Hundred billion VND industrial cluster in Thai Nguyen remains motionless after 5 years

Việt Bắc |

Thai Nguyen - After more than 5 years of implementation, the Ba Xuyen Industrial Cluster project (Song Cong City) is still inactive, at risk of wasting land resources.

The Ba Xuyen Industrial Cluster Project (CCN Ba Xuyen) in Ba Xuyen Commune, Song Cong City was implemented from the end of 2018 with a total investment of over 431 billion VND. The investor is Minh Tuan Construction Investment and Trading Joint Stock Company.

According to the reporter's records at the end of August 2024, after more than 5 years of implementation, the hundred billion dong project is still just a desolate, shabby land. Apart from a few construction materials being transported to the construction site, no items have been completed.

Most of the project items have not been constructed yet, many areas of land are left vacant, overgrown with weeds. Some construction areas have created ditches and water holes that are not covered or have warning signs of safety risks.

Ba Xuyen Industrial Park lies dormant after many years of implementation.
CCN Ba Xuyen lies dormant after many years of implementation.

According to schedule, the Ba Xuyen Industrial Park project will be completed in 2024 with the expectation of creating jobs for thousands of local workers. However, at present, the project is still in a state of inactivity with no clear completion date.

According to information from the People's Committee of Ba Xuyen commune, the reason why Ba Xuyen Industrial Park could not finish on time compared to the expected time was because of problems in compensation and site clearance (GPMB).

At the time of implementation, many households whose land was to be recovered for the project did not agree with the compensation plan because they thought the compensation amount was not enough to meet their housing and livelihood needs, so they did not hand over the land.

Inside the Ba Xuyen Industrial Park project, there is still almost only empty land.
Ba Xuyen Industrial Park project has a large area of ​​recovered land.

Therefore, by mid-first quarter of 2024 (after more than 5 years of implementation), the Ba Xuyen Industrial Park project has only cleared 30.96/48.53 hectares, reaching nearly 64%.

On the other hand, during the implementation process, investors encountered some difficulties and problems such as adjusting the detailed planning of the project, the deadline for the Prime Minister to allow the change of rice land use purpose expired, the investor had to request an extension of the project implementation time...

Mr. Ha Trong Dong (Song Cong City) said: "When Ba Xuyen Industrial Park started to be implemented, local people were very happy because the project would create jobs.

The inside is now messy and messy. I don't know if the project will continue or when it will be completed.

Many deep water holes formed at the unfinished construction site, risk of accidents.
Many deep water holes formed at the unfinished construction site, risk of accidents.

According to local people, the Ba Xuyen Industrial Park project is expected to create jobs for children in the area, especially families whose rice fields have been reclaimed.

However, after the land was reclaimed, it was left unused for many years, causing people to feel sorry for the waste of land resources.

Talking to reporters, Mr. Do Trong Lu - Chairman of Ba Xuyen Commune People's Committee said that Ba Xuyen Industrial Park project has a large area of ​​land to be recovered, including rice fields and agricultural land. People also hope that the project will be completed soon to create jobs and improve the lives of local people.

Also according to the People's Committee of Ba Xuyen commune, the Ba Xuyen Industrial Park project has just been allocated land recently, after the land is allocated, it can continue with the next steps.

Currently, the investor is preparing a document requesting the competent authority to extend the project implementation until 2026.

Việt Bắc
TIN LIÊN QUAN

Cụm công nghiệp gần 30ha tại TP Thái Nguyên vướng mặt bằng

Lam Thanh |

Việc chậm giải phóng mặt bằng, bố trí tái định cư khiến dự án cụm công nghiệp Sơn Cẩm 3 (TP Thái Nguyên) triển khai chậm trễ.

Những ngôi nhà chờ sập do vướng quy hoạch cụm công nghiệp

Lam Thanh |

Hàng chục hộ dân tại xã Sơn Cẩm (TP Thái Nguyên) đang sống bất an trong những ngôi nhà xập xệ, nằm trong diện quy hoạch nên không thể xây dựng, sửa sang.

Cụm công nghiệp mong "thoát ế" nhờ cung đường 245 tỉ đồng

Bài và ảnh: Tô Công |

Phú Thọ - Công trình giao thông nối từ Cụm công nghiệp Bắc Lâm Thao qua Quốc lộ 2 đến Cụm công nghiệp Phú Gia sau gần 2 năm thi công nay đã thành hình.

Xe tải bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết

Duy Tuấn |

Bình Thuận - Xe tải đang lưu thông thì bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết.

Tin 20h: Yên Bái kiểm tra nhà hàng "chặt chém" đoàn từ thiện

Nhóm PV |

Tin 20h ngày 19.9: Bà Nguyễn Phương Hằng được ra tù vào hôm nay; Yên Bái kiểm tra nhà hàng bị tố chặt chém đoàn từ thiện...

Phía Miss Universe nói về thông tin Kỳ Duyên chưa tốt nghiệp

Huyền Chi |

Thông tin Hoa hậu Kỳ Duyên chưa tốt nghiệp Trường Đại học Ngoại Thương gây xôn xao mạng xã hội.

Thể Công Tân Cảng bảo vệ thành công chức vô địch giải bóng chuyền U23 Quốc gia 2024

Nhóm PV |

U23 Thể Công Tân Cảng thắng U23 Ninh Bình 3-1 tại chung kết giải bóng chuyền U23 quốc gia vào tối 19.9.

Chậu hoa giấy trên phố đi bộ ở Đà Nẵng đồng loạt "nằm" tránh bão

Nguyễn Linh |

UBND quận Hải Châu, TP Đà Nẵng cho biết đã chủ động đặt nằm các chậu hoa giấy tại phố đi bộ Bạch Đằng để tránh thiệt hại bởi ảnh hưởng của cơn bão số 4.

The industrial cluster of nearly 30 hectares in Thai Nguyen City has land problems

Lam Thanh |

The delay in site clearance and resettlement arrangement caused the Son Cam 3 industrial cluster project ( Thai Nguyen City ) to be delayed.

The industrial cluster hopes to "escape" thanks to the 245 billion VND road

Bài và ảnh: Tô Công |

Phu Tho - The traffic project connecting Bac Lam Thao Industrial Cluster via National Highway 2 to Phu Gia Industrial Cluster after nearly 2 years of construction has now taken shape.