Ring Road 2.5 Project: Organize site clearance throughout Tet, not to let people suffer disadvantages

SÓNG HỮU |

Hanoi - Khuong Dinh Ward Compensation Council works throughout Tet to ensure the progress of the Ring Road 2.5 project, Nguyen Trai - Dam Hong section.

During the Binh Ngo Lunar New Year holiday, members of the Compensation, Support and Resettlement Council of Khuong Dinh Ward (Hanoi) still maintained working regimes to ensure the progress of the Ring Road 2.5 construction investment project, Nguyen Trai section (National Highway 6) to Dam Hong.

During this time, the Council members focused on reviewing and comparing legal documents, inventorying assets, completing and adjusting, supplementing the draft plan for compensation, support, and resettlement (which has been publicized) of the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, ensuring accuracy, publicity, transparency and compliance with legal regulations.

Working throughout the Lunar New Year shows a high sense of responsibility, determination to accelerate the progress of site clearance and minimize arising problems.

Mr. Nguyen Sy Doan, Chairman of Khuong Dinh Ward People's Committee, Chairman of the Compensation, Support and Resettlement Council, directly maintains the regime of being on duty, receiving citizens, listening to opinions, recommendations, and proposals related to the draft plan.

With a spirit of receptiveness, frankness and responsibility, Mr. Nguyen Sy Doan and the members of the Council exchanged specific contents that people are interested in such as: Determining the origin of land, recovered area, policies to support stable living, temporary housing rental support, as well as conditions and criteria for resettlement arrangement.

At citizen receptions, many opinions and recommendations were answered immediately based on current regulations and actual records. For cases that need further verification, the Council has assigned specialized officials to inspect and review all records, ensuring the legitimate and lawful rights and interests of the people. The general spirit is not to let errors occur, not to let people be disadvantaged, and at the same time ensure discipline and compliance with legal regulations.

Proactively working throughout Tet, directly dialoguing and exchanging with citizens has contributed to creating consensus and trust among the people, limiting prolonged petitions and lawsuits. Thereby, the progress of the Ring Road 2.5 project section passing through Khuong Dinh ward has been actively promoted, creating a premise for the project to be implemented soon according to plan.

In the coming time, the Compensation, Support and Resettlement Council of Khuong Dinh ward will continue to update and complete the plan based on people's contributions and actual review results; and at the same time strengthen propaganda, publicity, and transparency of information so that people understand the guidelines and policies, and join hands for the goal of synchronous and modern infrastructure development of the Capital.

The Ring Road 2.5 project, Nguyen Trai - Dam Hong section, has a length of 1,520m, a cross-section scale of 40m of roadbed. The project is invested by Khuong Dinh Ward People's Committee, with a total investment of 2,433 billion VND.

According to the report of the Khuong Dinh Ward Investment - Infrastructure Project Management Board, the Ring Road 2.5 project passing through the ward has a total recovered area of more than 60,900 m2, involving 736 cases, including organizations and households, and individuals.

For 36 cases according to Decision No. 15/QD-UBND dated January 24, 2003, the plan was approved from the previous phase, the Ward People's Committee has promoted propaganda, mobilization and completed the demolition and handover of the site.

SÓNG HỮU
RELATED NEWS

Hanoi technically opens underpass tunnel, Ring Road 2.5 nearly 2 million billion VND

|

Hanoi - The 2.5 Ring Road - National Highway 1A intersection underpass project and 1.6km of 2.5 Ring Road section Dam Hong - National Highway 1A technically opened to traffic this morning (February 10).

Ring Road 2.5 Project: Many recommendations on land acquisition and site clearance

|

Hanoi - Many households within the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, raised recommendations on land compensation prices, support policies, resettlement...

Ring Road 2.5: Consider adjusting compensation and resettlement plans

|

Hanoi - People's recommendations on the Ring Road 2.5 project will be reported to higher levels for consideration and adjustment of compensation plans in accordance with regulations and practice.

Village once buried by sand in Lao Cai puts on new clothes after storms and floods

|

Lao Cai - After the flood at the end of 2025 that buried Chut Village with sand, new houses have gradually appeared, bringing faith in a complete spring.

Ministry of Education announces university admission regulations for 2026

|

The Ministry of Education and Training has just announced the university admission regulations for 2026 with many new points related to the number of aspirations, academic records, IELTS scores,...

Before Tet, workers are paid a part of their salary by Phuc Hung Mechanical and Electrical Joint Stock Company

|

Before the 2026 Lunar New Year, some people whose salaries were owed by Phuc Hung Mechanical and Electrical Joint Stock Company were partially paid.

Hanoi Police at risk of being defeated in AFC Champions League

|

Hanoi Police may be defeated for violating player registration regulations at AFC Champions League Two.

Nearly 200 workers in Son La have received full salaries

|

Son La - Nearly 200 workers owed late construction costs for the Chieng Khoong Inter-level Boarding School Project have received full wages.

Hanoi technically opens underpass tunnel, Ring Road 2.5 nearly 2 million billion VND

SÓNG HỮU |

Hanoi - The 2.5 Ring Road - National Highway 1A intersection underpass project and 1.6km of 2.5 Ring Road section Dam Hong - National Highway 1A technically opened to traffic this morning (February 10).

Ring Road 2.5 Project: Many recommendations on land acquisition and site clearance

SÓNG HỮU |

Hanoi - Many households within the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, raised recommendations on land compensation prices, support policies, resettlement...

Ring Road 2.5: Consider adjusting compensation and resettlement plans

SÓNG HỮU |

Hanoi - People's recommendations on the Ring Road 2.5 project will be reported to higher levels for consideration and adjustment of compensation plans in accordance with regulations and practice.