Chairman of Ho Chi Minh City People's Committee urgently directs not to allow the 3,400 billion VND intersection to be behind schedule

MINH QUÂN |

HCMC - Faced with the risk of the An Phu intersection project being behind schedule for more than a year, the Chairman of the HCMC People's Committee directed to complete the project before December 31, 2025.

On August 21, the Ho Chi Minh City People's Committee issued an urgent document on speeding up the completion of the An Phu intersection construction project.

Starting construction at the end of 2022, the An Phu intersection at the eastern gateway of Ho Chi Minh City has a total investment of more than VND 3,400 billion, approved to be completed in December 2025.

However, according to a report by the Ho Chi Minh City Department of Construction, the project has only reached about 70% of the volume.

Many important items are still sluggish. The HC1-02 underpass (connecting the Ho Chi Minh City - Long Thanh - Dau Giay Expressway with Mai Chi Tho) and the N3, N4 overpasses (connecting Mai Chi Tho with Dong Van Cong) are expected to be completed by June 30, 2026.

More worryingly, the N1, N1, N1, N1.2 overpasses and the entire project are likely to be completed by the end of December 2026, which is about a year behind schedule.

In this situation, the Chairman of the Ho Chi Minh City People's Committee directed the Director of the Traffic Construction Investment Project Management Board (Traffic Board - investor) to urgently review and evaluate the capacity of all contractors.

The city requires tightening contract management, applying full sanctions for units behind schedule, from volume transfer, personnel replacement, advance payment collection to contract termination if necessary. The review results must be reported to the Ho Chi Minh City People's Committee and the Department of Construction before August 25, 2025.

In addition, the Traffic Department must strengthen on-site supervision, requiring supervision consultants to enhance their sense of responsibility, ensure quality and progress.

Contractors are ordered to add machinery and human resources, expand construction teams, organize "3 shifts, 4 teams" to compensate for the slow volume, and at the same time build detailed progress for each remaining item, report before August 25, 2025 to serve as a basis for project management.

The Chairman of the Ho Chi Minh City People's Committee emphasized: "The project must be completed and put into operation before December 31, 2025, in accordance with Resolution No. 11/NQ-HDND dated April 22, 2021 of the City People's Council".

The Director of the Traffic Department will be fully responsible if the project continues to be delayed.

Toan canh du an nut giao An Phu (TPHCM). Anh: Anh Tu
Overview of the An Phu intersection project (HCMC). Photo: Anh Tu

The An Phu intersection is built on a 3-storey scale, including a two-way underpass connecting the Ho Chi Minh City - Long Thanh - Dau Giay Expressway with Mai Chi Tho Avenue; a system of overpasses connecting the right turn and left turn of the main traffic directions; along with the central roundabout and the symbolic tower.

When completed, the project will not only solve the serious congestion at the eastern gateway of Ho Chi Minh City but also play a strategic role in connecting the expressway with Mai Chi Tho, Luong Dinh Cua, Dong Van Cong, Nguyen Thi Dinh streets, while ensuring synchronous exploitation when Long Thanh International Airport comes into operation in early 2026.

MINH QUÂN
RELATED NEWS

The largest intersection project in Ho Chi Minh City is delayed to the end of 2026

|

HCMC - The An Phu intersection project worth more than VND3,400 billion at the eastern gateway of HCMC is expected to be completed by December 31, 2026 - 12 months behind schedule.

An Phu intersection, Tham Luong canal, Nguyen Khoi bridge and road are named for being behind schedule

|

HCMC - The An Phu intersection project, My Thuy intersection, National Highway 50 expansion, Nguyen Khoi bridge and road, and Tham Luong - Ben Cat canal renovation are at a standstill.

An Phu intersection underpass officially opens to traffic, expected to reduce congestion at the eastern gateway of Ho Chi Minh City

|

At 12:00 on June 30, the 4-lane underpass at An Phu intersection, Ho Chi Minh City was officially put into operation.

Vietnam General Confederation of Labor sets a target to build more than 10,700 houses for workers to rent

|

Implementing the tasks assigned in the Project to develop at least 1 million social housing units in the period 2021-2030, the Vietnam General Confederation of Labor is implementing housing projects for workers to rent in many localities.

Prime Minister Le Minh Hung presents flowers to congratulate the Executive Committee of the 14th Vietnam General Confederation of Labour

|

At the 14th Vietnam Trade Union Congress, Prime Minister Le Minh Hung presented flowers to congratulate the Executive Committee of the 14th Vietnam General Confederation of Labor, term 2026-2031.

From "Trade Union Shelter" to housing policies for workers

|

Khanh Hoa - At the 14th Congress of the Vietnam Trade Union, the delegation of the Provincial Trade Union brought many recommendations to improve the lives of union members and workers.

Forming a "Trade Union Ecosystem" in Dong Thap Industrial Parks

|

Dong Thap - Mr. Nguyen Thanh Nhan - Member of the Standing Committee of the Dong Thap Provincial Labor Federation, Chairman of the Trade Union of Industrial Zones and Economic Zones - wrote an article in response to the direction of General Secretary and President To Lam at the 14th Congress of the Vietnam Trade Union, which became a direction for deploying work at his unit.

Master digital space to be closer to workers

|

At the 14th Congress of the Vietnam General Confederation of Labour, term 2026 - 2031, Mr. Nguyen Van Thang - Member of the Presidium of the Vietnam General Confederation of Labour, City Party Committee Member, Vice Chairman of the Vietnam Fatherland Front Committee of Hanoi City, Chairman of the Hanoi Labor Federation - presented a paper on propaganda, political, ideological, and legal education for union members and workers...

The largest intersection project in Ho Chi Minh City is delayed to the end of 2026

MINH QUÂN |

HCMC - The An Phu intersection project worth more than VND3,400 billion at the eastern gateway of HCMC is expected to be completed by December 31, 2026 - 12 months behind schedule.

An Phu intersection, Tham Luong canal, Nguyen Khoi bridge and road are named for being behind schedule

MINH QUÂN |

HCMC - The An Phu intersection project, My Thuy intersection, National Highway 50 expansion, Nguyen Khoi bridge and road, and Tham Luong - Ben Cat canal renovation are at a standstill.

An Phu intersection underpass officially opens to traffic, expected to reduce congestion at the eastern gateway of Ho Chi Minh City

Anh Tú |

At 12:00 on June 30, the 4-lane underpass at An Phu intersection, Ho Chi Minh City was officially put into operation.