The most polluted canal renovation project in Ho Chi Minh City is still facing land issues for more than 1,000 households

MINH QUÂN |

Ho Chi Minh City - The project to renovate Xuyen Tam canal - the most polluted canal in the city - is still facing site clearance issues for more than 1,000 households, significantly affecting the construction progress.

Rach Xuyen Tam has a length of nearly 9 km, connecting from Nhieu Loc - Thi Nghe canal to Vam Thuat river, passing through An Nhon, Gia Dinh, Binh Thanh and Binh Loi Trung wards. Of which, the main route is 6.7 km long, and the rest are three auxiliary branches with a total length of about 2.2 km.

This canal renovation project has a total investment of more than 17,000 billion VND, of which compensation, support and resettlement costs account for about 14,000 billion VND.

Currently, the project is being implemented with 3 main construction packages. In which, package XL-03 (section from Luong Ngoc Quyen street to Vam Thuat river) was started in May 2025 and is being accelerated by contractors. Units have mobilized sufficient machinery, equipment, and manpower, deploying 6 construction teams simultaneously.

Gói thầu XL-03 đang được đẩy nhanh xây bờ kè.  Ảnh: Anh Tú
Package XL-03 is being accelerated to build embankments. Photo: Anh Tu

The remaining two bidding packages are XL-01 (from Nhieu Loc - Thi Nghe canal to Bui Dinh Tuy bridge, including Cau Son canal) and XL-02 (from Bui Dinh Tuy bridge to Luong Ngoc Quyen street, including Binh Loi and Binh Trieu canals) which were started in December 2025, but are facing many difficulties due to site clearance issues.

Gói thầu XL-01 vướng mặt bằng nhiều nhất.  Ảnh: Anh Tú
Package XL-01 has the most site clearance problems. Photo: Anh Tu

On May 5, the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board (the investor) said that so far Binh Thanh and Gia Dinh wards have only handed over 861/2,046 affected cases, reaching about 42.08%.

In which, package XL-02 has received handover of 261/572 cases (reaching 45.6%) and is organizing construction at 8 fronts.

Package XL-01 is the most difficult area when most of the site has not been handed over or is only small-scale handover, not continuous. To date, only 600/1,474 cases have been handed over, reaching 40.7%.

Một số căn nhà đã tháo dỡ để cải tạo rạch Xuyên Tâm.  Ảnh: Anh Tú
Some houses have been dismantled to renovate Xuyen Tam canal. Photo: Anh Tu

However, the investor still proactively deploys construction in areas with site clearance. The first test pile of package XL-01 has been carried out in the area 181 - 197 Dien Bien Phu. At the same time, in the My Phuoc apartment complex area, units have coordinated with local authorities to build service roads across canals to add more construction fronts, taking advantage of the waiting time for site clearance.

Faced with existing problems, the investor proposed that localities accelerate the progress of compensation and site handover in May 2026 so that contractors can deploy simultaneously.

In case it is not possible to hand over the entire project, it is proposed to allow the receipt of each part to organize rolling construction, avoiding wasting time and resources.

According to the plan, if the full site is handed over, package XL-03 can be completed in November 2026. The remaining two packages are expected to be completed in 2028.

Tình trạng bàn giao mặt bằng không liền mạch đang ảnh hưởng đến tiến độ thi công dự án cải tạo rạch Xuyên Tâm. Ảnh: Anh Tú
The situation of non-continuous site handover is affecting the construction progress of the Xuyen Tam canal renovation project. Photo: Anh Tu

Previously, in March 2026, Mr. Nguyen Van Duoc - Member of the Party Central Committee, Deputy Secretary of the City Party Committee, Chairman of the Ho Chi Minh City People's Committee directly inspected the project and requested localities to complete the handover of land no later than the end of June 2026. During this time, local authorities must strengthen the mobilization of people to receive compensation, arrange resettlement or temporary residence.

For cases where money has been received but land has not been handed over, the city requests resolute enforcement according to regulations. Ward leaders will be responsible to the Ho Chi Minh City People's Committee if the handover work is not completed on time.

MINH QUÂN
RELATED NEWS

Ho Chi Minh City spends nearly 3,000 billion VND to revive 2 polluted canals

|

Ho Chi Minh City invests nearly 3,000 billion VND to renovate Ong Bau and Chin Xieng canals in the period 2026 - 2029, to reduce flooding, treat pollution and embellish the urban area.

Relocating houses along canals, accelerating urban embellishment in Ho Chi Minh City

|

Ho Chi Minh City is focusing efforts to remove bottlenecks in site clearance at key canal and ditch renovation projects such as Xuyen Tam canal and Doi canal. When this bottleneck is cleared, the goal of relocating 20,000 houses along the canal and accelerating urban embellishment can be achieved by 2030.

Ho Chi Minh City misses the land handover deadline for the Xuyen Tam canal renovation project

|

Ho Chi Minh City cannot hand over the entire site of the Xuyen Tam canal renovation project in November 2025 according to the direction of Ho Chi Minh City Party Secretary Tran Luu Quang.

U17 Indonesia surprises U17 China at Asian tournament

|

U17 Indonesia had an impressive start at the 2026 AFC U17 Championship finals when they defeated U17 China with a score of 1-0 in the opening match of Group B.

Handling a series of offensive characters and writing on Dong Hoi Citadel and Quang Binh Quan relics

|

Quang Tri - After the reflection of Lao Dong Newspaper, functional forces have conducted inspections and handled the drawings and handwriting on Dong Hoi Citadel and Quang Binh Quan.

Arsenal enters Champions League final

|

In the early morning of May 6 (Vietnam time), Arsenal surpassed Atletico Madrid to reach the Champions League final in the 2025-2026 season.

Prime Minister requests consolidation of key personnel at ACV before May 7

|

The Prime Minister requested the Ministry of Finance to urgently approve the policy on consolidating key personnel at Vietnam Airports Corporation (ACV).

Russia declares destruction of Ukraine's Damba electronic warfare station

|

Forces of the Northern Task Force of Russia destroyed a Damba electronic warfare station of Ukraine in the Sumy region, Ukraine.

Ho Chi Minh City spends nearly 3,000 billion VND to revive 2 polluted canals

MINH QUÂN |

Ho Chi Minh City invests nearly 3,000 billion VND to renovate Ong Bau and Chin Xieng canals in the period 2026 - 2029, to reduce flooding, treat pollution and embellish the urban area.

Relocating houses along canals, accelerating urban embellishment in Ho Chi Minh City

MINH QUÂN |

Ho Chi Minh City is focusing efforts to remove bottlenecks in site clearance at key canal and ditch renovation projects such as Xuyen Tam canal and Doi canal. When this bottleneck is cleared, the goal of relocating 20,000 houses along the canal and accelerating urban embellishment can be achieved by 2030.

Ho Chi Minh City misses the land handover deadline for the Xuyen Tam canal renovation project

MINH QUÂN |

Ho Chi Minh City cannot hand over the entire site of the Xuyen Tam canal renovation project in November 2025 according to the direction of Ho Chi Minh City Party Secretary Tran Luu Quang.