Hanoi's hotline on road expansion projects that have not been implemented for more than 10 years

SÓNG HỮU |

Hanoi assigned 5 wards to remove obstacles in site clearance and speed up the implementation of the Linh Nam Road Expansion Project.

Permanent Vice Chairman of Hanoi People's Committee Duong Duc Tuan has just signed a document approving the relocation of the electricity and telecommunications systems under the Linh Nam road upgrade and expansion investment project according to the plan.

Accordingly, the Hanoi People's Committee assigned the Department of Construction to guide the People's Committees of the wards: Linh Nam, Vinh Hung, Hoang Mai, Vinh Tuy, Tuong Mai to organize the implementation of the Investment Project according to regulations, ensuring progress.

The People's Committees of Linh Nam, Hoang Mai, Vinh Tuy, and Tuong Mai wards are responsible for closely coordinating with the People's Committees of Vinh Hung Ward (investor) to promptly resolve and remove difficulties and obstacles in site clearance (GPMB), speed up the implementation of the Investment Project, and report to the City People's Committee on contents beyond its authority according to regulations.

The Department of Construction and Finance is responsible for coordinating, guiding, urging, inspecting, and supervising investors in implementing the Investment Project to ensure investment quality, progress, and efficiency and not cause loss, waste, or violation of legal regulations.

Du an mo rong duong Linh Nam nhieu nam chua the trien khai do vuong giai phong mat bang. Anh: Song Huu
The Linh Nam road expansion project has not been implemented for many years due to land acquisition problems. Photo: Song Huu

The project to upgrade and expand Linh Nam road was approved by the Hanoi People's Committee in 2013.

By August 2024, the Hanoi People's Committee had approved an adjustment to the implementation time of the Linh Nam Road Upgrade and Expansion Project according to the plan, to be completed in 2027.

The reason for the adjustment is due to difficulties and problems in site clearance, leading to the project not ensuring progress.

The project is about 3.4km long, starting at Tam Trinh intersection and ending at Nguyen Khoi dike intersection. Part of the route (from Vinh Hung intersection to Nguyen Khoi dike) is the section of Hanoi Ring Road 2.5.

According to the plan, Linh Nam Street will be expanded on the basis of the existing road, with 2 sections with cross-sections of 22.5m and 40m respectively (meeting 4-6 lanes).

After the operation of the 2-level local government model (1.7), the Hanoi People's Committee assigned the Vinh Hung Ward People's Committee as the investor to implement the project to upgrade and expand Linh Nam road.

The total land area recovered for the project is 98,345.92m2, involving 814 households and 33 organizations in 5 wards including Vinh Tuy, Tuong Mai, Vinh Hung, Hoang Mai and Linh Nam.

According to the investor's representative, the biggest difficulty is currently the complicated origin of land. On the same plot of land, it is possible to intertwine residential land, garden land, pond land, or agricultural land according to Decree 64.

Many households have bought and sold/transacted using handwritten documents, through many owners. When comparing the legal documents, the owner takes a lot of time. This forces relevant units to review extremely carefully.

Currently, the wards are actively coordinating with investors in site clearance. Wards are proactively developing plans and establishing compensation for land acquisition councils in their wards, and reviewing records to deploy work.

"In the coming time, we will be more active in coordinating to solve problems, discuss and provide the best support mechanisms and solutions for people, ensuring the site clearance process is implemented best" - said the investor representative.

SÓNG HỮU
RELATED NEWS

Hanoi talks about compensation when reclaiming prime land in Hoan Kiem Lake for a 2.14ha project

|

Hanoi - Hoan Kiem Ward is preparing a compensation, support and resettlement plan when reclaiming land to build a square and park east of Hoan Kiem Lake.

Hanoi reclaims land to build a bridge over the river, the highest compensation is over 100 million VND/m2

|

Hanoi compensates the highest amount of more than 100 million VND/m2 when reclaiming land and clearing land to implement the Duong River Waterway Transport Upgrade Project, with a capital of nearly 1,850 billion VND.

Investor exposes banners expressing determination for the project to expand Hanoi's main arteries

|

Hanoi - Investors and contractors have stretched out banners with the determination to complete a section of the project to expand National Highway 32 through Quang Oai commune in 2025.

Worry about tax on tax when taxing gold bar transfer

|

According to delegate Tran Kim Yen, taxing people's savings from gold bars may not be meaningful in terms of economic management.

Heavy rain has not stopped, Song Ba Ha Hydropower Plant in Dak Lak regulates water discharge with 13,000 m3/s

|

Dak Lak - Hydropower plants are regulating water in reservoirs to ensure the safety of works during the rainy season.

Hanoi talks about compensation when reclaiming prime land in Hoan Kiem Lake for a 2.14ha project

|

Hanoi - Hoan Kiem Ward is preparing a compensation, support and resettlement plan when reclaiming land to build a square and park east of Hoan Kiem Lake.

Tractor trailer is swept away by flood, hundreds of people search for missing driver

|

Quang Tri - Rescue forces have salvaged a tractor-trailer swept away by floodwaters, while hundreds of people are still trying to search for the missing driver in La Lay commune.

Deadline for supporting businesses affected by US counterpart taxes

|

The Prime Minister requested that specific support plans for businesses affected by US countervailing tax policies be completed in November.

Hanoi talks about compensation when reclaiming prime land in Hoan Kiem Lake for a 2.14ha project

SÓNG HỮU |

Hanoi - Hoan Kiem Ward is preparing a compensation, support and resettlement plan when reclaiming land to build a square and park east of Hoan Kiem Lake.

Hanoi reclaims land to build a bridge over the river, the highest compensation is over 100 million VND/m2

HỮU CHÁNH |

Hanoi compensates the highest amount of more than 100 million VND/m2 when reclaiming land and clearing land to implement the Duong River Waterway Transport Upgrade Project, with a capital of nearly 1,850 billion VND.

Investor exposes banners expressing determination for the project to expand Hanoi's main arteries

SÓNG HỮU |

Hanoi - Investors and contractors have stretched out banners with the determination to complete a section of the project to expand National Highway 32 through Quang Oai commune in 2025.