Thuy Phuong canal renovation project accelerates to finish before the 2026 rainy and flood season

Minh Hạnh |

Hanoi is accelerating the progress of the Thuy Phuong canal renovation project, contributing to improving drainage capacity and reducing flooding for the Northwest region.

According to the direction of the City Party Committee and Hanoi People's Committee, urgent flood control projects in the area must be completed before June 30 to strengthen drainage capacity before the rainy and storm season.

In recent years, heavy rain and extreme rain have appeared with increasing frequency, putting great pressure on the urban infrastructure system. For example, the historic rain in September 2025 caused many central streets of Hanoi to be deeply flooded, traffic paralyzed, seriously affecting people's lives.

Dự án cải tạo kênh Thụy Phương tăng tốc về đích trước mùa mưa bão. Ảnh: Minh Hạnh
Thuy Phuong canal renovation project accelerates to reach the finish line before the rainy and storm season. Photo: Minh Hanh

According to the assessment of functional agencies, rapid urbanization while the drainage system and regulating lakes have not been synchronously invested is the main reason leading to flooding in many areas.

Hà Nội chạy đua hoàn thành kênh Thụy Phương trước ngày 30.6. Ảnh: Minh Hạnh
Hanoi races to complete Thuy Phuong canal before June 30. Photo: Minh Hanh

Faced with this reality, Hanoi City identifies flood control as an urgent task. Hanoi Technical Infrastructure Management Center is assigned to implement key projects, requiring accelerating construction progress to soon promote efficiency.

Dự án chống ngập trọng điểm ở Hà Nội cán mốc 95% khối lượng. Ảnh: Minh Hạnh
Key flood control project in Hanoi reaches 95% volume. Photo: Minh Hanh

On June 16, recorded at the construction site of the Thuy Phuong canal renovation project, the section from Hoang Minh Thao street to Thuy Phuong street, construction units are mobilizing maximum manpower and machinery to complete the project according to the plan, contributing to reducing drainage pressure for the Northwest area of the city during the rainy and storm season.

Mr. Nguyen Huy Hai - Deputy Head of the Water Supply and Drainage Project Management Department (Hanoi Technical and Agricultural Infrastructure Construction Investment Project Management Board) - said that to ensure progress, the contractor consortium has simultaneously deployed 25 construction teams with more than 300 officials and workers working 3 shifts, 4 crews continuously.

Tuyến cống ngầm trên đường Hoàng Minh Thảo. Ảnh: Minh Hạnh
Underground sewer line on Hoang Minh Thao street. Photo: Minh Hanh

As of June 15, the volume of main items of the project has reached about 95%. In which, the canal route from Thuy Phuong to Pham Van Dong has completed 100% of some items. The box culvert item, more than 1.4km long, has reached about 98% of the construction volume.

Although it is in the final sprint stage, the project implementation process still faces many difficulties. Construction units must handle complex geological foundations, and at the same time relocate underground technical infrastructure systems with high density. In addition, the shortage of supply and fluctuations in construction material prices also put great pressure on contractors.

Weather factors also significantly affect project progress. In May alone, the area recorded 10 heavy rains, causing construction activities to be interrupted many times.

In particular, the heavy rain in early May flooded the entire foundation pit of the pumping station, causing equipment damage and forcing the construction unit to spend nearly a week to overcome the consequences.

Dự án chống ngập trọng điểm ở Hà Nội cán mốc 95% khối lượng. Ảnh: Minh Hạnh
Key flood control project in Hanoi reaches 95% volume. Photo: Minh Hanh

The Thuy Phuong canal renovation project has a total length of about 7.6km, including open canals and underground culverts running along key roads such as Vo Chi Cong, Hoang Minh Thao. When completed and put into operation, the project will not only improve drainage capacity for large urban areas such as Resco, Ecohome, Ciputra but also contribute to replenishing water sources and improving the environment for the To Lich River.

Representatives of the Project Management Board said that from now until June 30, all human resources will be maximally focused to complete the remaining items, ensuring the project reaches the finish line on schedule as required by Hanoi City.

Minh Hạnh
RELATED NEWS

10,000 billion VND flood control project cannot be forever flooded in procedures

|

The 10,000 billion VND tide prevention project of Ho Chi Minh City is facing the risk of not being completed in 2026 due to a series of legal procedures that have not been resolved.

West Hanoi flood control regulating lakes race ahead with the rainy season

|

Hanoi - Reservoir projects are being accelerated, reaching about 90% of the construction volume, improving flood prevention capacity before the rainy and storm season.

Note the alternative route when La Thanh road is barricaded

|

Hanoi adjusts traffic organization on La Thanh road, Nguyen Chi Thanh - Thanh Cong section, guiding people to follow the new Ring Road 1.

Ministry of Public Security proposes responsibility for verifying food sellers on social networks

|

The Ministry of Public Security proposed to stipulate the responsibilities of e-commerce platforms and social networks in verifying the identity of food sellers.

Hanoi residents gradually switch to green vehicles with new support policies

|

Hanoi - Hanoi residents are starting to switch to green vehicles after a new support policy, contributing to reducing emissions and protecting the urban environment.

Ready to provide direct legal advice to thousands of workers and laborers

|

Many problems will be answered at the Legal Consulting Program organized by Lao Dong Newspaper, Vietnam Bar Federation and Ho Chi Minh City Labor Federation on June 21.

10,000 billion VND flood control project cannot be forever flooded in procedures

Lê Thanh Phong |

The 10,000 billion VND tide prevention project of Ho Chi Minh City is facing the risk of not being completed in 2026 due to a series of legal procedures that have not been resolved.

West Hanoi flood control regulating lakes race ahead with the rainy season

Minh Hạnh |

Hanoi - Reservoir projects are being accelerated, reaching about 90% of the construction volume, improving flood prevention capacity before the rainy and storm season.

Gấp rút hoàn trả mặt bằng đường Võ Chí Công sau khi lắp cống chống ngập

Minh Hạnh |

Hà Nội - Sau khi hoàn thành thông dòng tuyến cống hộp chống ngập trên đường Võ Chí Công, đơn vị thi công đang khẩn trương hoàn trả mặt bằng.

Kênh Thụy Phương tăng tốc thi công, quyết hoàn thành trước mùa mưa

Minh Hạnh |

Hà Nội - Dự án cải tạo kênh Thụy Phương đạt trên 70% tiến độ, đang tăng tốc thi công 3 ca 4 kíp, quyết hoàn thành trước mùa mưa 2026.