Red River bridge project in Hanoi: Another commune hands over sufficient land

SÓNG HỮU |

Hanoi - Phuc Tho commune has handed over 100% of the site to the investor of the Van Phuc bridge construction project and the road connecting to National Highway 32.

On January 29, Phuc Tho Commune People's Committee (Hanoi) had information on the progress of site clearance for the Van Phuc bridge construction investment project across the Red River and the road connecting to National Highway 32 section passing through the commune.

Phuc Tho Commune People's Committee said that this is a group A project, a level I project, of particular importance in the transport infrastructure development strategy of Hanoi Capital and neighboring provinces.

In which, the Van Phuc bridge project passes through Phuc Tho commune with a total length of 3.86km (the total area to be cleared in Phuc Tho commune is 21.29ha).

According to Hanoi's request, Phuc Tho commune must complete site clearance before January 31, 2026 to hand over to the investor, the Hanoi Traffic Works Project Management Board.

Clearly identifying the importance of the project, based on the direction of the City Party Committee and the City People's Committee, the Party Committee and People's Committee of Phuc Tho commune urgently focused on leading, directing, and mobilizing the involvement of the entire political system with the highest determination; ensuring unified, consistent, and timely leadership to remove difficulties and obstacles arising during the implementation process.

The Commune People's Committee proactively reviews and develops implementation plans according to specific timelines; clearly assigns people and responsibilities.

With a large volume of site clearance, while the implementation time is urgent, the project area has many specific characteristics, related to households and key civil works, the government identifies site clearance work as a key political task, requiring synchronous, drastic, flexible, and reasonable involvement.

Along with issuing specific plans and plans, the Commune People's Committee has organized direct dialogues with households whose land is recovered to publicly disclose information and clearly explain investment policies, regulations, and compensation and support policies in accordance with the law.

Not only stopping at focused meetings, the Commune People's Committee has actively coordinated with departments, branches, the Vietnam Fatherland Front Committee of the commune and directed relevant agencies and units to promote propaganda and mobilize households in many forms.

Thanks to the democratic, public, and transparent approach, the majority of households expressed their agreement and support for the project implementation policy. Many households were excited, voluntarily handed over the land and soon completed the procedures to receive compensation money.

By January 27, Phuc Tho Commune People's Committee had handed over 21.29ha/21.29ha of land to the investor - the City Traffic Works Project Management Board. In which, 100% of the land in Long Xuyen area with a total area of 14.25ha (including 136 households and 4 organizations) was handed over; 100% of the land in Phung Thuong area with a total area of 7.04ha (including 193 households and 1 organization) was handed over, exceeding the city's schedule.

According to Phuc Tho Commune People's Committee, the results were also thanks to the consensus and support of the people whose land is within the project area. Many households expressed excitement and confidence in the Party and State's policies, and were willing to receive compensation and support money and hand over the site on schedule.

SÓNG HỮU
RELATED NEWS

Hanoi is about to enforce land recovery for nearly 100 households for the 26.1 ha project

|

Hanoi - It is expected that on January 30, Thien Loc Commune People's Committee will organize land recovery enforcement for nearly 100 households to implement the G19 new urban area project, with an area of 26.1 ha.

4 key traffic projects to reduce congestion in Hanoi open to traffic before February 10

|

Hanoi is expected to open to traffic 4 key traffic projects including Ring Road 2.5, Giai Phong - Kim Dong underpass and National Highway 1 before the Lunar New Year 2026.

Forecast for tomorrow's gasoline and oil prices to increase sharply, increasing to a maximum of 3,220 VND/liter

|

It is predicted that gasoline and oil prices may increase sharply from 1,207 - 3,220 VND/liter in this week's price adjustment session.

Iranian ship attacked by submarine, at least 101 people missing

|

At least 101 people are missing after a submarine attacked an Iranian ship, the Sri Lankan navy reported.

Live football match between Vietnam women's team and India at the 2026 Women's Asian Cup

|

Live match between Vietnam women's team and India at the 2026 Women's Asian Cup, taking place at 6:00 PM today (March 4).

Stock market recovery

|

Vietnam's stock market reversed to increase points in the context of a volatile global financial market.

Ministry of Home Affairs denies rumors of merging 34 provinces and cities to 16 and arranging communes and wards

|

Representatives of the Ministry of Home Affairs said that there is currently no policy on continuing to arrange and merge provinces, cities and commune-level administrative units.

Da Nang voters trust in the qualifications and bravery of National Assembly Deputy candidates

|

Da Nang - Voters highly appreciate the qualifications and capacity of National Assembly candidates and expect elected delegates to pursue issues of concern to the people to the end.

Bãi trông xe trên đất dự án ở Tây Hồ: Mức xử phạt chỉ bằng 1/10 doanh thu

KHÁNH AN - SÓNG HỮU |

Hà Nội - Sau khi bị xử phạt, bãi trông xe trên đất dự án ở Tây Hồ vẫn tiếp tục hoạt động, bởi so với "doanh thu khủng", tiền phạt chỉ như "muối bỏ bể".

Hanoi is about to enforce land recovery for nearly 100 households for the 26.1 ha project

SÓNG HỮU |

Hanoi - It is expected that on January 30, Thien Loc Commune People's Committee will organize land recovery enforcement for nearly 100 households to implement the G19 new urban area project, with an area of 26.1 ha.

4 key traffic projects to reduce congestion in Hanoi open to traffic before February 10

Minh Hạnh |

Hanoi is expected to open to traffic 4 key traffic projects including Ring Road 2.5, Giai Phong - Kim Dong underpass and National Highway 1 before the Lunar New Year 2026.