Dong Nai transfers the work of a leader if the public investment disbursement target is not achieved

HÀ ANH CHIẾN |

Dong Nai - To ensure the completion of 100% of the assigned public investment capital plan, from now until the end of 2025, the province must disburse an average of more than VND 2,700 billion per month.

On September 18, the People's Committee of Dong Nai province held a conference on disbursement of public investment capital for the last 9 months of 2025 and solutions to accelerate the disbursement of public investment capital for the last 3 months of 2025.

According to the Department of Finance, the capital plan of Dong Nai Provincial People's Committee is allocated more than VND 35,674 billion.

If the more than VND9,200 billion of the Gia Nghia - Chon Thanh expressway project is not included, the National Assembly will allow the extension of the disbursement period until the end of 2026 and the newly assigned additional plan is VND1,200 billion, then the rate will reach 52.2%, higher than the national average.

The remaining capital to be disbursed by the end of 2025 is more than VND 10,843 billion, an average of more than VND 2,700 billion per month to ensure 100% completion of the assigned plan.

The reason for the low disbursement is that many projects are still stuck in compensation and site clearance; some projects have to handle bidding recommendations; heavy rain; some projects have investors delaying the completion of project approval procedures; the urging of contractors to speed up the construction progress of some investors is not really drastic...

According to Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee, in the remaining time of 2025, for the disbursement of public investment capital, the province will apply the principle that any unit that completes well and ensures quality will be rewarded, commended, and given priority in assessment, planning, appointment, and year-end rewards. On the contrary, they will be downgraded to emulation, not considered for planning, appointment of positions, consideration of transfer of work...

From now until the disbursement deadline of December 31, every 2 weeks, the Department of Home Affairs will coordinate with the Department of Finance to review and update the implementation progress, as a basis for assessing the responsibility of the heads of the units. In case the target is not achieved according to the set work schedule, advise the Provincial People's Committee to transfer the work.

HÀ ANH CHIẾN
RELATED NEWS

Public investment projects in Gia Lai will help attract businesses

|

Gia Lai - Public investment projects will lead private investment and non-state enterprises, which are significant for the socio-economic development of the province.

Nghe An disbursed VND5,941 billion in public investment in the first 8 months of the year, ranking 11th nationwide

|

Nghe An - By August 31, Nghe An had disbursed VND5,941 billion, reaching 58.2% of the plan; higher than the national average, ranking 11th nationwide.

3 top leaders of Ho Chi Minh City urgently meet to speed up public investment disbursement

|

HCMC - Secretary of the City Party Committee Tran Luu Quang, Chairman of the People's Council Vo Van Minh and Chairman of the People's Committee Nguyen Van Duoc chaired a meeting to promote the disbursement of public investment capital.

Paying traffic fines using QR Codes, people in Ho Chi Minh City say quickly and transparently

|

HCMC - Traffic violators in HCMC believe that the procedure for paying traffic fines using on-site QR Codes is transparent and time-saving.

Thaco announces profit increase of 14%, total assets increase to more than 195.5 trillion VND

|

Thaco's financial report recorded that equity and total assets of enterprises in 2024 continue to increase sharply, but after-tax profits have not broken out.

Appointment and reappointment of 2 Army Major Generals and 1 Vice Admiral of the Navy

|

The Prime Minister appointed and reappointed 3 military personnel, of which Major General Le Dinh Cuong held the position of Commander of the Vietnam Coast Guard.

Da Nang calls for help because the expired BOT station still blocks the national highway, trucks avoid the station to overflow into residential areas

|

Da Nang - An Thang Ward has proposed to dismantle the expired BOT station but still blocks the national highway, causing trucks to avoid the station and rush into residential areas near schools.

Dak Lak Department of Health talks about how to handle the case of nearly 500 cases of kidney stone surgery when the machine is broken

|

Dak Lak - The provincial Department of Health talks about how to handle collectives and individuals in the case of nearly 500 cases of kidney stone surgery when the machine was broken after the police's conclusion.

Public investment projects in Gia Lai will help attract businesses

THANH TUẤN |

Gia Lai - Public investment projects will lead private investment and non-state enterprises, which are significant for the socio-economic development of the province.

Nghe An disbursed VND5,941 billion in public investment in the first 8 months of the year, ranking 11th nationwide

QUANG ĐẠI |

Nghe An - By August 31, Nghe An had disbursed VND5,941 billion, reaching 58.2% of the plan; higher than the national average, ranking 11th nationwide.

3 top leaders of Ho Chi Minh City urgently meet to speed up public investment disbursement

MINH QUÂN |

HCMC - Secretary of the City Party Committee Tran Luu Quang, Chairman of the People's Council Vo Van Minh and Chairman of the People's Committee Nguyen Van Duoc chaired a meeting to promote the disbursement of public investment capital.