On September 18, the People's Committee of Dong Nai province held a conference on disbursement of public investment capital for the last 9 months of 2025 and solutions to accelerate the disbursement of public investment capital for the last 3 months of 2025.
According to the Department of Finance, the capital plan of Dong Nai Provincial People's Committee is allocated more than VND 35,674 billion.
If the more than VND9,200 billion of the Gia Nghia - Chon Thanh expressway project is not included, the National Assembly will allow the extension of the disbursement period until the end of 2026 and the newly assigned additional plan is VND1,200 billion, then the rate will reach 52.2%, higher than the national average.
The remaining capital to be disbursed by the end of 2025 is more than VND 10,843 billion, an average of more than VND 2,700 billion per month to ensure 100% completion of the assigned plan.
The reason for the low disbursement is that many projects are still stuck in compensation and site clearance; some projects have to handle bidding recommendations; heavy rain; some projects have investors delaying the completion of project approval procedures; the urging of contractors to speed up the construction progress of some investors is not really drastic...
According to Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee, in the remaining time of 2025, for the disbursement of public investment capital, the province will apply the principle that any unit that completes well and ensures quality will be rewarded, commended, and given priority in assessment, planning, appointment, and year-end rewards. On the contrary, they will be downgraded to emulation, not considered for planning, appointment of positions, consideration of transfer of work...
From now until the disbursement deadline of December 31, every 2 weeks, the Department of Home Affairs will coordinate with the Department of Finance to review and update the implementation progress, as a basis for assessing the responsibility of the heads of the units. In case the target is not achieved according to the set work schedule, advise the Provincial People's Committee to transfer the work.