10,000 billion VND flood control project cannot be forever flooded in procedures

Lê Thanh Phong |

The 10,000 billion VND tide prevention project of Ho Chi Minh City is facing the risk of not being completed in 2026 due to a series of legal procedures that have not been resolved.

The project is expected to be a "steel shield" to protect the city from increasingly serious flooding.

However, after nearly a decade of implementation, the project has not yet been able to reach the finish line and now faces the risk of continuing to be missed due to procedural bottlenecks that have not been removed.

It is worth mentioning that this is not a newly started project or still has problems in site clearance. The project has completed more than 90% of the volume, and many main items have taken shape.

However, just because the procedures related to BT contract payments have not been completed, capital flow is blocked, and the project has to struggle to be prolonged year after year.

Meanwhile, every day of delay has to pay the price in real money. The incurred loan interest has reached about 2,500 billion VND and continues to increase.

Social resources are being eroded not by natural disasters, not by lack of construction capacity, but by prolonged administrative procedures.

Resolution 212 of the Government was issued in July 2025 to remove difficulties for the project. The handling mechanism has also been clearly identified, from adjusting the feasibility study report to the payment plan using land funds or public investment capital.

However, the actual implementation has not yet achieved the expected speed.

People have the right to ask, if the mechanism is there, the policy is clear, so why can't the project still be completed?

Every rainy season comes, a series of roads are deeply flooded, traffic is chaotic, production and business activities are affected, and people's lives are disrupted.

Damage from flooding is not only calculated in money but also in time, development opportunities and quality of life.

Therefore, each year of delaying putting the project into operation is an additional year for people to live with flooding and constant worries every time it rains.

Ho Chi Minh City is entering a new stage of development with the aspiration to become a modern megacity, the leading economic center in the region.

What is needed at this time is the more drastic action of functional agencies in implementing the mechanisms allowed by the Government, urgently completing the remaining dossiers to release capital and bring the project to completion.

If the 10,000 billion VND flood control project continues to be delayed, what will be lost is not only trillions of VND of arising loan interest, but also an opportunity to improve the quality of life for people and the adaptability of Ho Chi Minh City to the increasing challenges of climate change.

A dynamic city cannot let flood control projects forever be "submerged" in procedures.

Lê Thanh Phong
RELATED NEWS

10,000 billion VND tide prevention project in Ho Chi Minh City at risk of delay due to procedural issues

|

Ho Chi Minh City - The nearly 10,000 billion VND tide prevention project is facing the risk of not being completed in 2026 due to a series of legal procedures that have not been resolved.

Saigon Hot News: Progress of 10,000 billion VND tide prevention project helps reduce flooding for Ho Chi Minh City

|

Saigon Hot News on May 8th: Deputy Minister of Health visits a boy in the abuse case in Ho Chi Minh City; Progress of the 10,000 billion VND tide prevention project to help reduce flooding for Ho Chi Minh City...

10,000 billion VND tide control sluice project needs a solid commitment

|

Ho Chi Minh City restarts the 10,000 billion VND tide control culvert project after a period of interruption, and puts the Ben Nghe tide control culvert into operation.

People rescue goods to help drivers reduce damage after collision

|

Lam Dong - Many people in Lien Huong commune have joined hands to collect and buy goods to help drivers reduce damage after collisions.

Removing obstacles in the migration out of Hue Citadel

|

HUE - The project to relocate people out of Hue Citadel is being removed from land difficulties, as many households have not yet moved because of many reasons.

Waste treatment plant stops operating, wards in Da Lat flooded with domestic waste

|

Lam Dong - After 3 days of collection interruption due to the treatment plant stopping operation, waste in the center of Da Lat is congested, smelly, causing serious pollution.

10,000 billion VND tide prevention project in Ho Chi Minh City at risk of delay due to procedural issues

MINH QUÂN |

Ho Chi Minh City - The nearly 10,000 billion VND tide prevention project is facing the risk of not being completed in 2026 due to a series of legal procedures that have not been resolved.

Saigon Hot News: Progress of 10,000 billion VND tide prevention project helps reduce flooding for Ho Chi Minh City

Thanh Chân - Anh Tú |

Saigon Hot News on May 8th: Deputy Minister of Health visits a boy in the abuse case in Ho Chi Minh City; Progress of the 10,000 billion VND tide prevention project to help reduce flooding for Ho Chi Minh City...

10,000 billion VND tide control sluice project needs a solid commitment

Lê Thanh Phong |

Ho Chi Minh City restarts the 10,000 billion VND tide control culvert project after a period of interruption, and puts the Ben Nghe tide control culvert into operation.