Dak Lak Police go to the grassroots level to remove bottlenecks in site clearance for expressway construction

BẢO TRUNG |

Dak Lak - The police force has coordinated with local authorities to mobilize many households to voluntarily hand over land to serve the construction of the expressway through the area.

On June 8, Dak Lak Provincial Police said that from the beginning of 2026 to now, the Provincial Police force has coordinated with local authorities to successfully mobilize many households to voluntarily hand over land to implement component project 3, belonging to the Khanh Hoa - Buon Ma Thuot expressway.

This result shows the effectiveness of mass mobilization work, contributing to removing "bottlenecks" in site clearance, creating conditions for construction units to accelerate project progress.

Accordingly, police officers and soldiers directly went to the grassroots level to meet, dialogue, listen to the thoughts and aspirations of the people; and at the same time propagate and explain clearly the meaning and importance of the project as well as compensation, support and resettlement policies according to regulations.

Thanks to this, many households have agreed and voluntarily handed over the land without having to apply coercive measures.

Lực lượng công an phối hợp với các đơn vị liên quan, chính quyền địa phương tháo gỡ vướng mắc, triển khai thi công hoàn thiện dự án cao tốc. Ảnh: Chính Nhân
The police force coordinates with relevant units and local authorities to remove obstacles and deploy construction to complete the expressway project. Photo: Chinh Nhan

One of the typical cases is the mobilization of Mr. N.V.T's household (residing in Dak Lak province) to voluntarily hand over the land area to serve the construction of the tunnel slope item of the expressway.

Previously, although functional agencies had repeatedly propagated and dialogued, the obstacles still lasted, affecting the project implementation progress.

In parallel with that, based on firmly grasping the situation, the police force has coordinated with local authorities and relevant units to persistently meet, exchange, and explain; and listen to the difficulties and legitimate petitions of the people.

Since then, functional forces have created consensus, helping households voluntarily hand over land, contributing to removing one of the important bottlenecks of the project without the need for coercion.

According to Mr. Dang Tho Dan, Managing Director of Component Project 3, Project Management Board for Investment and Construction of Transport and Agriculture and Rural Development Projects of the province, to date, the project has completed nearly 97% of the construction volume and is basically technically cleared.

However, in some locations, there are still difficulties and obstacles related to site clearance for auxiliary items.

Currently, levels, sectors and localities are continuing to review and resolve people's petitions in accordance with the law, ensuring the legitimate rights and interests of the people, and creating conditions for the project to be completed soon according to plan.

BẢO TRUNG
RELATED NEWS

Slow progress, 2 highway rest stops through Ha Tinh are still unfinished

|

Ha Tinh - Two rest stops on the North-South expressway are still under construction even though the completion milestone is approaching, the Road Administration sent an official dispatch requesting to speed up progress.

46 households receive compensation for site clearance phase 2 of Van To IC, Hai Phong

|

Hai Phong - Chi Minh commune has just paid more than 23.6 billion VND in compensation and support for site clearance phase 2 to 46 households serving the Van To Industrial Cluster Project.

Accelerate the progress of site clearance for Van Lang Industrial Cluster, Hung Yen

|

Hung Yen - Hung Ha commune is deploying to remove obstacles and accelerate site clearance for Van Lang Industrial Cluster.

European leaders support Russia-Ukraine ceasefire talks

|

Britain, France and Germany affirmed that Europe needs to actively participate in peace negotiation efforts.

In early July, excavation of the collective grave of martyrs at Le Thi Rieng Park

|

Ho Chi Minh City - Deputy Prime Minister Pham Thi Thanh Tra requested to deploy excavation of the mass grave of martyrs at Le Thi Rieng Park from the beginning of July.

Video of goal U19 Vietnam - U19 Indonesia (1-2)

|

U19 Vietnam lost 1-2 to U19 Indonesia. Watch the Southeast Asia U19 Championship exclusively from June 1 - June 14 on TV360 at https://tv360.vn. Free Viettel 4G/5G data.

Energy Transition - Driving Force for Double-Number Growth Goals

|

On June 9, 2026, Lao Dong Newspaper in coordination with the Ministry of Industry and Trade organized the Workshop "Energy Transition - Driving Force for Two-digit Growth Goals".

Slow progress, 2 highway rest stops through Ha Tinh are still unfinished

TRẦN TUẤN |

Ha Tinh - Two rest stops on the North-South expressway are still under construction even though the completion milestone is approaching, the Road Administration sent an official dispatch requesting to speed up progress.

46 households receive compensation for site clearance phase 2 of Van To IC, Hai Phong

Mai Hương |

Hai Phong - Chi Minh commune has just paid more than 23.6 billion VND in compensation and support for site clearance phase 2 to 46 households serving the Van To Industrial Cluster Project.

Accelerate the progress of site clearance for Van Lang Industrial Cluster, Hung Yen

Mai Hương |

Hung Yen - Hung Ha commune is deploying to remove obstacles and accelerate site clearance for Van Lang Industrial Cluster.