Investor exposes banners expressing determination for the project to expand Hanoi's main arteries

SÓNG HỮU |

Hanoi - Investors and contractors have stretched out banners with the determination to complete a section of the project to expand National Highway 32 through Quang Oai commune in 2025.

In recent days, many people have been surprised when a notice appeared at the construction site of the National Highway 32 expansion project in Quang Oai commune (Hanoi) with the content: "The investor and contractor are determined to complete the project in 2025, the section from Power Company to the end of Lan Chi Supermarket in Quang Oai commune, Hanoi city".

According to local people, after a long period of sluggish construction, the fact that the investor and contractor set a goal of completing the project this year is also a positive sign.

"There is not much time left until the end of the year, we just hope that the investor will urge the contractor to speed up the construction progress to complete the route as set out, to make traffic convenient and the lives of people along the route will also change" - Ms. Bui Thi Thanh Phuong (29 years old, living next to the project site) said.

ss
National Highway 32 is a vital axis connecting Hanoi City with Phu Tho Province. Photo: Song Huu
ss
The banhon is located at the construction site of the National Highway 32 expansion project through Quang Oai commune, Hanoi. Photo: Song Huu

Speaking with Lao Dong, Mr. Vu Viet Cuong - Director of the Quang Oai Commune Infrastructure Investment Project Management Board (representative of the investor) said that the project to upgrade and expand National Highway 32, the section passing through Tay Dang town (old Ba Vi district, now Quang Oai commune) phase 1 is about 1.7km long.

Of which, the section from Ba Vi Power Company to the end of Lan Chi Supermarket is about 800m long.

Mr. Cuong said that the continuous storms and rains in recent months have made it impossible for the contractor to carry out construction on site.

ss
Machinery gathered at the project site. Photo: Song Huu

Up to now, when the weather is favorable, the contractor has mobilized many machines to implement the construction of project items such as roadbed compaction, crushed stone province, sidewalks, etc.

At the same time, the construction unit is also coordinating with relevant parties to implement the undergrounding of the power system, relocation of the traffic light system at the National Highway 32 - Thanh Nien intersection.

"The investor has urged the contractor to develop a suitable construction organization plan, increase shifts, increase shifts to complete and open the 800m section from Ba Vi Power Company to Lan Chi Supermarket in 2025, helping people travel smoothly" - Mr. Cuong said.

The Investment - Infrastructure Project Management Board also requires contractors to add signs and instructions for traffic safety systems on the route; arrange to increase irrigation to keep the road surface moist, reduce road dust to avoid affecting the visibility of traffic participants.

ss
The project to expand National Highway 32 through Quang Oai commune is under construction. Photo: Song Huu

The remaining section of the route, about 900m long, cannot be constructed synchronously due to land clearance problems.

Mr. Cuong said that there are currently more than 200 households whose land is being reclaimed and cleared to implement the project.

Before the operation of the 2-level local government model, Ba Vi district (old) had approved 67 plans. To date, only 15 households have received compensation.

With the remaining approved plans, local authorities are actively propagating and mobilizing people to receive money and hand over the site.

"We aim to complete the payment of approved plans in 2025 to serve as a springboard to promote site clearance progress in 2026" - Mr. Cuong said.

Currently, the local government has also reported to the Hanoi Department of Construction to extend the project completion time to the end of 2026, 1 year later than the original plan.

SÓNG HỮU
RELATED NEWS

Hanoi expands arterial roads, many people do not cooperate to hand over land

|

Hanoi - Considering the compensation price is lower than the market price, many households have not yet agreed to hand over the site for the construction of the National Highway 32 expansion project.

Putting into use 800m of the arterial road expansion project in Hanoi in 2025

|

Hanoi - The 800m project to upgrade and expand National Highway 32 through Quang Oai commune is expected to be completed in 2025, helping people travel smoothly.

Time to hand over enough land to open a 40m wide arterial road in Hanoi

|

Hanoi - It is expected that in the second quarter of 2026, the wards will hand over enough land to construct the expansion of Tam Trinh Street to 40m, with an investment capital of VND 3,354 billion.

International beauties, used cars add sparkling beauty to Da Lat streets

|

Da Lat - Da Lat City of Thousands of Flowers is more sparkling with the participation of nearly 80 international beauties and dozens of ancient cars participating in the parade through the streets.

Electricity says Ecohome Nhon Binh lacks cooperation in power generation

|

Gia Lai - Regarding the prolonged power outage at Ecohome Nhon Binh Social Housing Apartment, the Electricity sector said it has provided full support but the repair process is still very slow.

Thien Khoi FC crowned champion of the 2025 National 7-a-side Football Cup

|

Defeating Dai Tu in a dramatic final match, Thien Khoi FC became the champion of the 2025 Hyundai Thanh Cong Cup National 7-a-side Football Cup (VSC-S5).

Traffic ban on Prenn Pass to Da Lat from tomorrow afternoon, December 8

|

Lam Dong - The ban on traffic on Prenn Pass will take place from 11am to 5pm on December 8 to cut down trees at risk of falling, causing traffic insecurity.

Gia Bac Pass in Lam Dong opens to traffic after 5 days of paralysis due to serious landslides

|

Lam Dong - At 5:00 p.m. this afternoon, Gia Bac Pass officially opened the route, vehicles on National Highway 28 began traveling again after a period of paralysis due to landslides.

Hanoi expands arterial roads, many people do not cooperate to hand over land

Chánh Tiến |

Hanoi - Considering the compensation price is lower than the market price, many households have not yet agreed to hand over the site for the construction of the National Highway 32 expansion project.

Putting into use 800m of the arterial road expansion project in Hanoi in 2025

HỮU CHÁNH - ĐẶNG TIẾN |

Hanoi - The 800m project to upgrade and expand National Highway 32 through Quang Oai commune is expected to be completed in 2025, helping people travel smoothly.

Time to hand over enough land to open a 40m wide arterial road in Hanoi

SÓNG HỮU |

Hanoi - It is expected that in the second quarter of 2026, the wards will hand over enough land to construct the expansion of Tam Trinh Street to 40m, with an investment capital of VND 3,354 billion.