Adjusting trillion project in Thanh Hoa due to lack of capital

Xuân Hùng |

Thanh Hoa Provincial People's Committee decided to adjust the implementation of the road project from No Hen bridge to Provincial Road 514.

On July 29, the Department of Transport of Thanh Hoa province said that the road project connecting Thanh Hoa City to Tho Xuan airport, from No Hen bridge to Provincial Road 514, has been stalled for many years, causing difficulties for people. Now, there is a solution. handle.

To have a basis for allocating capital and continuing to complete the project, the Department of Transport of Thanh Hoa province submitted a report to the Provincial People's Committee proposing to adjust the project content.

Accordingly, adjusting the project implementation time from "No more than 5 years (from 2019 - 2023)" to "Completed in 2025" at the same time as the above content is adjusting the implementation time of successful contracts. Technical sections and stops based on the assigned capital plan, ensuring not to exceed the implementation time of the entire approved project.

According to Thanh Hoa Department of Transport, adjusting the project implementation time does not change the approved goals and scale of the project and continuing to implement the contract and complete it in 2025 is necessary.

Based on the report of Thanh Hoa Department of Transport, Mr. Mai Xuan Liem - Vice Chairman of Thanh Hoa Provincial People's Committee signed a decision to adjust the project content and adjusted content according to the proposal of the Department of Transport.

Vice Chairman of Thanh Hoa Provincial People's Committee also requested that during the process of extending the time to implement the bidding package, the investor must work with the contractor to classify and analyze the work behind schedule due to various causes. subjectively and objectively to handle arising issues in accordance with the signed contract terms and current regulations on construction investment management; Inspect, review and strictly manage project costs, ensuring compliance with current legal regulations.

As Lao Dong informed , the above project passes through many communes of Trieu Son and Nhu Thanh districts, approved by the Chairman of Thanh Hoa Provincial People's Committee in Decision No. 4521/QD-UBND dated October 31, 2019; The investor is the Department of Transport of Thanh Hoa province.

The project scale is to invest in upgrading and expanding 12,113km of existing roads to ensure the scale of level 3 plain roads with a total investment of nearly 972 billion VND. Project implementation period is no more than 5 years (2019 - 2023).

However, after many years of implementation, the above project is still unfinished, causing many difficulties for people's lives. Up to now, the People's Committee of Thanh Hoa province has only allocated funds to pay compensation for agricultural land and crops on the land. The remaining compensation funds for residential land and architectural objects of households do not have compensation funds. Many households live in a state of suspended planning, not knowing when they will be paid to move to a new place.

The reason, according to the People's Committee of Thanh Hoa province, through the process of organizing site clearance, the specific land price to calculate compensation when the State recovers land has increased 2-3 times compared to the approved estimate, leading to the total cost. Land clearance of the project exceeded 846 billion VND, an increase of more than 456 billion VND compared to the previously approved estimate.

Thus, the additional capital needed to complete site clearance is more than 777 billion VND.

The rising cost of site clearance has exceeded the province's ability to balance capital sources for the project because the province's medium-term public investment plan has fully allocated to tasks and projects in Resolution No. 123/NQ-HDND dated October 11. .2021 and medium-term public investment plan with State budget capital for the period 2021 - 2025 in Thanh Hoa province.

Xuân Hùng
TIN LIÊN QUAN

Dự án hơn 49 tỉ đồng về sức khỏe ở Quảng Bình 7 năm chưa xong

CÔNG SÁNG |

Dự án Trung tâm Truyền thông - Giáo dục sức khỏe Quảng Bình được đầu tư 49,3 tỉ đồng, xây dựng từ năm 2017 nhưng đến nay vẫn chưa hoàn thành.

Ngổn ngang thi công 5 cây cầu ở dự án đường ven sông Cái

HÀ ANH CHIẾN |

Đồng Nai - 5 cây cầu trên dự án đường ven sông Cái (từ Hà Huy Giáp đến Trần Quốc Toản, TP Biên Hòa) có tổng mức đầu tư 3.960 tỉ đồng vẫn đang ngổn ngang.

Dự án đấu giá đất ở Quảng Ngãi không có nhà đầu tư tham gia

VIÊN NGUYỄN |

Các dự án đấu giá đất ở Quảng Ngãi đang gặp khó khăn vì không thu hút được nhà đầu tư, là một trong những nguyên nhân khiến tỉnh này hụt thu tiền sử dụng đất.

Vụ công trình làm nứt nhà dân ở Hà Nội, chính quyền nói gì?

NHÓM PV |

Theo chính quyền phường Quang Trung, hình ảnh công nhân đang làm việc tại công trình số nhà 19, ngõ 136/98 Tây Sơn là để hút nước phòng dịch sốt xuất huyết.

Triều Tiên cho nổ tung tuyến đường bộ nối với Hàn Quốc

Khánh Minh |

Triều Tiên cho nổ tung các tuyến đường nối với Hàn Quốc vốn từng được coi là biểu tượng của sự hợp tác liên Triều.

Thân tín của bà trùm ma túy Oanh "Hà" được trả công 15 tỉ

Việt Dũng |

Trong số hơn 626kg ma túy mua bán xuyên quốc gia do bà trùm Oanh "Hà" cầm đầu, Nguyễn Văn Nam có mặt hầu hết ở các chuyến hàng, nhận công hậu hĩnh.

Bất cập tiền công đức 2 đền ở Ninh Bình do nguồn thu quá lớn

NGUYỄN TRƯỜNG |

Ninh Bình - Những tồn tại, bất cập trong việc quản lý tiền công đức tại đền Dâu và đền Quán Cháo (thành phố Tam Điệp) là do nguồn thu quá lớn.

Chánh văn phòng hãng luật bị tố đe dọa, xúc phạm phụ nữ

TRÍ MINH |

Một chánh văn phòng hãng luật bị tố cáo có hành vi đe dọa, xúc phạm danh dự, nhân phẩm phụ nữ. Người dân đã trình báo sự việc tới cơ quan công an.

The project of more than 49 billion VND on health in Quang Binh has not been completed for 7 years

CÔNG SÁNG |

The Quang Binh Health Education and Communication Center project was invested 49.3 billion VND, built in 2017 but has not yet been completed.

Chaotic construction of 5 bridges at the Cai River road project

HÀ ANH CHIẾN |

Dong Nai - 5 bridges on the Cai River road project (from Ha Huy Giap to Tran Quoc Toan, Bien Hoa City) with a total investment of 3,960 billion VND are still in disarray.

The land auction project in Quang Ngai has no investors participating

VIÊN NGUYỄN |

Land auction projects in Quang Ngai are facing difficulties because they cannot attract investors, which is one of the reasons why this province lacks land use fee collection.