Find a plan to clear land on Quang Binh coastal road

CÔNG SÁNG |

Quang Binh province requires localities to urgently implement measures to thoroughly resolve coastal road clearance .

Land clearance nearly 90%

Component project 1 - Coastal road in Quang Binh province has a total investment of 2,197 billion VND, passing through 16 communes and wards of 6 districts, towns and cities; affecting 1,083 households, organizations and 21 aquaculture farms.

Although construction started at the end of January 2022, up to now there are still problems with the site . Currently, the Project is simultaneously constructing 7/7 bidding packages of the Project with the area of ​​land continuously handed over for construction being 70.2/80km, reaching a rate of 87.8%; Basic items of bridges and culverts, drainage works, roadbeds, and road foundations are under construction. Some districts have slow site clearance rates such as Dong Hoi City reaching 66.3%, Le Thuy district reaching 81.93%, Quang Trach district reaching 87.8%; The remaining localities all reached a rate of 95 - 97%.

On August 19, the People's Committee of Quang Binh province said that Mr. Phan Phong Phu - Vice Chairman of the People's Committee of Quang Binh province has just issued a document directing the implementation and implementation of the proposed progress and quality; Capital disbursement is also guaranteed by investors.

Many road sections have been implemented. Photo: Cong Sang
Many road sections have been implemented. Photo: Cong Sang

“However, the biggest obstacle is site clearance , specifically site clearance for aquaculture farms, mausoleums, people's houses and properties, and construction of resettlement areas for relocation. people" - Mr. Phu said.

Vice Chairman of Quang Provincial People's Committee has proposed contents that need to be urgently focused on implementation. For affected aquaculture farms, the Department of Agriculture and Rural Development and the Department of Finance will assess the continuity of aquaculture farm assets within and outside the site clearance scope; The Appraisal Council on the valuation of aquaculture materials, machinery and equipment not included in the compensation price list of the Provincial People's Committee shall chair a Council meeting before August 26 to synthesize and advise the Provincial People's Committee according to assigned tasks.

To have a basis for the two Provincial Councils mentioned above to meet, the People's Committees of districts, towns and cities direct the District Council to meet and send the results to the Department of Agriculture and Rural Development for synthesis.

In case of difficulties or problems, send a document to the Department of Transport to summarize and report to the Steering Committee and Provincial People's Committee for solutions.

Accelerate the progress of resettlement areas

Regarding the issue of resettlement, the Provincial Vice Chairman requested the People's Committee of Le Thuy district to direct the District Land Fund Development and Construction Investment Project Management Board to speed up the implementation of 2 resettlement areas in Ngu Thuy Bac commune. completed before August 30 and in Ngu Thuy commune completed before October 31.

Bo Trach District People's Committee urgently approves the detailed planning of Dong Trach commune resettlement area and implements further procedures, ensuring construction before October 31. Quang Trach District People's Committee directed to speed up construction progress, ensuring completion of the resettlement area before September 30.

With other problems, Le Thuy district urgently reviewed and specifically calculated the cost of compensation for site clearance in the area and sent it to the Department of Transport for synthesis and reporting to the Provincial People's Committee; Direct the People's Committee of Ngu Thuy commune to resolve land disputes between 6 households according to its authority, completed before August 20.

Some aquaculture farms on the Quang Binh coastal road are facing problems. Photo: Cong Sang
Some aquaculture farms on the Quang Binh coastal road are facing problems. Photo: Cong Sang

Quang Ninh district continues to direct propaganda work to get households to agree to receive compensation and hand over the land. Quang Trach district directs the completion of the plan to publicize and carry out procedures to approve the compensation plan for the section passing through Xuan Hoa Parish, Quang Xuan commune before August 20.

Resolving problems to promptly hand over the site to the investor will speed up construction progress and ensure disbursement of the capital plan arranged in 2024, especially disbursement of all 100% of the capital plan. central budget before October 31.

CÔNG SÁNG
TIN LIÊN QUAN

Giải phóng mặt bằng cao tốc Vạn Ninh – Cam Lộ còn hơn 700m, bao giờ xong?

HƯNG THƠ |

Chiều dài còn lại chưa được giải phóng mặt bằng ở cao tốc Vạn Ninh – Cam Lộ ở Quảng Trị là 723m, địa phương quyết tâm bàn giao trước ngày 20.7.2024.

Mất 8 năm giải phóng mặt bằng vành đai 1.800 tỉ đồng ở Hà Nội

HỮU CHÁNH |

Hà Nội - Đến tháng 2.2025, 6.000m2 mặt bằng còn lại sẽ được bàn giao để thi công hoàn thiện dự án Vành đai 3,5 (đoạn qua Hoài Đức) sau nhiều năm chậm trễ.

Những điểm nghẽn tại tuyến đường ven biển ở Quảng Bình

CÔNG SÁNG |

Tuyến đường ven biểnQuảng Bình triển khai từ đầu năm 2022, nhưng đến nay vẫn còn những điểm nghẽn, đặc biệt là việc giải phóng mặt bằng.

Giá cả ở Việt Nam chênh lệch thế nào trong mắt khách Tây?

Nguyễn Đạt |

Tính toán chi phí du lịch Việt Nam, khách Tây bất ngờ vì đồ ăn nhanh, cà phê khá đắt so với quê nhà, còn dịch vụ làm đẹp quá rẻ.

Dân vùng táo muối đặc sản Hải Phòng nỗ lực cứu vụ Tết

Hoàng Khôi |

Người dân vùng trồng táo muối đặc sản Hải Phòng tiếc nuối, xót xa khi hàng trăm ha táo tươi tốt, đang độ ra hoa để cho thu hoạch vụ Tết bỗng tả tơi, thiệt hại do bão.

Cầu Long Thành hoàn thành sửa chữa vượt tiến độ

MINH QUÂN |

Công tác sửa chữa khe co giãn tại cầu Long Thành trên tuyến cao tốc TPHCM - Long Thành - Dầu Giây đã hoàn thành trước kế hoạch 4 ngày.

Bão áp sát, một trường ở Quảng Bình vẫn thi sát hạch lái xe

CÔNG SÁNG |

Mặc dù bão số 4 đã áp sát đất liền, nhưng Trường Trung cấp nghề Bình Minh Quảng Bình vẫn tổ chức thi sát hạch lái xe cho các học viên.

Xuất hiện thư nặc danh dọa đặt bom sân bay Cam Ranh

Hữu Long |

Khánh Hòa – Công an xác định có một thư điện tử nặc danh với nội dung đe dọa đặt bom gửi đến sân bay Cam Ranh.

There is more than 700m left to clear the Van Ninh - Cam Lo expressway, when will it be finished?

HƯNG THƠ |

The remaining length that has not been cleared at Van Ninh - Cam Lo expressway in Quang Tri is 723m, the locality is determined to hand over before July 20, 2024.

Mất 8 năm giải phóng mặt bằng vành đai 1.800 tỉ đồng ở Hà Nội

HỮU CHÁNH |

Hà Nội - Đến tháng 2.2025, 6.000m2 mặt bằng còn lại sẽ được bàn giao để thi công hoàn thiện dự án Vành đai 3,5 (đoạn qua Hoài Đức) sau nhiều năm chậm trễ.

Những điểm nghẽn tại tuyến đường ven biển ở Quảng Bình

CÔNG SÁNG |

Tuyến đường ven biểnQuảng Bình triển khai từ đầu năm 2022, nhưng đến nay vẫn còn những điểm nghẽn, đặc biệt là việc giải phóng mặt bằng.