The project to renovate the longest canal in Ho Chi Minh City is messy, people are miserable

MINH QUÂN |

The Tham Luong - Ben Cat - Rach Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, is causing outrage because of prolonged and delayed construction.

On October 31, along the Tham Luong - Ben Cat canal through Go Vap district, the construction of the concrete embankment was basically completed.

However, both sides of the canal were surrounded by mud, many sections became muddy, making it difficult to move.

Doan kenh qua quan Go Vap da duoc thi cong ke be tong. Anh: Minh Quan
The canal section through Go Vap district (HCMC) has been constructed with concrete embankments. Photo: Minh Quan
Hai ben bo kenh bun dat ngon ngang, khong co cong nhan thi cong. Anh: Minh Quan
Both sides of the canal are covered in mud. Photo: Minh Quan

Some drainage sections are unfinished and not fully installed, causing mud to accumulate. The construction site is deserted with very little construction activity, creating a desolate landscape.

Mr. Mai Van Hieu, a local resident, said: “They dug up the soil along the canal bank, drove in concrete piles, and left a ditch between the road and the canal for months. The road surface is littered with rocks and soil, some areas have sunk and water has accumulated without warning signs. This is extremely dangerous, especially for children. When it is sunny, dust flies everywhere, and when it rains, the road becomes muddy and extremely difficult to travel.”

Duong ven kenh lay loi, ngap nuoc.  Anh: Minh Quan
The road along the canal is muddy and flooded. Photo: Minh Quan

Tan Tao A Ward, Binh Tan District, is in the same situation. The road along the canal bank is being used as a place to store construction materials, and the excavated soil and rocks are piled up, causing muddy flooding, especially after heavy rains. This situation has lasted for many months, disrupting the lives of residents here.

Many businesses along the canal banks are also facing difficulties. Mr. Tran Tan Binh, a shop owner in Tan Tao A ward, shared: “We are very supportive of the project because it will help improve the living environment. However, the prolonged construction and muddy roads have greatly affected my business. I hope the project will be completed soon so that business can return to normal.”

Rao chan so sai, tiem an nguy hiem.  Anh: Minh Quan
Rough, potentially dangerous fence. Photo: Minh Quan
Nhieu vat lieu xay dung de ngon ngang ben duong.  Anh: Minh Quan
Many construction materials are left scattered on the roadside. Photo: Minh Quan

According to the Management Board of Ho Chi Minh City Urban Infrastructure Construction Investment Project (investor), the Tham Luong - Ben Cat - Rach Nuoc Len canal renovation project has only reached 37.9% of the progress after nearly two years of implementation.

The previous project identified locations such as Sub-area 3 in Binh Tri Dong B Ward (Binh Tan District), Go Vap Cultural Park (Go Vap District) and Solid Waste Treatment Complex in Da Phuoc Commune (Binh Chanh District) as dumping sites for generated soil and sludge.

However, due to the lack of consensus from local residents and management agencies, mud and soil must now be temporarily gathered at the construction site, causing problems with the construction site and hindering acceptance and disbursement.

The Project Management Board said that the mud generated from the construction is not hazardous waste and can be used for public projects in Ho Chi Minh City to avoid waste. If localities do not have a need to use it, the unit will propose to transfer it to other areas with needs, such as District 12, after completing the required procedures.

Dat da chat thanh dong doc 2 ben bo kenh.  Anh: Minh Quan
Rocks and soil piled up along both sides of the canal. Photo: Minh Quan

The project also encountered difficulties in the supply of materials such as sand and stone, along with input material prices increasing higher than the bid price. This caused financial difficulties for the contractor, affecting the construction progress.

Unstable weather, heavy rain combined with high tides also disrupted construction and slowed down project progress.

Tham Luong - Ben Cat - Rach Nuoc Len Canal is nearly 32 km long, Vietnamese sausagey through 7 districts of Ho Chi Minh City.

The renovation project worth VND8,200 billion, started in February 2023 and is expected to be completed on April 30, 2025.

The project includes concrete embankment, dredging, 7-12m canal roads, drainage system, lighting, trees, 19 culverts, 12 boat docks and 3 connecting bridges.

In 2024, the project was assigned 3,400 billion VND, but it is expected that only 1,028 billion VND (30.23%) will be disbursed.

MINH QUÂN
TIN LIÊN QUAN

Renovation of the longest canal in Ho Chi Minh City faces obstacles, risk of delay

|

The Tham Luong - Ben Cat - Rach Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, has only completed 37.9% of its volume after nearly two years of implementation.

Tien Linh left the field on a stretcher after scoring 2 goals for Binh Duong

|

Striker Nguyen Tien Linh was injured and had to leave the field on a stretcher during the match between Binh Duong and Hoang Anh Gia Lai.

Kuzeyboru easily beat Sigorta Shop on the day Thanh Thuy did not compete

|

Kuzeyboru team won Sigorta Shop 4-1 in the 2024-2025 Turkish Volleyball National Championship.

Heavy rain and cold weather in the North next week

|

The Meteorological Agency forecasts that on November 4, there will be heavy rain in some areas in the North and severe cold in some mountainous areas.

Prime Minister hands over decision to appoint VTV General Director

|

The Prime Minister congratulated and affirmed that Mr. Nguyen Thanh Lam's appointment as VTV General Director was appropriate in the current context.

Unit accepting to dismantle Son Hai Group's signs

|

Thanh Hoa - Regarding the incident in which Son Hai Group denounced the destruction of highway signs, the road management unit has spoken out about the incident.

Hoang Anh Gia Lai lost their first match in V.League 2024-2025

|

On the evening of November 2, Hoang Anh Gia Lai club suffered a 1-4 defeat against Binh Duong in round 6 of LPBank V.League 2024-2025.

Renovation of the longest canal in Ho Chi Minh City faces obstacles, risk of delay

MINH QUÂN |

The Tham Luong - Ben Cat - Rach Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, has only completed 37.9% of its volume after nearly two years of implementation.

Dự án cải tạo kênh dài nhất TPHCM cần thêm gần 1.600 tỉ đồng

MINH QUÂN |

Dự án cải tạo kênh Tham Lương - Bến Cát - rạch Nước Lên dài nhất TPHCM cần bổ sung gần 1.600 tỉ đồng cho giải phóng mặt bằng, xây thêm cầu, công viên...

Tuyến kênh dài nhất TPHCM đã lộ hình hài sau hơn 1 năm khởi công cải tạo

Anh Tú |

TPHCM - Sau hơn một năm kể từ ngày khởi công, dự án cải tạo kênh Tham Lương – Bến Cát – rạch Nước Lên (đi qua địa bàn 7 quận, huyện của thành phố là Quận 12, Bình Tân, Tân Phú, Tân Bình, Gò Vấp, Bình Thạnh và huyện Bình Chánh) đã đạt hơn 37% khối lượng. Hiện tiến độ thi công đang được đẩy nhanh để hoàn thành vào dịp 30.4.2025.