Lao Cai - Hanoi - Hai Phong railway project through numbers

Đinh Đại |

Lao Cai - Site clearance and infrastructure preparation for the railway project are being simultaneously implemented by localities.

In early July, specialized units and local authorities are simultaneously deploying measurement, inventory, completing land acquisition dossiers and preparing ground to meet the progress of the Lao Cai - Hanoi - Hai Phong railway line.

The project has a length of about 391 km of main route and 28 km of branch route, passing through 6 provinces and cities. The preliminary total investment is about 203,000 billion VND (equivalent to 8.37 billion USD), implemented in 2 phases.

Phường Lào Cai là một trong những địa bàn có khối lượng giải phóng mặt bằng lớn của tuyến đường sắt. Ảnh: Đinh Đại
Lao Cai ward is one of the areas with a large volume of site clearance. Photo: Dinh Dai

As the starting point of the railway line, Lao Cai is focusing resources to synchronously implement tasks related to site clearance, construction of resettlement areas and connecting infrastructure.

In which, Lao Cai ward is one of the areas with a large volume of site clearance.

The project is expected to recover about 106 hectares of land, affecting 120 households and 56 businesses in residential groups No. 2, 4, 29 and Son Man 1 area.

Đẩy mạnh công tác tuyên truyền, tạo sự đồng thuận trong nhân dân. Ảnh: Đinh Đại
Localities meet, dialogue, and answer people's petitions. Photo: Dinh Dai

According to the plan, households subject to relocation will be arranged in the resettlement area of residential group No. 29, the resettlement area of road S5 belonging to the ground leveling and technical infrastructure project of Tan Lap urban area, along with the resettlement area of road S9 belonging to Sub-urban Area No. 6 and No. 7.

Lao Cai ward sets a goal to complete land acquisition, compensation, support, resettlement and site clearance in the fourth quarter of 2026 to hand over clean ground for construction.

Mặt bằng dự án thành phần đầu tư hạ tầng kết nối các ga và quảng trường ga đang được triển khai theo kế hoạch. Ảnh: Đinh Đại
Infrastructure investment component projects connecting stations and station squares are being implemented. Photo: Dinh Dai

Information from the People's Committee of Lao Cai province, the route section passing through the province is about 143.6 km long, passing through 12 communes and wards. The area of land recovery in the pre-feasibility phase is about 1,397ha, involving 6,694 households, with a total site clearance cost of about 8,200 billion VND.

To date, the locality has completed surveying the entire route according to the pre-feasibility study dossier; conducted statistics and inventory for 1,414 households, organized and issued land acquisition notices for 577 households.

For Component Project 1 on infrastructure investment connecting stations on the route and station squares, the province has handed over 7.46/7.9 ha of land to the Railway Project Management Board for construction deployment.

Các dự án tái định cư phục vụ người dân chuyển về. Ảnh: Đinh Đại
Resettlement projects serving people moving in. Photo: Dinh Dai

The bidding package is implemented by a consortium of Truong Son Construction Corporation, Vietnam Import-Export and Construction Corporation, FECON Joint Stock Company, Vietnam Railway Construction Corporation Joint Stock Company and Corporation 319 (Ministry of National Defense). Construction period from January 2026 to July 2027.

For component project 2, the province has received site clearance markers for 9 stations and technical operation stations to serve land recovery and deploy further steps.

In parallel with site clearance, resettlement work is also being accelerated. Out of a total of 38 resettlement areas planned to be built to serve the project, 28 areas have been started so far; the remaining 10 areas are completing investment procedures.

Lào Cai đặt mục tiêu hoàn thành công tác giải phóng mặt bằng để bàn giao mặt bằng sạch phục vụ thi công dự án. Ảnh: Đinh Đại
Part of the ground at Dong Pho Moi Industrial Park has been leveled. Photo: Dinh Dai

In addition, ground leveling projects to serve the relocation of production facilities are also being implemented synchronously. Currently, one project has been completed, and the remaining two projects are expected to be completed in the fourth quarter of 2026.

When completed, the railway line is expected to strengthen cargo and passenger transport capacity, connect Lao Cai international border gate with the Capital region and Hai Phong seaport, and expand the Kunming - Lao Cai - Hanoi - Hai Phong economic corridor.

Đinh Đại
RELATED NEWS

Lao Cai - Hanoi - Hai Phong Railway: Suddenly breaking down trade and tourism connections

|

Immediately after starting the simultaneous construction of 5 stations on the Lao Cai - Hanoi - Hai Phong railway line, the Prime Minister requested the Ministry of Construction and localities to urgently survey and design the remaining 16 stations to start construction in the first quarter of 2026. The acceleration of progress further affirms the value and importance of the project.

Starting construction of 16 Lao Cai - Hanoi - Hai Phong railway stations in the first quarter of 2026

|

The remaining 16 stations of the Lao Cai - Hanoi - Hai Phong railway line are being surveyed and designed to start construction in the first quarter of 2026.

People agree to donate land to the Lao Cai - Hanoi - Hai Phong railway project

|

Hai Phong - People in the communes in the West of Hai Phong agreed to donate land and coordinate with the authorities to implement the Lao Cai - Hanoi - Hai Phong railway project on schedule.

PNJ lost more than VND 2,260 billion in capitalization, what is noteworthy about the financial picture?

|

PNJ shares fell to the floor, causing the enterprise's capitalization to lose more than 2,260 billion VND. Regarding the business situation, PNJ recorded a picture with many bright spots.

Hero Ngo Thi Tuyen passed away at the age of 80

|

Thanh Hoa - Hero Ngo Thi Tuyen, who carried 2 boxes of ammunition heavier than twice her body weight during the anti-American resistance war, has passed away.

Bad news

|

Mr. Nguyen Dinh Hoe, born in 1935 (father of comrade Nguyen Dinh Chuc - Former Deputy Editor-in-Chief of Lao Dong Newspaper) passed away at 22:52 on July 3, 2026 (ie May 19, Binh Ngo year), at the age of 92.

Lao Cai - Hanoi - Hai Phong Railway: Suddenly breaking down trade and tourism connections

Nhóm phóng viên |

Immediately after starting the simultaneous construction of 5 stations on the Lao Cai - Hanoi - Hai Phong railway line, the Prime Minister requested the Ministry of Construction and localities to urgently survey and design the remaining 16 stations to start construction in the first quarter of 2026. The acceleration of progress further affirms the value and importance of the project.

Starting construction of 16 Lao Cai - Hanoi - Hai Phong railway stations in the first quarter of 2026

PHẠM ĐÔNG |

The remaining 16 stations of the Lao Cai - Hanoi - Hai Phong railway line are being surveyed and designed to start construction in the first quarter of 2026.

People agree to donate land to the Lao Cai - Hanoi - Hai Phong railway project

Mai Hương |

Hai Phong - People in the communes in the West of Hai Phong agreed to donate land and coordinate with the authorities to implement the Lao Cai - Hanoi - Hai Phong railway project on schedule.