Hanoi reclaims land to build a bridge over the river, the highest compensation is over 100 million VND/m2

HỮU CHÁNH |

Hanoi compensates the highest amount of more than 100 million VND/m2 when reclaiming land and clearing land to implement the Duong River Waterway Transport Upgrade Project, with a capital of nearly 1,850 billion VND.

Talking to reporters of Lao Dong Newspaper about the site clearance for the Duong River waterway upgrade project, a representative of the Viet Hung Ward Infrastructure - Investment Project Management Board (Hanoi) said that they are achieving positive results.

There are 53 households in the ward subject to land acquisition and site clearance to implement the project.

"Preliminary statistics show that about 70% of households have received money and handed over the site with the highest compensation of more than 100 million VND/m2. Households are resettled in Viet Hung ward or Bo De ward" - said a representative of the Project Management Board.

s
There are 53 households in Viet Hung ward (Hanoi) subject to land acquisition and site clearance for the Duong River Waterway Transport Upgrade Project. Photo: Song Huu

Within the project scope, there are still more than 1,700m2 of land managed and used by Vietnam Paper Corporation that has not been cleared.

"The government has publicized compensation, support and resettlement plans. When the public disclosure period ends, we will invite the representative of the Paper Company to the ward to continue discussing and soon agree on the site clearance plan" - the representative said.

In November, the locality will approve all remaining plans, striving to complete site clearance in December according to the city's direction.

In Phu Dong commune, site clearance for the Duong River waterway upgrade project is also being implemented. However, according to records, there are still many households that have not agreed to hand over the site. They said that the current compensation and resettlement support level is not satisfactory.

s
s
A residential area in Phu Dong commune has not been cleared. Photo: Song Huu

The Duong River waterway upgrade project (including a road and railway bridge across the Duong River) was approved for investment by the Ministry of Transport (now the Ministry of Construction), with the goal of completion in 2025.

The project includes 2 construction packages: railway bridge (XL-CD-01) and road bridge (XL-CD-02), with a total investment of nearly VND 1,850 billion.

According to the reporter of Lao Dong Newspaper in mid-November 2025, the construction of project items is being implemented by the contractor.

Regarding the project progress, a representative of the Railway Project Management Board (Ministry of Construction) said that the XL-CD-01 package (rail bridge) started construction on September 12, 2023, and to date the completed volume is more than 49% of the contract value.

Package XL-CD-02 (road bridge) started construction on September 5, 2023, the completed volume reached 43.7% compared to the contract, has completed pillars T3; pillars T4, T5 have completed the lower structure, and are currently under construction of the bridge tower.

The approach bridges, approach roads, service roads, branch routes, etc. have been stalled and have not been constructed due to land clearance problems.

s
The Duong River road and railway bridge will start construction in 2023. Photo: Song Huu
s
The railway bridge package (red) has completed nearly 50% of the workload. Photo: Song Huu
s
The two pillars of the road bridge in the middle of the Duong River have taken shape. Photo: Song Huu

According to the plan, Long Bien district and Gia Lam district (now Viet Hung ward and Phu Dong commune) will complete site clearance and hand over to the contractor in the fourth quarter of 2024 (including enforcement if any).

However, during the implementation process, some contents were prolonged (project approval was delayed by 6 months, the new Land Law took effect from August 1, 2024...) leading to site clearance progress not meeting requirements.

Due to the slow site clearance, the Ministry of Construction recently adjusted the completion time of the railway and road bridge across the Duong River to 2026, a year later than planned.

Along with adjusting the project progress, the Ministry of Construction assigned the Railway Project Management Board to closely coordinate with departments, branches, and Hanoi City authorities to urgently clear the site, relocate technical infrastructure, hand over clean land to the contractor for construction; report problems to be resolved.

HỮU CHÁNH
RELATED NEWS

Hanoi is about to hand over enough land, 2 billion-dollar bridges across the Duong River will be completed next year

|

Hanoi - In the fourth quarter, the locality will hand over the site to the investor to build 2 road and railway bridges across the Duong River, completing the project in 2026.

Hanoi is slow to hand over the site, Duong River bridge delays progress

|

Hanoi's delay in handing over the site has hindered the progress of the Duong River bridge project, even though the railway industry has made 10 requests.

Hanoi announced a situation of urgent landslide in the Duong river bank in Long Bien district

|

Hanoi - City People's Committee issued a decision on the announcement of emergency situations landslide on the Duong river bank in Ngoc Thuy ward, Long Bien district.

Long Bien leases nearly 13,000m2 of land along the Duong River dike, priced from 525 million VND/year

|

Hanoi - Long Bien District rented nearly 13,000m2 of land in Phuc Loi ward, 20m from the Duong river dike corridor.

Raising red carp to serve Ong Cong Ong Tao, people earn big profits near Tet

|

Ninh Binh - Red carp farming households serving the Ong Cong Ong Tao festival are entering the biggest harvest season of the year, many families are busy selling fish to the market.

Mr. Tran Sy Thanh is recommended by voters to run for National Assembly deputy

|

Hanoi - 100% of voters at the place of residence unanimously recommended comrade Tran Sy Thanh to run for National Assembly Deputy of the 16th term.

Will cold air cause rain and severe cold during the 2026 Lunar New Year

|

According to representatives of the meteorological agency, there are no signs of strong cold air appearing during the Lunar New Year 2026 period.

Cambodia condemns Thailand's move along the border

|

The Cambodian government believes that Thailand's actions violate the agreement, change the border status, and hinder the lives of local people.

Hanoi is about to hand over enough land, 2 billion-dollar bridges across the Duong River will be completed next year

CHÁNH TIẾN |

Hanoi - In the fourth quarter, the locality will hand over the site to the investor to build 2 road and railway bridges across the Duong River, completing the project in 2026.

Hanoi is slow to hand over the site, Duong River bridge delays progress

Chánh Tiến |

Hanoi's delay in handing over the site has hindered the progress of the Duong River bridge project, even though the railway industry has made 10 requests.

Hanoi announced a situation of urgent landslide in the Duong river bank in Long Bien district

KHÁNH AN |

Hanoi - City People's Committee issued a decision on the announcement of emergency situations landslide on the Duong river bank in Ngoc Thuy ward, Long Bien district.

Long Bien leases nearly 13,000m2 of land along the Duong River dike, priced from 525 million VND/year

KHÁNH AN |

Hanoi - Long Bien District rented nearly 13,000m2 of land in Phuc Loi ward, 20m from the Duong river dike corridor.