lai Chau expressway, raising regional connectivity

Đinh Đại |

Lao Cai - The Bao Ha - Lai Chau expressway project is being jointly promoted, aiming to complete the transportation network and strengthen regional development links.