Ring Road 2.5 Project: Issues that people with recovered land are concerned about

HỮU CHÁNH |

Hanoi - Proposals from people whose land is recovered to build Ring Road 2.5 mainly focus on land compensation prices, land support policies, resettlement...

Ring Road 2.5 project, Nguyen Trai section (National Highway 6) - Dam Hong (Khuong Dinh ward, Hanoi) has a length of 1,520m, cross-section scale of the roadbed 40m.

The project has a total investment of 2,433 billion VND, invested by Khuong Dinh Ward People's Committee.

According to the report of the Khuong Dinh Ward Investment - Infrastructure Project Management Board, the Ring Road 2.5 project passing through the ward has a total recovered area of more than 60,900 m2, involving 736 cases, including organizations and households, and individuals.

For 36 cases according to Decision No. 15/QD-UBND dated January 24, 2003, the plan was approved from the previous phase, the Ward People's Committee has promoted propaganda, mobilization and completed the demolition and handover of the site.

Khuong Dinh Ward People's Committee said that on the afternoon of February 27, the ward organized a conference to collect opinions from households and individuals on the draft plan for compensation, support, and resettlement when the State recovers a part of the land area to implement the investment project to build Ring Road 2.5 Nguyen Trai - Dam Hong section for 17 households and individuals belonging to residential group No. 13 (Thuong Dinh), group 1 (Khuong Dinh), group 1 (Ha Dinh), group 10A (Khuong Trung).

The conference is organized publicly and democratically to promptly inform and answer people's recommendations, creating consensus in the land clearance process.

At the conference, there were 8 opinions and recommendations from people mainly focusing on land compensation prices, land support policies, construction works, resettlement, other supports and population issues.

Representatives of professional departments and divisions directly exchanged and clarified the legal basis and policies applied according to the 2024 Land Law, decrees of the Government and regulations of the Hanoi People's Committee, thereby helping people understand their rights and obligations when the State recovers land.

A
Mr. Nguyen Sy Doan - Chairman of Khuong Dinh Ward People's Committee - delivered a directive speech at the conference. Photo: TTĐT Khuong Dinh Ward

Speaking to direct the conference, Mr. Nguyen Sy Doan - Chairman of Khuong Dinh Ward People's Committee - affirmed: Organizing the collection of people's opinions is an important step to ensure publicity and transparency, and at the same time show the receptiveness of grassroots authorities in the process of implementing key projects of the City.

The Ward People's Committee is committed to continuing to review and fully synthesize the opinions and legitimate recommendations of the people to report to competent authorities for consideration and adjustment of compensation, support, and resettlement plans in accordance with regulations and practice.

The conference took place in a frank and responsible atmosphere, contributing to creating consensus and high unity between the government and people, thereby promoting the progress of site clearance, early deployment of the Ring Road 2.5 project, meeting the requirements of developing transport infrastructure and urban embellishment in Khuong Dinh ward in particular and Hanoi city in general.

HỮU CHÁNH
RELATED NEWS

Ring Road 2.5 Project: Government and people exchange many contents on site clearance

|

Hanoi - During the Lunar New Year, Khuong Dinh ward still welcomes, listens to and answers people's petitions related to site clearance for the Ring Road 2.5 project.

Ring Road 2.5 Project: Organize site clearance throughout Tet, not to let people suffer disadvantages

|

Hanoi - Khuong Dinh Ward Compensation Council works throughout Tet to ensure the progress of the Ring Road 2.5 project, Nguyen Trai - Dam Hong section.

Hanoi technically opens underpass tunnel, Ring Road 2.5 nearly 2 million billion VND

|

Hanoi - The 2.5 Ring Road - National Highway 1A intersection underpass project and 1.6km of 2.5 Ring Road section Dam Hong - National Highway 1A technically opened to traffic this morning (February 10).

Fishermen hit big with tuna on the first sea trip of the year

|

Khanh Hoa - Tuna fishing vessels of fishermen dock at ports with holds full of seafood, bringing in large revenues.

Understanding taxes correctly: Business households need to "know" 5 important things when switching to declaration

|

Business households are required to memorize 5 things below when switching from fixed tax to declaration in 2026.

2026 weather forecast into the hottest heat group in 176 years

|

The latest weather forecast models show that 2026 may be in the group of 4 hottest years since 1850.

Gold price update morning of February 28: Suddenly soaring

|

Gold price update morning of February 28: World gold prices surge. Domestic market is likely to increase accordingly in the new trading session.

Russia has a lever of global influence stronger than oil and gas

|

Russia's oil and gas are subject to many sanctions, but nuclear energy is a different story.

Ring Road 2.5 Project: Government and people exchange many contents on site clearance

SÓNG HỮU |

Hanoi - During the Lunar New Year, Khuong Dinh ward still welcomes, listens to and answers people's petitions related to site clearance for the Ring Road 2.5 project.

Ring Road 2.5 Project: Organize site clearance throughout Tet, not to let people suffer disadvantages

SÓNG HỮU |

Hanoi - Khuong Dinh Ward Compensation Council works throughout Tet to ensure the progress of the Ring Road 2.5 project, Nguyen Trai - Dam Hong section.

Hanoi technically opens underpass tunnel, Ring Road 2.5 nearly 2 million billion VND

SÓNG HỮU |

Hanoi - The 2.5 Ring Road - National Highway 1A intersection underpass project and 1.6km of 2.5 Ring Road section Dam Hong - National Highway 1A technically opened to traffic this morning (February 10).