The Nhat Le 3 bridge project encountered difficulties because of the site

CÔNG SÁNG |

Quang Binh province is facing difficulties in project component 2 - Nhat Le 3 bridge and roads at both ends of the bridge during site clearance.

Construction volume reached about 55%

On August 19, the People's Committee of Quang Binh province said that it had just issued drastic instructions to promptly hand over the site in December 2024 of component project 2 - Nhat Le 3 bridge and roads at both ends of the bridge.

The project is designed to span Nhat Le River. The starting point of the route intersects with National Highway 1A in Luong Ninh commune (Quang Ninh district), the ending point of the route intersects with Vo Nguyen Giap street (in Bao Ninh commune, Dong Hoi city).

Construction of the bridge's lower part has now been completed, pouring concrete at the steel arch base; installation of bridge beams of span M1-T1; T8-T9 and T9-M2, are installing steel arches, casting bridge girders and the next items. Construction volume reaches about 55% of contract value.

The new project is constructing traffic route No. 1 with an area of ​​about 0.25/3.24 hectares. Currently, the site clearance work is facing many problems, so the construction progress of the resettlement area is very slow.

Currently, the project has not yet completed site clearance work. Photo: V. Hoang
Currently, the project has not yet completed site clearance work. Photo: V. Hoang

However, up to now, the site clearance work has not been completed. The main reason is related to the compensation unit price, land disputes between households, relocation of graves... in the eastern bridgehead area (Bao Ninh commune).

Focus on site clearance

To solve the above problems in site clearance and promptly hand over the site to the investor to speed up the construction progress, Mr. Phan Phong Phu - Vice Chairman of the Provincial People's Committee, Head of the Steering Committee for Implementation Project implementation - there have been instructions for units and localities to urgently focus on implementation.

Accordingly, for site clearance work in Bao Ninh commune, the Project Management Board continues to coordinate with the People's Committee of Bao Ninh commune in mobilizing households to comply with the State's legal guidelines and policies. in compensation and site clearance work. Coordinate to remove difficulties and obstacles in the process of determining land origin to complete site clearance in December 2024.

At the same time, Dong Hoi City People's Committee also directed the Department of Natural Resources and Environment to speed up land valuation procedures according to new regulations, completed in August 2024. Bao Ninh Commune People's Committee actively coordinates with the Investor and related units in determining the origin of land; Organize to mobilize households to agree with the land recovery policy.

For resettlement work, the Project Management Board coordinates closely with Dong Hoi City People's Committee and Bao Ninh Commune People's Committee to speed up implementation progress in compensation and site clearance stages; Priority is given to clearing land plots along traffic route No. 1 to allocate land for 18 households subject to resettlement in December 2024.

Dong Hoi City People's Committee directed the Department of Natural Resources and Environment and Bao Ninh Commune People's Committee to soon complete the case of Mr. Pham Thanh Dong's household encroaching on production forest land of the Dong Hoi and Coastal Protection Forest Management Board of Quang Binh province. in August 2024.

The Nhat Le 3 bridge project and the road at both ends of the bridge will start construction in early 2023 with a total investment of 1,300 billion VND. The road at both ends of the bridge is designed according to the urban main road level, with a design speed of 60 km/h, roadbed width from 23.5m to 54.5m, including 4 lanes. Project implementation period is until 2026. Project capital comes from the Central Government.

The project promises to create an important highlight in the picture of transport infrastructure and socio-economic development of Quang Binh province.

CÔNG SÁNG
TIN LIÊN QUAN

Khởi động dự án cao tốc 113km, vốn 56.300 tỉ đồng

HỮU CHÁNH |

Hà Nội đang hoàn chỉnh hồ sơ mời thầu dự án thành phần cao tốc Vành đai 4, dự kiến phát hành hồ sơ mời thầu trong tháng 8.2024.

Tìm phương án giải phóng mặt bằng đường ven biển Quảng Bình

CÔNG SÁNG |

Tỉnh Quảng Bình yêu cầu các địa phương khẩn trương thực hiện các biện pháp nhằm giải quyết triệt để giải phóng mặt bằng đường ven biển.

Thủ tướng Chính phủ khảo sát dự án đường ven biển và cầu Nhật Lệ 3 tại Quảng Bình

CÔNG SÁNG |

Chiều 2.6, Thủ tướng Chính phủ Phạm Minh Chính đã đi khảo sát dự án đường ven biển và cầu Nhật Lệ 3 (TP Đồng Hới, tỉnh Quảng Bình).

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Du khách quốc tế bất ngờ với phố Halloween giữa lòng Thủ đô

HOÀNG LỘC - NGỌC LINH |

Hà Nội - Nhiều du khách quốc tế không khỏi bất ngờ, thích thú khi đến khu phố Hàng Mã (Hoàn Kiếm) hiện đang ngập tràn các mặt hàng Halloween.

Trang trại nuôi vịt xả thải gây ô nhiễm vẫn dây dưa tái phạm

An Long |

Long An - Dù đã bị nhắc nhở và xử phạt nhiều lần nhưng chủ trang trại vẫn liên tiếp tái đàn, xả thải gây ô nhiễm môi trường.

Nút giao 4 tầng sắp xây trên đại lộ Phạm Văn Đồng ở Thủ Đức

MINH QUÂN |

TPHCM - Nút giao Phạm Văn Đồng với Vành đai 2 tại TP Thủ Đức sẽ được thiết kế 4 tầng, bao gồm một hầm chui và ba cầu vượt.

INEOS đúng hay sai khi cắt hợp đồng đại sứ của Sir Alex Ferguson?

VIỆT HÙNG |

Nhìn về góc độ kinh tế, Sir Jim Ratcliffe đã đúng nhưng về mặt thương hiệu câu lạc bộ, có thể ông đã tính sai khi chấm dứt hợp đồng đại sứ thương hiệu của Sir Alex Ferguson.

Launching the 113km expressway project, capital of 56,300 billion VND

HỮU CHÁNH |

Hanoi is completing bidding documents for the Ring Road 4 expressway component project , expected to release bidding documents in August 2024.

Find a plan to clear land on Quang Binh coastal road

CÔNG SÁNG |

Quang Binh province requires localities to urgently implement measures to thoroughly resolve coastal road clearance .