Ring Road 2.5 section, 582m long, is expected to be technically opened to traffic in September 2026

SÓNG HỮU |

Hanoi - Ring Road 2.5 section passing through Xuan Dinh ward, 582m long, is expected to be technically opened to traffic before September 30th after many years of stagnation due to site clearance issues.

The project to build road No. 5 into the center of Tay Ho Tay New Urban Area (ring road 2.5 through Xuan Dinh ward, Hanoi) has a length of 582m and a cross-section of 50m.

The project includes items such as building the foundation, road surface, drainage, water supply, technical trenches, lighting, sidewalks, green trees, and traffic organization.

According to Xuan Dinh Ward People's Committee, the total recovered area of the project is 28,318m2, of which 98 households are affected.

The project was started in January 2021, with a construction time of 320 days. However, due to problems in site clearance, the project was stalled for a long time.

By the end of June 2026, the entire site has been handed over, creating conditions for the project to accelerate implementation.

Công trường dự án đường Vành đai 2,5 qua địa bàn phường Xuân Đỉnh (Hà Nội), sáng 11.9. Ảnh: Sóng Hữu
Construction site of Ring Road 2.5 project through Xuan Dinh ward (Hanoi), morning of the 11th. 9. Photo: Song Huu

According to Lao Dong's records on September 11, many machines, equipment and a team of engineers and workers were mobilized by the contractor to serve the construction work.

Looking from above, the Ring Road 2.5 section connecting from the Diplomatic Corps area to Nguyen Hoang Ton street has revealed its shape.

Taking advantage of favorable weather, the contractor is making efforts to accelerate the project progress.

Máy móc, công nhân làm việc trên công trường dự án. Ảnh: Sóng Hữu
Machinery and workers working at the project construction site. Photo: Song Huu

Up to now, the roadbed item and underground technical infrastructure system have been completed; asphalt paving, sidewalk paving, curbs, installation of lighting systems, green trees and traffic organization are being urgently implemented according to schedule.

The goal is to complete the remaining items and technically open traffic before September 30, 2026.

Mr. Le Van Minh (Xuan Dinh ward) is excited that the Ring Road 2.5 project through the ward has had very positive changes recently.

Everyone hopes that the project will be completed soon so that travel is convenient and the urban appearance will also have a big change" - Mr. Minh said.

s
s
People and vehicles circulating on the route. Photo: Song Huu
s
Some sections have been paved with sidewalk stone. Photo: Song Huu
csc
Green tree system planted along the route. Photo: Song Huu
scsc
The intersection with Nguyen Hoang Ton street has been asphalted. Photo: Song Huu

The project to build road No. 5 to the center of Tay Ho Tay New Urban Area plays a role as a key traffic route contributing to promoting socio-economic development of the area and completing the urban transport network, strengthening connectivity, reducing traffic pressure during peak hours, and improving the quality of the urban environment in the city in general and Xuan Dinh ward in particular.

SÓNG HỮU
RELATED NEWS

Hanoi Ring Road 2.5 is about to be closed

|

Hanoi - Ring Road 2.5 when closed will reduce congestion for Ring Road 2 and Ring Road 3 routes, contributing to the socio-economic development of the Capital.

Construction of Ring Road 2.5 causes dust and pollution, functional agencies intervene

|

Hanoi - Functional units have organized a working session to coordinate the handling of violations of traffic order and safety on Ring Road 2.5.

Thousands of tons of clams raised by people die after storms

|

Thanh Hoa - Mass clam deaths at about 60ha of farming ground of 50 households in Ngoc Son ward, estimated damage output from 2,000-2,400 tons.

Houthi forces completely control the strategic Bab al Mandab strait

|

Houthi forces in Yemen have just seized control of Mayyun Island and taken over the Bab al Mandab Strait, a vital shipping route for global oil exports.

Ministry of Industry and Trade requests Grab to clarify fares, fees, and discounts

|

The National Competition Committee (Ministry of Industry and Trade) is conducting a review and verification of reflections related to Grab's price and fee policies.

Case of former principal collecting 15,000 VND/sidetime tutoring: Parents say students benefit

|

Parents affirmed that their children benefited and there was no damage in the case of the former Principal of Ba Dinh Secondary School collecting 15,000 VND/sidetime tutoring.

Hanoi Ring Road 2.5 is about to be closed

SÓNG HỮU |

Hanoi - Ring Road 2.5 when closed will reduce congestion for Ring Road 2 and Ring Road 3 routes, contributing to the socio-economic development of the Capital.

Xe phun nước hoạt động liên tục, đường Vành đai 2,5 tạm hết cảnh bụi bẩn, ô nhiễm

SÓNG HỮU |

Hà Nội - Nhà thầu dự án đường đường Vành đai 2,5 tăng cường việc phun nước, tưới rửa mặt đường để giảm ô nhiễm sau phản ánh của Báo Lao Động.

Construction of Ring Road 2.5 causes dust and pollution, functional agencies intervene

SÓNG HỮU |

Hanoi - Functional units have organized a working session to coordinate the handling of violations of traffic order and safety on Ring Road 2.5.