The final stretch on the billion-dollar route through Thai Nguyen

Nguyễn Hoàn |

The 6.68km-long Ring Road V project in Phu Binh district, Thai Nguyen province, after 3 years of construction, is now in the final stage.

The 6.68km-long Ring Road V connecting Thai Nguyen province with Bac Giang province, with an investment of 699.3 billion VND, is invested by the Provincial Traffic Construction Investment Project Management Board. This is a section of the more than 330km-long route passing through 8 localities with a total investment of nearly 86,000 billion VND.

Construction started in 2021. To implement this project, nearly 700 households were affected with a total land acquisition area of ​​about 30 hectares.

On October 24, according to the reporter, after 3 years of implementation, the road section of the V beltway project has been basically completed. Construction and installation are underway at 2 locations of the canal overpass.

Hinh hai du an duong vanh dai V qua dia phan tinh Thai Nguyen sau 3 nam trien khai. Anh: Viet Bac.
The shape of the Ring Road V project through Thai Nguyen province after 3 years of implementation. Photo: Viet Bac.

According to the investor's report, the site clearance for the main route has reached over 97%. The project is currently carrying out construction of the roadbed excavation, road foundation, asphalt concrete, and construction of 2 bridges on the route, reaching 99% of the volume.

Other items such as trees, sidewalks, and lighting systems are being installed synchronously. The investor and contractors are committed to completing the project before December 31, 2024.

Talking to reporters, Mr. Tran Xuan Hien - Construction Team Leader of Traffic Construction and Management Joint Stock Company 236 said that the project implementation process encountered some difficulties in site clearance, some sections of the road were weak in geology, and progress was interrupted due to heavy rain.

"Up to now, the problems have been resolved, the project has achieved over 70% of the workload and is in the final stage of concentrating human resources and means to complete the route in 2024," Mr. Thang informed.

When completed, the Ring Road V through Thai Nguyen will increase the connectivity of the Hanoi - Thai Nguyen Expressway with National Highway 37 and Bac Giang province. At the same time, connecting neighboring areas with the Hanoi - Thai Nguyen Expressway and National Highway 37 will promote the development of industry and services in the region.

Some images recorded by PV:

1
The Belt Road V project connecting Bac Giang - Thai Nguyen is now in its final stage after 3 years of construction. Photo: Viet Bac.
2
After having the site, the contractor accelerated construction. Photo: Viet Bac.
Mat duong rong hon 22 m voi 4 lan xe. Van toc luu thong du kien tu 80-100 km/h. Anh: Viet Bac.
The road surface is more than 22m wide with 4 lanes. The expected traffic speed is from 80-100 km/h. Photo: Viet Bac.
Nhan luc, phuong tien huy dong toi cong truong chay dua voi tien do. Anh: Viet Bac.
Human resources and equipment mobilized to the construction site to race against schedule. Photo: Viet Bac.
Vi tri cau vuot kenh huong tinh Bac Giang co ban hoan thien. Anh: Viet Bac.
The main span of the overpass on the Bac Giang province canal has been completed, while the approach road and auxiliary items are under construction. Photo: Viet Bac.

The V-Road Project is over 330km long, passing through 36 districts, towns and cities of Hanoi, Hoa Binh, Ha Nam, Thai Binh, Hai Duong, Bac Giang, Thai Nguyen and Vinh Phuc.

In the 2021-2025 period, this route will be a 4-lane grade II road and a 6-lane urban road. In the following period, when there are sufficient investment resources and transportation needs, Ring Road V will be invested in a 6-lane highway scale by building an elevated highway or a regular road.

Nguyễn Hoàn
TIN LIÊN QUAN

Ms. Nguyen Hai Tram is the Standing Deputy Secretary of Tien Giang Provincial Party Committee

|

Tien Giang - Ms. Nguyen Hai Tram was mobilized and appointed to join the Executive Committee, Standing Committee of the Provincial Party Committee and hold the position of Permanent Deputy Secretary of the Tien Giang Provincial Party Committee.

Transfer high-risk invoice list to police

|

The tax authority will continue to coordinate in providing the list of taxpayers with high risks regarding invoices to the police.

Dump truck crashes into multiple cars waiting at red light, killing 1 person

|

Binh Duong - In Tan Uyen city, a dump truck accident just occurred, causing one person to die on the spot and many vehicles to be damaged.

Colonel Nguyen Huu Phuoc appointed Director of Khanh Hoa Provincial Police

|

Colonel Nguyen Huu Phuoc - Deputy Director of Phu Tho Provincial Police was appointed by the Ministry of Public Security as Director of Khanh Hoa Provincial Police.

Vietnam futsal team wins second match at Southeast Asian tournament

|

On the afternoon of November 4, the Vietnamese futsal team won 2-0 against Malaysia at the Southeast Asian championship with goals from Minh Quang and Thinh Phat.

Sitting fishing in the middle of the dry Red River

|

Phu Tho - Compared to the time when the flood exceeded historical levels nearly 2 months ago, the current water level of the Red River has dropped, with people even sitting in the middle of the river to fish.

Cần 79 tỉ đồng để sửa chữa đường vành đai 3 trên cao

Minh Hạnh |

Hà Nội - Một số hạng mục của cầu cạn đường vành đai 3 trên cao được Sở Giao thông Vận tải (GTVT) đề nghị sửa chữa.

Chi tiết tuyến đường vành đai đắt nhất hành tinh vừa được chốt tiến độ

Nhóm PV |

UBND thành phố Hà Nội vừa ban hành quyết định điều chỉnh dự án đầu tư xây dựng đường Vành đai 1 đoạn Hoàng Cầu - Voi Phục. Đây được mệnh danh là Vành đai đắt nhất hành tinh.

Chặng nước rút tại dự án cầu vượt đường sắt trăm tỉ tại Thái Nguyên

Lam Thanh |

Sau khi hoàn thành, cầu vượt đường sắt Hà Nội - Thái Nguyên sẽ giúp giảm áp lực giao thông cho 1 trong những nút giao có mật độ phương tiện lớn bậc nhất thành phố.