Land clearance nearly 90%
Component project 1 - Coastal road in Quang Binh province has a total investment of 2,197 billion VND, passing through 16 communes and wards of 6 districts, towns and cities; affecting 1,083 households, organizations and 21 aquaculture farms.
Although construction started at the end of January 2022, up to now there are still problems with the site . Currently, the Project is simultaneously constructing 7/7 bidding packages of the Project with the area of land continuously handed over for construction being 70.2/80km, reaching a rate of 87.8%; Basic items of bridges and culverts, drainage works, roadbeds, and road foundations are under construction. Some districts have slow site clearance rates such as Dong Hoi City reaching 66.3%, Le Thuy district reaching 81.93%, Quang Trach district reaching 87.8%; The remaining localities all reached a rate of 95 - 97%.
On August 19, the People's Committee of Quang Binh province said that Mr. Phan Phong Phu - Vice Chairman of the People's Committee of Quang Binh province has just issued a document directing the implementation and implementation of the proposed progress and quality; Capital disbursement is also guaranteed by investors.
“However, the biggest obstacle is site clearance , specifically site clearance for aquaculture farms, mausoleums, people's houses and properties, and construction of resettlement areas for relocation. people" - Mr. Phu said.
Vice Chairman of Quang Provincial People's Committee has proposed contents that need to be urgently focused on implementation. For affected aquaculture farms, the Department of Agriculture and Rural Development and the Department of Finance will assess the continuity of aquaculture farm assets within and outside the site clearance scope; The Appraisal Council on the valuation of aquaculture materials, machinery and equipment not included in the compensation price list of the Provincial People's Committee shall chair a Council meeting before August 26 to synthesize and advise the Provincial People's Committee according to assigned tasks.
To have a basis for the two Provincial Councils mentioned above to meet, the People's Committees of districts, towns and cities direct the District Council to meet and send the results to the Department of Agriculture and Rural Development for synthesis.
In case of difficulties or problems, send a document to the Department of Transport to summarize and report to the Steering Committee and Provincial People's Committee for solutions.
Accelerate the progress of resettlement areas
Regarding the issue of resettlement, the Provincial Vice Chairman requested the People's Committee of Le Thuy district to direct the District Land Fund Development and Construction Investment Project Management Board to speed up the implementation of 2 resettlement areas in Ngu Thuy Bac commune. completed before August 30 and in Ngu Thuy commune completed before October 31.
Bo Trach District People's Committee urgently approves the detailed planning of Dong Trach commune resettlement area and implements further procedures, ensuring construction before October 31. Quang Trach District People's Committee directed to speed up construction progress, ensuring completion of the resettlement area before September 30.
With other problems, Le Thuy district urgently reviewed and specifically calculated the cost of compensation for site clearance in the area and sent it to the Department of Transport for synthesis and reporting to the Provincial People's Committee; Direct the People's Committee of Ngu Thuy commune to resolve land disputes between 6 households according to its authority, completed before August 20.
Quang Ninh district continues to direct propaganda work to get households to agree to receive compensation and hand over the land. Quang Trach district directs the completion of the plan to publicize and carry out procedures to approve the compensation plan for the section passing through Xuan Hoa Parish, Quang Xuan commune before August 20.
Resolving problems to promptly hand over the site to the investor will speed up construction progress and ensure disbursement of the capital plan arranged in 2024, especially disbursement of all 100% of the capital plan. central budget before October 31.