Hanoi Ring Road 2.5 is about to be closed

SÓNG HỮU |

Hanoi - Ring Road 2.5 when closed will reduce congestion for Ring Road 2 and Ring Road 3 routes, contributing to the socio-economic development of the Capital.

At the construction site of Ring Road 2.5 section Cau Giay - Dich Vong New Urban Area (Cau Giay ward, Hanoi) in September, many machines and workers were mobilized to speed up construction progress.

The section has a length of 420m, started many years ago, but by May 2026, the local government will complete site clearance to deploy the construction of the road.

scasavc
Ring Road 2.5 project, Cau Giay section - Dich Vong New Urban Area is being accelerated for construction, September 1. Photo: Song Huu

Project commander - Mr. Do Van Giap said that the construction of items is being urgently deployed by the contractor.

The time from now until the technical traffic opening milestone is not much, so all engineers and workers are working hard every day, every hour to ensure the project progress" - Mr. Giap said.

Máy móc làm việc trên công trường dự án. Ảnh: Sóng Hữu
Machinery working at the project construction site. Photo: Song Huu

In addition to Ring Road 2.5, Cau Giay - Dich Vong New Urban Area section, other sections of the route such as Dich Vong - Duong Dinh Nghe New Urban Area; Vu Pham Ham - Tran Duy Hung; Nguy Nhu Kon Tum - Nguyen Trai; Nguyen Trai - Dam Hong... are also being urgently constructed.

The project section from Nguyen Trai to Dam Hong in Khuong Dinh ward is about 1.5km long.

The investor and contractors are organizing simultaneous construction of 3 fronts, prioritizing completing the underground technical infrastructure system, electricity and underground works to ensure synchronization before asphalt concrete paving.

Công trường dự án đường Vành đai 2,5 đoạn Nguyễn Trãi - Đầm Hồng, ngày 3.9. Ảnh: Sóng Hữu
Construction site of Ring Road 2.5 project, Nguyen Trai - Dam Hong section, September 3. Photo: Song Huu

The project to invest in the construction of Ring Road 2.5 sections: Dich Vong - Duong Dinh Nghe New Urban Area; Vu Pham Ham - Tran Duy Hung; Nguy Nhu Kon Tum - Nguyen Trai is divided into 3 sections, with a total length of about 2.26 km.

This is a project implemented under the urgent construction order of the City People's Committee and started on March 20, 2026.

To date, the Dich Vong - Duong Dinh Nghe New Urban Area section has reached about 80% of the volume, has completed the rainwater and wastewater drainage system and is constructing the foundation, road surface, and technical infrastructure, striving to basically complete it before October 5, 2026.

The remaining two sections are focusing on constructing the roadbed and drainage system.

However, according to the Hanoi Traffic Construction Investment Project Management Board, the construction process faces many difficulties due to both having to protect the existing underground technical infrastructure system on Nguyen Trai, Tran Duy Hung, Vu Pham Ham routes, and being affected by prolonged rainy weather, waste soil transportation and the receiving capacity of landfills are still limited.

d
Ring Road 2.5 section passing through Dich Vong New Urban Area, September 1. Photo: Song Huu

For the construction item of road No. 5 to the Center of Tay Ho Tay New Urban Area, the length of the route is 582.04m, cross-section 50m, connecting from the Diplomatic Corps area to Nguyen Hoang Ton street.

By the end of June 2026, the entire site has been handed over, creating conditions for the project to accelerate implementation.

Up to now, the roadbed item and underground technical infrastructure system have been completed; asphalt paving, sidewalk paving, curbs, installation of lighting systems, green trees and traffic organization are being urgently implemented according to schedule; the goal is to complete the remaining items and technically open traffic before September 30, 2026.

Đến nay, nhiều đoạn Vành đai 2,5 đã hoàn thành, đưa vào khai thác. Trong ảnh là đoạn Vành đai 2,5 đoạn Đầm Hồng - Quốc lộ 1A, ngày 3.9. Ảnh: Sóng Hữu
To date, many sections of Ring Road 2.5 have been completed and put into operation. Pictured is Ring Road 2.5, Dam Hong - National Highway 1A section, September 6. Photo: Song Huu

Inspecting the site of the Ring Road 2 project on September 9, Member of the Party Central Committee, Standing Deputy Secretary of the Hanoi Party Committee Nguyen Trong Dong requested units to mobilize maximum manpower, machinery, and equipment; maintain "3 shifts, 4 crews" construction, take advantage of favorable weather to compensate for progress, determined to technically open Ring Road 2.5 on the occasion of the Capital Liberation Day 10. 10.

Ring Road 2.5 starts from Ciputra New Urban Area, ending at the intersection with Ring Road 3 (section near Thanh Tri bridge) with a total length of about 19.64km, planned width of 40-50m.

It is expected that by October 10, when the remaining sections of the route are technically opened to traffic, Ring Road 2.5 Hanoi will be officially closed, helping to reduce congestion for Ring Road 2 and Ring Road 3 routes, contributing to the socio-economic development of the Capital.

SÓNG HỮU
RELATED NEWS

Construction of Ring Road 2.5 causes dust and pollution, functional agencies intervene

|

Hanoi - Functional units have organized a working session to coordinate the handling of violations of traffic order and safety on Ring Road 2.5.

The journey of effort and bravery of the world Pencak Silat champion

|

To win the world Pencak Silat championships, female martial artist Quynh Chi overcame many difficulties and seemed to have to give up due to injury.

Important changes in social pension benefits from October 5th

|

From October 5, 2026, new regulations on social pension payments have many points, in which priority is given to transferring money through bank accounts and social security accounts.

Russian Southern Army Corps begins offensive into Druzhkovka

|

Russia's new attack in Donetsk combined with a widespread air campaign to stifle the enemy's logistics line.

Large underpass at the gateway to Ho Chi Minh City flooded half a meter, cars stalled

|

Ho Chi Minh City - Heavy rain on the evening of September 10 caused the HC1-02 underpass at An Phu intersection, the eastern gateway of Ho Chi Minh City, to be flooded about 0.5m.

VTV General Director talks about information that Meritorious Artist, director Do Thanh Hai leaves VTV

|

Before the information that director, Meritorious Artist Do Thanh Hai left VTV after many years of attachment, Mr. Nguyen Thanh Lam - General Director of Vietnam Television (VTV) - spoke up.

Xe phun nước hoạt động liên tục, đường Vành đai 2,5 tạm hết cảnh bụi bẩn, ô nhiễm

SÓNG HỮU |

Hà Nội - Nhà thầu dự án đường đường Vành đai 2,5 tăng cường việc phun nước, tưới rửa mặt đường để giảm ô nhiễm sau phản ánh của Báo Lao Động.

Construction of Ring Road 2.5 causes dust and pollution, functional agencies intervene

SÓNG HỮU |

Hanoi - Functional units have organized a working session to coordinate the handling of violations of traffic order and safety on Ring Road 2.5.

Thi công dự án Vành đai 2,5 gây ô nhiễm, đi ngược Chỉ thị 08 của Hà Nội

HỮU CHÁNH |

Hà Nội - Nhà thầu không thực hiện đầy đủ biện pháp bảo đảm vệ sinh môi trường trong quá trình thi công dự án đường Vành đai 2,5 đoạn Nguyễn Trãi - Đầm Hồng.